Quantification of the State of Practice of Offsite Construction and Related Technologies: Current Trends and Future Prospects

Publication: Journal of Construction Engineering and Management
Volume 148, Issue 7

Abstract

Although some researchers and practitioners have perceived that the current reliance on offsite construction methods is high, other studies have hypothesized that the use of offsite construction techniques is still considered to be somehow limited. To this end, this paper aims to quantify the state of practice of offsite construction in terms of current trends and future prospects for the overall industry as well as the following main sectors: industrial, building and commercial, and infrastructure. First, a questionnaire was formed, pilot-tested, distributed, and completed by 100 construction practitioners. Second, the questionnaire’s internal and external validity and reliability were examined using statistical analysis. Third, the research findings were validated. The results showed that the future offsite construction operations will be different from the current operations by shifting from single-trade fabrication to modularization, shifting from customized offsite construction components to standardized offsite construction components, shifting from permanent offsite construction structures to relocatable or portable offsite construction structures, and shifting the reliance on single-skilled labor to multiskilled labor. In addition, 87% of industry practitioners perceive that the future offsite construction growth rate in the coming decade will be higher than that of the previous decade. This research also showed that offsite construction will become the norm rather than the exception because (1) the current average offsite construction percentage of 33.64% will substantially grow to reach an average of 54.9% in the future, (2) the offsite construction industry will grow 4.33 times, on average, in the coming decade, (3) companies are planning to increase their offsite construction utilization rate by an average of 5.03-fold, and (4) the offsite construction automation percentage will increase by 7% in the future. The research outcomes also provided guidance on the key technologies that the industry shall currently invest in and consider leveraging in the future.

Get full access to this article

View all available purchase options and get full access to this article.

Data Availability Statement

All data generated or analyzed during the study are included in the published article.

Acknowledgments

This research was collaboratively carried out by the authors through funding provided by the Construction Industry Institute (CII) at the Missouri University of Science and Technology, Purdue University, and the University of Arkansas under CII RT-371. To this end, the authors are very thankful for the financial and logistical support provided by CII. Also, the authors deeply appreciate and value the efforts and the insightful guidance provided by the CII RT-371 industry team members who offered a wealth of knowledge and real-world experience with exceptional dedication.

