Risk Propagation in Multilayer Heterogeneous Network of Coupled System of Large Engineering Project

This article has a reply.
VIEW THE REPLY
Publication: Journal of Management in Engineering
Volume 38, Issue 3

Abstract

Because of the long duration, multiplicity of technical disciplines, large number of project stakeholders, and high levels of complexity and uncertainty, project risk propagation control in large engineering projects (LEPs) is an enormous challenge for project managers. Although previous research has attained many risk propagation achievements regarding complex systems, complex coupled system modeling ignores the heterogeneity of the organizational structure of the actual LEPs, which affects the reliability of the calculated risk propagation results. To bridge this gap, this paper abstracts the LEP structure into a multilayer heterogeneous network comprising the stakeholder network and the project schedule network and proposes a method for characterizing the coupling relationship between two layers of the heterogeneous network. Then, the multiple uncertainties in risk propagation are greatly considered, and a risk propagation model is established based on the multilayer heterogeneous network and improved related schedule risk analysis model (CSRAM). Finally, the proposed model is applied to determine the delayed payment risk propagation in an actual LEP to verify the feasibility of the proposed model. The results indicate the following: (1) the delayed payment risk of a stakeholder evolves into a delay in the entire project; (2) several groups of comparative simulation experiments show that the proposed model, which considers multiple uncertainties and actual networks, includes more comprehensive and valuable risk information; (3) the multiple uncertainties of risk propagation are gradually superimposed with the increase in the number of construction activities affected by risk propagation; and (4) controlling for risk factors that have a high degree of influence and a large negative impact is an effective measure for blocking risk propagation across multilayer networks. This research lays an important foundation for risk propagation control in LEPs and contributes to the extension of the current theory of risk propagation in complex systems.

Get full access to this article

View all available purchase options and get full access to this article.

Data Availability Statement

All data, models, and code that support the findings of this study are available from the corresponding author upon reasonable request.

Acknowledgments

This study is sponsored by the National Natural Science Foundation of China (Grant Nos. 51779195, 51878385, and 52079073) and Open Foundation of the Hubei Key Laboratory of Construction and Management in Hydropower Engineering (Grant No. 2020KSD10).