References

Abdul Nabi, M., and I. El-adaway. 2021. “Understanding the key risks affecting cost and schedule performance of modular construction projects.” J. Manage. Eng. 37 (4): 04021023. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000917.
Ahn, S., L. Crouch, T. W. Kim, and R. Rameezdeen. 2020. “Comparison of worker safety risks between onsite and offsite construction methods: A site management perspective.” J. Constr. Eng. Manage. 146 (9): 05020010. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001890.
Akofio-Sowah, M. A., R. Boadi, A. Amekudzi, and M. Meyer. 2014. “Managing ancillary transportation assets: The state of the practice.” J. Infrastruct. Syst. 20 (1): 04013010. https://doi.org/10.1061/(ASCE)IS.1943-555X.0000162.
Assaad, R., M. O. Ahmed, I. H. El-adaway, A. Elsayegh, and V. S. Siddhardh Nadendla. 2021. “Comparing the impact of learning in bidding decision-making processes using algorithmic game theory.” J. Manage. Eng. 37 (1): 04020099. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000867.
Assaad, R., and I. H. El-adaway. 2021. “Impact of dynamic workforce and workplace variables on the productivity of the construction industry: New gross construction productivity indicator.” J. Manage. Eng. 37 (1): 04020092. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000862.
Assaad, R., I. H. El-adaway, and I. S. Abotaleb. 2020a. “Predicting project performance in the construction industry.” J. Constr. Eng. Manage. 146 (5): 04020030. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001797.
Assaad, R., I. H. El-adaway, M. Hastak, and K. L. Needy. 2020b. “Commercial and legal considerations of offsite construction projects and their hybrid transactions.” J. Constr. Eng. Manage. 146 (12): 05020019. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001948.
Assaad, R., I. H. El-adaway, M. Hastak, and K. L. Needy. 2022. “The impact of offsite construction on the workforce: Required skillset and prioritization of training needs.” J. Constr. Eng. Manage. 175 (Feb): 121394.
Balasubramanian, N. 2012. “Likert technique of attitude scale construction in nursing research.” Asian J. Nursing Educ. Res. 2 (2): 22.
Baldwin, A., C.-S. Poon, L.-Y. Shen, S. Austin, and I. Wong. 2009. “Designing out waste in high-rise residential buildings: Analysis of precasting methods and traditional construction.” Renew. Energy 34 (9): 2067–2073.
Bayraktar, M. E., Q. Cui, M. Hastak, and I. Minkarah. 2004. “State-of-practice of warranty contracting in the United States.” J. Infrastruct. Syst. 10 (2): 60–68.
Bekdik, B. 2017. “Improving productivity in building construction—By repetitions in products, processes, and organisations.” Doctoral dissertation, Dept. of Management Engineering, Technical Univ. of Denmark.
Biggs, J. 2018. “Getting ahead of construction tech adoption challenges.” Accessed January 16, 2020. https://jobsite.procore.com/getting-ahead-of-construction-tech-adoption-challenges/.
Blismas, N., R. Wakefield, and B. Hauser. 2010. “Concrete prefabricated housing via advances in systems technologies: Development of a technology roadmap.” Eng. Constr. Archit. Manage. 17 (1): 99–110.
Boktor, J., A. Hanna, and C. C. Menassa. 2014. “State of practice of building information modeling in the mechanical construction industry.” J. Manage. Eng. 30 (1): 78–85.
Cho, K., S. Ahn, K. Park, and T. W. Kim. 2021. “Schedule delay leading indicators in precast concrete construction projects: Qualitative comparative analysis of Korean cases.” J. Manage. Eng. 37 (4): 04021024. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000915.
Choi, J. O. 2014. “Links between modularization critical success factors and project performance.” Doctoral dissertation, Dept. of Civil, Architectural, and Environmental Engineering, Univ. of Texas at Austin.
Choi, J. O., J. T. O’Connor, and T. W. Kim. 2016. “Recipes for cost and schedule successes in industrial modular projects: Qualitative comparative analysis.” J. Con. Eng. and Man. 142 (10): 04016055. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001171.
Choi, J. O., B. K. Shrestha, Y. H. Kwak, and J. S. Shane. 2020. “Innovative technologies and management approaches for facility design standardization and modularization of capital projects.” J. Manage. Eng. 36 (5): 04020042. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000805.
Christmann, A., and S. V. Aelst. 2006. “Robust estimation of Cronbach’s alpha.” J. Mult. Anal. 97 (7): 1660–1674.
Cicchetti, D. V., and S. A. Sparrow. 1981. “Developing criteria for establishing interrater reliability of specific items: Applications to assessment of adaptive behavior.” Am. J. Mental Deficiency 1981 (Jan): 1–9.
CII (Construction Industry Institute). 2021a. “CII research.” Accessed February 23, 2021. https://www.construction-institute.org/groups/standing-committees/funded-studies-committee/cii-research.
CII (Construction Industry Institute). 2021b. “Research programs.” Accessed February 23, 2021. https://www.construction-institute.org/groups/standing-committees/funded-studies-committee/research-programs.
Cochran, W. G. 1977. Sampling techniques. 3rd ed. New York: Wiley.
Collin, J. G. 2007. “US State-of-practice for the design of the geosynthetic reinforced load transfer platform in column supported embankments.” In Soil improvement, 1–12. Reston, VA: ASCE.
Connelly, L. M. 2008. “Pilot studies.” Medsurg Nursing 17 (6): 411.
Cooper, D. R., and P. S. Schindler. 2006. Business research methods. Boston: McGraw-Hill.
Dou, Y., X. Xue, C. Wu, X. Luo, and Y. Wang. 2020. “Interorganizational diffusion of prefabricated construction technology: Two-stage evolution framework.” J. Constr. Eng. Manage. 146 (9): 04020114. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001904.
Feghaly, J., M. El Asmar, and S. T. Ariaratnam. 2020. “State of professional practice for water infrastructure project delivery.” Pract. Period. Struct. Des. Constr. 25 (3): 04020018. https://doi.org/10.1061/(ASCE)SC.1943-5576.0000500.
Fish, J. 2019. “The future of construction will be changed by technology.” Accessed January 16, 2020. https://rew-online.com/2019/11/the-future-of-construction-will-be-changed-by-technology/.
FMI (Fails Management Institute). 2018. “New day, new mindset: Rethinking offsite construction.” Accessed November 17, 2019. https://www.fminet.com/special-reports/2018-fmi-curt-cii-owner-survey/.
Frost & Sullivan. 2019. “Global modular and prefabricated building market set for robust CAGR of 6.3% from 2018 to 2025.” Accessed February 24, 2021. https://ww2.frost.com/news/press-releases/global-modular-and-prefabricated-building-market-set-for-robust-cagr-of-6-3-from-2018-to-2025/.
Furbach, U., S. Hölldobler, M. Ragni, C. Schon, and F. Stolzenburg. 2019. “Cognitive reasoning: A personal view.” KI-Künstliche Intelligenz 33 (3): 209–217. https://doi.org/10.1007/s13218-019-00603-3.
Gosling, J., M. Pero, M. Schoenwitz, D. Towill, and R. Cigolini. 2016. “Defining and categorizing modules in building projects: An international perspective.” J. Constr. Eng. Manage. 142 (11): 04016062. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001181.
Hanna, A., F. Boodai, and M. El Asmar. 2013. “State of practice of building information modeling in mechanical and electrical construction industries.” J. Cons. Eng. Manage. 139 (10): 04013009. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000747.
Hanna, A. S., M. Yeutter, and D. G. Aoun. 2014. “State of practice of building information modeling in the electrical construction industry.” J. Cons. Eng. Manage. 140 (12): 05014011. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000893.
Hastak, M., and C. Koo. 2017. “Theory of an intelligent planning unit for the complex built environment.” J. Manage. Eng. 33 (3): 04016046. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000486.
Jaillon, L., and C. S. Poon. 2008. “Sustainable construction aspects of using prefabrication in dense urban environment: A Hong Kong case study.” Constr. Manage. Econ. 26 (9): 953–966.
JBKnowledge. 2018. “Construction technology report.” Accessed November 17, 2019. https://jbknowledge.com/2018-construction-technology-report-survey.
Jeanjean, P. 2012. “State of practice: Offshore geotechnics throughout the life of an oil and gas field.” In Geotechnical engineering state of the art and practice: Keynote lectures from GeoCongress 2012, 643–677. Reston, VA: ASCE.
Ji, W., S. M. AbouRizk, O. R. Zaïane, and Y. Li. 2018. “Complexity analysis approach for prefabricated construction products using uncertain data clustering.” J. Constr. Eng. Manage. 144 (8): 04018063. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001520.
Kelchner, L. 2021. “The advantages of multi-skilled labor.” Accessed February 24, 2021. https://smallbusiness.chron.com/advantages-multiskilled-labor-18280.html.
Koo, T. K., and M. Y. Li. 2016. “A guideline of selecting and reporting intraclass correlation coefficients for reliability research.” J. Chiropr. Med. 15 (2): 155–163. https://doi.org/10.1016/j.jcm.2016.02.012.
Lee, J., and H. Hyun. 2019. “Multiple modular building construction project scheduling using genetic algorithms.” J. Constr. Eng. Manage. 145 (1): 04018116. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001585.
Lee, Y., J. I. Kim, A. Khanzode, and M. Fischer. 2021. “Empirical study of identifying logistical problems in prefabricated interior wall panel construction.” J. Manage. Eng. 37 (3): 05021002. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000907.