References

Ahn, S., S. Shokri, S. Lee, C. T. Haas, and R. C. G. Haas. 2017. “Exploratory study on the effectiveness of interface-management practices in dealing with project complexity in large-scale engineering and construction projects.” J. Manage. Eng. 33 (2): 04016039. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000488.
Chen, L., Q. C. Lu, S. Li, W. J. He, and J. Yang. 2021. “Bayesian Monte Carlo simulation-driven approach for construction schedule risk inference.” J. Manage. Eng. 37 (2): 04020115. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000884.
Chen, Y., Z. G. Hu, and Q. Liu. 2019. “Exploring the properties of cost overrun risk propagation network (CORPN) for promoting cost management.” J. Civ. Eng. Manage. 25 (1): 1–18. https://doi.org/10.3846/jcem.2019.7462.
Chen, Y., Z. G. Hu, Q. Liu, and M. Y. Zhao. 2018. “Risk propagation of delayed payment in stakeholder network of large hydropower project construction considering risk resistance and mitigation.” Math. Prob. Eng. 2018 (Jan): 8013207. https://doi.org/10.1155/2018/8013207.
Cheng, Y. S., J. F. Yuan, L. Zhu, and W. Li. 2020. “Risk propagation model and simulation of schedule change in construction projects: A complex network approach.” Complexity. 8854609. https://doi.org/10.1155/2020/8854609.
Deng, X. Q., X. M. Yang, Y. Zhang, Y. S. Li, and Z. Lu. 2019. “Risk propagation mechanisms and risk management strategies for a sustainable perishable products supply chain.” Comput. Ind. Eng. 135 (Sep): 1175–1187. https://doi.org/10.1016/j.cie.2019.01.014.
Fang, C., and F. Marle. 2013. “Dealing with project complexity by matrix-based propagation modelling for project risk analysis.” J. Eng. Des. 24 (4): 239–256. https://doi.org/10.1080/09544828.2012.720014.
Fang, C., F. Marle, M. Xie, and E. Zio. 2013. “An integrated framework for risk response planning under resource constraints in large engineering projects.” IEEE Trans. Eng. Manage. 60 (3): 627–639. https://doi.org/10.1109/TEM.2013.2242078.
Fang, C., F. Marle, E. Zio, and J. C. Bocquet. 2012. “Network theory-based analysis of risk interactions in large engineering projects.” Reliab. Eng. Syst. Saf. 106 (Oct): 1–10. https://doi.org/10.1016/j.ress.2012.04.005.
Feng, J. C., Y. T. Wang, and K. Zhang. 2020. “Evaluation of the quality supervision system for construction projects in China considering the quality behavior risk transmission.” Symmetry-Basel 12 (10): 1660. https://doi.org/10.3390/sym12101660.
Hall, S. N., M. A. Gallagher, and D. S. Fenn. 2020. “Risk framework for an organizational system with major components.” Risk Anal. 40 (12): 2509–2523. https://doi.org/10.1111/risa.13572.
Khanzadi, M., E. Eshtehardian, and M. M. Esfahani. 2017. “Cash flow forecasting with risk consideration using Bayesian Belief Networks (BBNS).” J. Civ. Eng. Manage. 23 (8): 1045–1059. https://doi.org/10.3846/13923730.2017.1374303.
Kim, S., S. Chang, and D. Castro-Lacouture. 2020. “Dynamic modeling for analyzing impacts of skilled labor shortage on construction project management.” J. Manage. Eng. 36 (1): 04019035. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000720.
Lee, E., Y. Park, and J. G. Shin. 2009. “Large engineering project risk management using a Bayesian belief network.” Expert Syst. Appl. 36 (3): 5880–5887. https://doi.org/10.1016/j.eswa.2008.07.057.
Li, R. M., N. D. Yang, Y. L. Zhang, and H. Liu. 2020. “Risk propagation and mitigation of design change for complex product development (CPD) projects based on multilayer network theory.” Comput. Ind. Eng. 142 (Apr): 106370. https://doi.org/10.1016/j.cie.2020.106370.
Li, R. M., N. D. Yang, Y. L. Zhang, H. Liu, and M. Z. Zhang. 2021. “Impacts of module-module aligned patterns on risk cascading propagation in complex product development (CPD) interdependent networks.” Phys. A 564 (Feb): 125531. https://doi.org/10.1016/j.physa.2020.125531.
Li, Z. Y., X. T. Nie, B. Wang, and T. Y. Fan. 2019. “Analysis of the transmission of project duration and cost impacts based on the GERT network technique.” Symmetry-Basel 11 (3): 337. https://doi.org/10.3390/sym11030337.
Liu, H., N. D. Yang, Z. Yang, Y. L. Zhang, and J. H. Lin. 2019a. “Modeling and simulations of the cascading failure of multiple interdependent R&D networks under risk propagation.” Phys. Lett. A 383 (21): 2443–2450. https://doi.org/10.1016/j.physleta.2019.05.012.
Liu, H. Y., W. T. He, J. Guo, and Q. S. Huang. 2015. “Risk propagation mechanism: Qingdao crude oil leaking and explosion case study.” Eng. Fail. Anal. 56 (Oct): 555–561. https://doi.org/10.1016/j.engfailanal.2014.10.003.
Liu, M., H. Y. Chong, P. C. Liao, and L. Y. Xu. 2019b. “Probabilistic-based cascading failure approach to assessing workplace hazards affecting human error.” J. Manage. Eng. 35 (3): 04019006. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000690.
Liu, M., P. B. Tang, P. C. Liao, and L. Y. Xu. 2020. “Propagation mechanics from workplace hazards to human errors with dissipative structure theory.” Saf. Sci. 126 (Jun): 104661. https://doi.org/10.1016/j.ssci.2020.104661.
Luo, L. Z., G. Q. Shen, G. Y. Xu, Y. L. Liu, and Y. J. Wang. 2019. “Stakeholder-associated supply chain risks and their interactions in a prefabricated building project in Hong Kong.” J. Manage. Eng. 35 (2): 05018015. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000675.
Mahmoodzadeh, A., M. Mohammadi, H. H. Ibrahim, K. M. G. Noori, S. N. Abdulhamid, and H. F. H. Ali. 2021. “Forecasting sidewall displacement of underground caverns using machine learning techniques.” Autom. Constr. 123 (Mar): 103530. https://doi.org/10.1016/j.autcon.2020.103530.
Mousavi, S. M., R. Tavakkoli-Moghaddam, H. Hashemi, and S. M. H. Mojtahedi. 2011. “A novel approach based on non-parametric resampling with interval analysis for large engineering project risks.” Saf. Sci. 49 (10): 1340–1348. https://doi.org/10.1016/j.ssci.2011.05.004.
Ökmen, Ö., and A. Öztaş. 2008. “Construction project network evaluation with correlated schedule risk analysis model.” J. Constr. Eng. Manage. 134 (1): 49–63. https://doi.org/10.1061/(asce)0733-9364(2008)134:1(49).
Shahtaheri, M., C. T. Haas, and R. Rashedi. 2017. “Applying very large scale integration reliability theory for understanding the impacts of Type II risks on megaprojects.” J. Manage. Eng. 33 (4): 04017003. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000504.
Wang, Z., H. Yao, G. L. Yang, and J. Du. 2015. “Failure risk propagation and protection schemes in coupled systems.” Chaos Solitons Fractals 80 (Nov): 62–75. https://doi.org/10.1016/j.chaos.2015.06.005.
Yang, L., J. M. Lou, and X. B. Zhao. 2021. “Risk response of complex projects: Risk association network method.” J. Manage. Eng. 37 (4): 05021004. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000916.
Zhang, Y. T., C. H. Tsai, and P. C. Liao. 2020. “Rethinking risk propagation mechanism in public-private partnership projects: Network perspective.” J. Infrastruct. Syst. 26 (2): 04020011. https://doi.org/10.1061/(ASCE)IS.1943-555X.0000538.
Zhao, N. 2019. “Managing interactive collaborative mega project supply chains under infectious risks.” Int. J. Prod. Econ. 218 (Dec): 275–286. https://doi.org/10.1016/j.ijpe.2019.06.008.
Zhao, N., and T. C. E. Cheng. 2018. “A periodic collaboration and coexistence management model with the oscillation effect for complex mega infrastructure project under the risk of infection.” Complexity. 9846074. https://doi.org/10.1155/2018/9846074.
Zhong, D. H., S. R. Yang, H. T. Chang, J. Yu, and F. G. Yan. 2015. “Construction schedule risk analysis of high roller-compacted concrete dams based on improved CSRAM.” Sci. China Technol. Sci. 58 (6): 1021–1030. https://doi.org/10.1007/s11431-015-5781-8.
Zhou, Z. P., and J. Irizarry. 2016. “Integrated framework of modified accident energy release model and network theory to explore the full complexity of the Hangzhou subway construction collapse.” J. Manage. Eng. 32 (5): 05016013. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000431.