Lerche, J., H. H. Neve, G. Ballard, J. Teizer, S. Wandahl, and A. Gross. 2020. “Application of last planner system to modular offshore wind construction.” J. Constr. Eng. Manage. 146 (11): 05020015. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001922.
Lessing, J., and S. Brege. 2018. “Industrialized building companies’ business models: Multiple case study of Swedish and North American companies.” J. Constr. Eng. Manage. 144 (2): 05017019. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001368.
Li, X., W. Lu, F. Xue, L. Wu, R. Zhao, J. Lou, and J. Xu. 2022. “Blockchain-enabled IoT-BIM platform for supply chain management in modular construction.” J. Constr. Eng. Manage. 148 (2): 04021195. https://doi.org/10.1061/(ASCE)CO.1943-7862.0002229.
Lim, I., J. Sawab, J. Wang, S. Fan, Y. L. Mo, and M. Li. 2021. “Characterization of ultrahigh-performance concrete materials for application in modular construction.” J. Mater. Civ. Eng. 33 (5): 04021087. https://doi.org/10.1061/(ASCE)MT.1943-5533.0003674.
Lima, R., D. F. de Noronha Osório, and H. Gamboa. 2019. “Heart rate variability and electrodermal activity in mental stress aloud: Predicting the outcome.” In Biosignals, 42–51. Hampshire, UK: Science and Technology Publications.
Limaye, P. 2019. “Modular market predicted to grow to $215 billion by 2025.” Accessed January 16, 2020. https://www.curt.org/modular-market-predicted-to-grow-to-215-billion-by-2025/.
Liu, L., and S. Ramakrishna. 2021. An introduction to circular economy. Berlin: Springer.
Loo, B. P. 2002. “Role of stated preference methods in planning for sustainable urban transportation: State of practice and future prospects.” J. Urban Plann. Dev. 128 (4): 210–224.
Lopes, G. C., R. Vicente, M. Azenha, and T. M. Ferreira. 2018. “A systematic review of prefabricated enclosure wall panel systems: Focus on technology driven for performance requirements.” Sustainable Cities Soc. 40 (8): 688–703.
Lu, N., 2009. “The current use of offsite construction techniques in the United States construction industry.” In Construction research congress 2009: Building a sustainable future, 946–955. Reston, VA: ASCE.
Market Research Future. 2017. “Modular construction market research report: Forecast to 2023.” Accessed February 1, 2021. https://www.marketresearchfuture.com/reports/modular-construction-market-1682.
McHugh, M. L. 2012. “Interrater reliability: The kappa statistic.” Biochem Med (Zagreb) 22 (3): 276–282.
Mehdizadeh, M. J., N. Shariatmadari, and M. Karimpour-Fard. 2020. “Probabilistic slope stability analysis in Kahrizak landfill: Effect of spatial variation of MSW’s geotechnical properties.” Bull. Eng. Geol. Environ. 79 (5): 2679–2695.
Modular Building Institute. 2021. “Relocatable buildings vs. permanent modular construction: What’s the difference?” Accessed February 24, 2021. https://www.modular.org/HtmlPage.aspx?name=MA-f-rb-v-pmc.
Munvar, C., D. G. Mengistu, and G. Mahesh. 2020. “Concurrent delay analysis: Methods, case law, and expert perception.” J. Leg. Aff. Dispute Resolut. Eng. Constr. 12 (1): 04519035. https://doi.org/10.1061/(ASCE)LA.1943-4170.0000343.
Nikolaou, S., J. E. Go, C. Z. Beyzaei, C. Moss, and P. W. Deming. 2012. “Geo-seismic design in the Eastern United States: State of practice.” In Geotechnical engineering state of the art and practice, 828–854. Reston, VA: ASCE.
O’Connor, J. T., W. J. O’Brien, and J. O. Choi. 2013. Industrial modularization how to optimize; how to maximize. Austin, TX: Univ. of Texas at Austin.
O’Connor, J. T., W. J. O’Brien, and J. O. Choi. 2014. “Critical success factors and enablers for optimum and maximum industrial modularization.” J. Cons. Eng. Manage. 140 (6): 04014012. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000842.
O’Connor, J. T., W. J. O’Brien, and J. O. Choi. 2015. “Standardization strategy for modular industrial plants.” J. Constr. Eng. Manage. 141 (9): 04015026. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001001.
O’Connor, J. T., W. J. O’Brien, and J. O. Choi. 2016. “Industrial project execution planning: Modularization versus stick-built.” Pract. Period. Struct. Des. Constr. 21 (1): 04015014. https://doi.org/10.1061/(ASCE)SC.1943-5576.0000270.
OECD (Organisation for Economic Co-Operation and Development). 2018. “Transformative technologies and jobs of the future.” Accessed November 17, 2019. https://www.oecd.org/innovation/transformative-technologies-and-jobs-of-the-future.pdf.
Pan, W., and C. K. Hon. 2020. “Briefing: Modular integrated construction for high-rise buildings.” In Vol. 173 of Proc., Institution of Civil Engineers—Municipal Engineer, 64–68. London: ICE Publishing.
Park, H. M., and H. W. Jung. 2003. “Evaluating interrater agreement with intraclass correlation coefficient in SPICE-based software process assessment.” In Proc., 3rd Int. Conf. on Quality Software, 308–314. New York: IEEE.
Pocock, J. B., S. T. Kuennen, J. Gambatese, and J. Rauschkolb. 2006. “Constructability state of practice report.” J. Constr. Eng. Manage. 132 (4): 373–383.
Ramaji, I. J., A. M. Memari, and J. I. Messner. 2017. “Product-oriented information delivery framework for multistory modular building projects.” J. Comput. Civ. Eng. 31 (4): 04017001. https://doi.org/10.1061/(ASCE)CP.1943-5487.0000649.
Randiwela, P., and S. T. Wijayaratne. 2017. “Determinants of perceived brand globalness: FMCG and airline services.” In Proc., Oxford Business and Economics Conf. 2017. Oxford, UK: Global Conference on Business & Economics.
Razkenari, M., A. Fenner, A. Shojaei, H. Hakim, and C. Kibert. 2020. “Perceptions of offsite construction in the United States: An investigation of current practices.” J. Build. Eng. 29 (3): 101138.
Robertson, O., and M. S. Evans. 2020. “Just how reliable is your internal reliability? An overview of Cronbach’s alpha (α).” In Psychology postgraduate affairs group. Glasgow, UK: PsyPAG.
Said, H. 2015. “Prefabrication best practices and improvement opportunities for electrical construction.” J. Constr. Eng. Manage. 141 (12): 04015045. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001018.
Schatsky, D., C. Muraskin, and R. Gurumurthy. 2015. Cognitive technologies: The real opportunities for business. New York: Deloitte University Press.
Sharafi, P., M. Rashidi, B. Samali, H. Ronagh, and M. Mortazavi. 2018. “Identification of factors and decision analysis of the level of modularization in building construction.” J. Archit. Eng. 24 (2): 04018010. https://doi.org/10.1061/(ASCE)AE.1943-5568.0000313.
Singh, A. S. 2017. “Common procedures for development, validity and reliability of a questionnaire.” Int. J. Econ. Commerce Manage. 5 (5): 790–801.
Slowey, K. 2019. “Report: 60% of US construction activity concentrated in 10 states.” Accessed December 2, 2021. https://www.constructiondive.com/news/report-60-of-us-construction-activity-concentrated-in-10-states/558524/.
Smith, R. E. 2016. Off-site and modular construction explained. Washington, DC: National Institute of Building Sciences.
Spring, G. S. 2005. “Road safety: discussion of state of practice.” J. Transp. Eng. 131 (5): 329–332.
Srour, F. J., I. Srour, and M. G. Lattouf. 2017. “A survey of absenteeism on construction sites.” Int. J. Manpower 38 (4): 533–547. https://doi.org/10.1108/IJM-08-2015-0135.
Steinhardt, D. A., K. Manley, and W. Miller. 2014. Predicting Australian builders’ intentions to use prefabrication. Brisbane, Australia: Queensland Univ. of Technology.
Taber, K. S. 2018. “The use of Cronbach’s alpha when developing and reporting research instruments in science education.” Res. Sci. Educ. 48 (6): 1273–1296. https://doi.org/10.1007/s11165-016-9602-2.
Tetteh, M. O., A. P. Chan, A. Darko, A. Torku, and G. Nani. 2021. “Critical barriers to international construction joint ventures success: Multiexpert views and contextual disparities.” J. Constr. Eng. Manage. 147 (8): 04021081. https://doi.org/10.1061/(ASCE)CO.1943-7862.0002059.
Tumbeva, M. D., A. P. Thrall, and T. P. Zoli. 2021. “Modular joint for the accelerated fabrication and erection of steel bridges.” J. Bridge Eng. 26 (6): 04021022. https://doi.org/10.1061/(ASCE)BE.1943-5592.0001706.
Vokes, C., and J. Brennan. 2013. Technology and skills in the construction industry. London: UK Commissions for Employment and Skills.
Watson, P. 2018. “There are two main barriers to the widespread use of offsite construction.” Accessed December 2, 2021. https://www.building.co.uk/comment/there-are-two-main-barriers-to-the-widespread-use-of-offsite-construction/5095454.article.
Wong, P. S., C. Zwar, and E. Gharaie. 2017. “Examining the drivers and states of organizational change for greater use of prefabrication in construction projects.” J. Constr. Eng. Manage. 143 (7): 04017020. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001309.
Yang, Y., M. Pan, W. Pan, and Z. Zhang. 2021. “Sources of uncertainties in offsite logistics of modular construction for high-rise building projects.” J. Manage. Eng. 37 (3): 04021011. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000905.
Yussef, A., G. E. Gibson, M. El Asmar, and D. Ramsey. 2020. “Industry survey for determining the state of practice of front end engineering design for industrial construction.” Pract. Periodical Struct. Des. Constr. 25 (4): 04020025. https://doi.org/10.1061/(ASCE)SC.1943-5576.0000504.
Zaalouk, A., and S. Han. 2021. “Parameterized design optimization framework for worker-friendly workplaces in modular construction.” J. Constr. Eng. Manage. 147 (5): 04021030. https://doi.org/10.1061/(ASCE)CO.1943-7862.0002029.