Information & Authors

Information

Published In

Go to Journal of Management in Engineering
Journal of Management in Engineering
Volume 38Issue 3May 2022

History

Received: Jul 20, 2021
Accepted: Nov 24, 2021
Published online: Jan 28, 2022
Published in print: May 1, 2022
Discussion open until: Jun 28, 2022

Permissions

Request permissions for this article.

ASCE Technical Topics:

Authors

Affiliations

Lecturer, Hubei Key Laboratory of Construction and Management in Hydropower Engineering, China Three Gorges Univ., Yichang 443002, China; Lecturer, College of Hydraulic and Environmental Engineering, China Three Gorges Univ., Yichang 443002, China (corresponding author). Email: [email protected]
Graduate Student, College of Hydraulic and Environmental Engineering, China Three Gorges Univ., Yichang 443002, China. Email: [email protected]
Professor, State Key Laboratory of Water Resources and Hydropower Engineering Science, Wuhan Univ., Wuhan 430072, China. Email: [email protected]
Associate Professor, Hubei Key Laboratory of Construction and Management in Hydropower Engineering, China Three Gorges Univ., Yichang 443002, China; Associate Professor, College of Hydraulic and Environmental Engineering, China Three Gorges Univ., Yichang 443002, China. Email: [email protected]
Xiazhong Zheng [email protected]
Professor, College of Hydraulic and Environmental Engineering, China Three Gorges Univ., Yichang 443002, China. Email: [email protected]

Metrics & Citations

Metrics

Citations

Download citation

If you have the appropriate software installed, you can download article citation data to the citation manager of your choice. Simply select your manager software from the list below and click Download.