Information & Authors

Information

Published In

Go to Journal of Construction Engineering and Management
Journal of Construction Engineering and Management
Volume 148Issue 7July 2022

History

Received: Sep 14, 2021
Accepted: Mar 2, 2022
Published online: May 9, 2022
Published in print: Jul 1, 2022
Discussion open until: Oct 9, 2022

Permissions

Request permissions for this article.

Authors

Affiliations

Rayan H. Assaad, A.M.ASCE [email protected]
Assistant Professor of Construction and Civil Infrastructure, John A. Reif, Jr. Dept. of Civil and Environmental Engineering, New Jersey Institute of Technology, Newark, NJ 07102. Email: [email protected]
Hurst-McCarthy Professor of Construction Engineering and Management, Professor of Civil Engineering, and Founding Director of Missouri Consortium for Construction Innovation, Dept. of Civil, Architectural, and Environmental Engineering and Dept. of Engineering Management and Systems Engineering, Missouri Univ. of Science and Technology, Rolla, MO 65409 (corresponding author). ORCID: https://orcid.org/0000-0002-7306-6380. Email: [email protected]
Makarand Hastak, M.ASCE [email protected]
Dernlan Family Head and Professor, Div. of Construction Engineering and Management, Professor, Lyles School of Civil Engineering, Purdue Univ., West Lafayette, IN 47907. Email: [email protected]
Kim LaScola Needy [email protected]
Dean of the College of Engineering, Professor of Industrial Engineering, and Irma F. and Raymond F. Giffels Endowed Chair in Engineering, Univ. of Arkansas, 4183 Bell Engineering Center, Fayetteville, AR 72701. Email: [email protected]

Metrics & Citations

Metrics

Citations

Download citation

If you have the appropriate software installed, you can download article citation data to the citation manager of your choice. Simply select your manager software from the list below and click Download.

Cited by

  • Flexible Infrastructure Design: A Real Options Reasoning Approach to Navigating Uncertainty in Large-Scale Projects, Journal of Management in Engineering, 10.1061/JMENEA.MEENG-5678, 40, 3, (2024).
  • Skilled Worker Shortage across Key Labor-Intensive Construction Trades in Union versus Nonunion Environments, Journal of Management in Engineering, 10.1061/JMENEA.MEENG-5649, 40, 1, (2024).
  • Analyzing the Critical Success Factors Affecting Project Bundling Performance of Infrastructure Projects, Journal of Construction Engineering and Management, 10.1061/JCEMD4.COENG-14824, 150, 9, (2024).
  • Strategic Workforce Planning for Production of Prefabricated Bathroom Units: An Advanced Markovian Approach, Journal of Construction Engineering and Management, 10.1061/JCEMD4.COENG-14514, 150, 8, (2024).
  • Off-site construction in highways projects: management, technical, and technology perspectives from the United Kingdom, Construction Management and Economics, 10.1080/01446193.2023.2167218, (1-25), (2023).
  • Automated Generation of Horizontal Precast Slab Stacking Plans, Journal of Construction Engineering and Management, 10.1061/JCEMD4.COENG-13424, 149, 12, (2023).
  • Key Factors Affecting Labor Productivity in Offsite Construction Projects, Journal of Construction Engineering and Management, 10.1061/JCEMD4.COENG-12654, 149, 1, (2023).
  • Offsite Construction Methods—What We Learned from the UK Housing Sector, Infrastructures, 10.3390/infrastructures7120164, 7, 12, (164), (2022).
  • The COVID-19 Pandemic: A Catalyst and Accelerator for Offsite Construction Technologies, Journal of Management in Engineering, 10.1061/(ASCE)ME.1943-5479.0001091, 38, 6, (2022).

View Options

Get Access

Access content

Please select your options to get access

Log in/Register Log in via your institution (Shibboleth)
ASCE Members: Please log in to see member pricing

Purchase

Save for later Information on ASCE Library Cards
ASCE Library Cards let you download journal articles, proceedings papers, and available book chapters across the entire ASCE Library platform. ASCE Library Cards remain active for 24 months or until all downloads are used. Note: This content will be debited as one download at time of checkout.

Terms of Use: ASCE Library Cards are for individual, personal use only. Reselling, republishing, or forwarding the materials to libraries or reading rooms is prohibited.
ASCE Library Card (5 downloads)
$105.00
Add to cart
ASCE Library Card (20 downloads)
$280.00
Add to cart
Buy Single Article
$35.00
Add to cart

Get Access

Access content

Please select your options to get access

Log in/Register Log in via your institution (Shibboleth)
ASCE Members: Please log in to see member pricing

Purchase

Save for later Information on ASCE Library Cards
ASCE Library Cards let you download journal articles, proceedings papers, and available book chapters across the entire ASCE Library platform. ASCE Library Cards remain active for 24 months or until all downloads are used. Note: This content will be debited as one download at time of checkout.

Terms of Use: ASCE Library Cards are for individual, personal use only. Reselling, republishing, or forwarding the materials to libraries or reading rooms is prohibited.
ASCE Library Card (5 downloads)
$105.00
Add to cart
ASCE Library Card (20 downloads)
$280.00
Add to cart
Buy Single Article
$35.00
Add to cart

Media

Figures

Other

Tables

Share

Share

Copy the content Link

Share with email

Email a colleague

Share