Cited by

  • Collaborative Management Framework for Interorganizational Risk in Megaprojects Based on Metanetwork, Journal of Management in Engineering, 10.1061/JMENEA.MEENG-6073, 40, 5, (2024).
  • Combining Stakeholder and Risk Management: Multilayer Network Analysis for Complex Megaprojects, Journal of Construction Engineering and Management, 10.1061/JCEMD4.COENG-13807, 150, 2, (2024).
  • Cascading Failure Analysis of Causal Factors for Construction Collapse Accidents Based on Network Theory, Journal of Construction Engineering and Management, 10.1061/JCEMD4.COENG-13392, 150, 2, (2024).
  • Knowledge Graph Improved Dynamic Risk Analysis Method for Behavior-Based Safety Management on a Construction Site, Journal of Management in Engineering, 10.1061/JMENEA.MEENG-5306, 39, 4, (2023).
  • Understanding Causes for Construction Claims in Hydropower Projects, Journal of Management in Engineering, 10.1061/JMENEA.MEENG-5247, 39, 5, (2023).
  • Regional Sustainable Performance of Construction Industry in China from the Perspective of Input and Output: Considering Occupational Safety, Buildings, 10.3390/buildings12050618, 12, 5, (618), (2022).
  • Exploring the Barriers against Using Cryptocurrencies in Managing Construction Supply Chain Processes, Buildings, 10.3390/buildings12030357, 12, 3, (357), (2022).
  • Incorporating Project Complexities in Risk Assessment: Case of an Airport Expansion Construction Project, Journal of Management in Engineering, 10.1061/(ASCE)ME.1943-5479.0001099, 38, 6, (2022).
  • Managing Interdependence-Induced Systemic Risks in Infrastructure Projects, Journal of Management in Engineering, 10.1061/(ASCE)ME.1943-5479.0001071, 38, 5, (2022).

View Options

Get Access

Access content

Please select your options to get access

Log in/Register Log in via your institution (Shibboleth)
ASCE Members: Please log in to see member pricing

Purchase

Save for later Information on ASCE Library Cards
ASCE Library Cards let you download journal articles, proceedings papers, and available book chapters across the entire ASCE Library platform. ASCE Library Cards remain active for 24 months or until all downloads are used. Note: This content will be debited as one download at time of checkout.

Terms of Use: ASCE Library Cards are for individual, personal use only. Reselling, republishing, or forwarding the materials to libraries or reading rooms is prohibited.
ASCE Library Card (5 downloads)
$105.00
Add to cart
ASCE Library Card (20 downloads)
$280.00
Add to cart
Buy Single Article
$35.00
Add to cart

Get Access

Access content

Please select your options to get access

Log in/Register Log in via your institution (Shibboleth)
ASCE Members: Please log in to see member pricing

Purchase

Save for later Information on ASCE Library Cards
ASCE Library Cards let you download journal articles, proceedings papers, and available book chapters across the entire ASCE Library platform. ASCE Library Cards remain active for 24 months or until all downloads are used. Note: This content will be debited as one download at time of checkout.

Terms of Use: ASCE Library Cards are for individual, personal use only. Reselling, republishing, or forwarding the materials to libraries or reading rooms is prohibited.
ASCE Library Card (5 downloads)
$105.00
Add to cart
ASCE Library Card (20 downloads)
$280.00
Add to cart
Buy Single Article
$35.00
Add to cart

Media

Figures

Other

Tables

Share

Share

Copy the content Link

Share with email

Email a colleague

Share