Understanding Causes for Construction Claims in Hydropower Projects

Publication: Journal of Management in Engineering
Volume 39, Issue 5

Abstract

Hydropower project construction faces huge complexities and uncertainties. Construction claims are very likely to occur, creating losses to contractors and resulting in damage at project level such as breakdown in multiparty cooperation and delays in project completion. Previous studies tended to use subjective methods such as interviews and questionnaires to collect data for claim management research, and did not explore how causal factors interact and evolve to claims. This study aims to explore relationships among causal factors of construction claims (CFCCs), identify critical CFCCs, reveal direct and fundamental causes of claims, and tailor strategies to improve claim management. This work was based on 192 project cases collected from field investigations and academic and official sources; 58 CFCCs and 140 claim causation chains were extracted, forming CFCC networks. CFCCs (nodes) with high total degree and intermediary centrality values in the networks, such as schedule delay, cost increase, and increase of quantities were most critical. Preventing these factors will help eliminate claims. CFCCs with high out-degree values, such as client scope change, changes in construction conditions, construction interruption, and natural hazards, will cause more CFCCs and should therefore be particularly controlled. Besides, CFCCs with high clustering coefficients, such as influence of weather, design errors or omissions, inconsistency between drawings and bill of quantities, construction without advance payment from client, and insufficient site reconnaissance, need to be properly handled because their neighboring nodes can easily influence each other. It was also found that most CFCCs related to engineering influence would directly cause construction claims, and CFCCs pertaining to contractors’ behaviors and external risks tended to fundamentally contribute to construction claims in hydropower projects. The findings and management strategies of this study provide references for claims managers in practice, and are valuable for academics exploring claim management mechanisms in other types of projects.

Get full access to this article

View all available purchase options and get full access to this article.

Data Availability Statement

Some or all data, models, or code that support the findings of this study are available from the corresponding author upon reasonable request.

Acknowledgments

This work was supported by the Guangdong Basic and Applied Basic Research Foundation (Grant No. 2023A1515011433), the Shenzhen Natural Science Fund (the Stable Support Plan Program 20220810155553002), and the Yichang Natural Science Research Project (Grant No. A22-3-017).

References

Afzali, H. H. A., L. Bojke, and J. Karnon. 2018. “Model structuring for economic evaluations of new health technologies.” Pharmacoeconomics 36 (11): 1309–1319. https://doi.org/10.1007/s40273-018-0693-7.
Albert, R., and A. L. Barabási. 2002. “Statistical mechanics of complex networks.” Rev. Mod. Phys. 74 (1): 47–97. https://doi.org/10.1103/RevModPhys.74.47.
Ali, B., H. Zahoor, A. R. Nasir, A. Maqsoom, R. W. A. Khan, and K. M. Mazher. 2020. “BIM-based claims management system: A centralized information repository for extension of time claims.” Autom. Constr. 110 (Aug): 102937. https://doi.org/10.1016/j.autcon.2019.102937.
Alsuliman, J. A. 2019. “Causes of delay in Saudi public construction projects.” Alexandria Eng. J. 58 (2): 801–808. https://doi.org/10.1016/j.aej.2019.07.002.
Assaf, S., M. A. Hassanain, A. Abdallah, A. M. Z. Sayed, and A. Alshahrani. 2019. “Significant causes of claims and disputes in construction projects in Saudi Arabia.” Built Environ. Project Asset Manage. 9 (5): 597–615. https://doi.org/10.1108/BEPAM-09-2018-0113.
Assaf, S. A., and S. Al-Hejji. 2006. “Causes of delay in large construction projects.” Int. J. Project Manage. 24 (4): 349–357. https://doi.org/10.1016/j.ijproman.2005.11.010.
Attri, R., N. Dev, and V. Sharma. 2013. “Interpretive structural modelling (ISM) approach: An overview.” Res. J. Manage. Sci. 2 (2): 3–8.
Bai, J. S. 2006. Analysis of engineering claims and contract management in hydropower project construction. [In Chinese.] Beijing: China Water & Power Press.
Bakhary, N. A., H. Adnan, and A. Ibrahim. 2015. “A study of construction claim management problems in Malaysia.” Procedia Econ. Finance 23 (May): 63–70. https://doi.org/10.1016/S2212-5671(15)00327-5.
Carmichael, S., and M. Murray. 2006. “Record keeping for contemporaneous delay analysis: A model for effective event management.” Construct. Manage. Econ. 24 (10): 1007–1018. https://doi.org/10.1080/01446190500521207.
Charkhakan, M. H., and G. Heravi. 2019. “Evaluating the preventability of conflicts arising from change occurrence in construction projects.” Eng. Constr. Archit. Manage. 26 (8): 1777–1800. https://doi.org/10.1108/ECAM-09-2018-0361.
Chau, K. W. 2007. “Application of a PSO-based neural network in analysis of outcomes of construction claims.” Autom. Constr. 16 (5): 642–646. https://doi.org/10.1016/j.autcon.2006.11.008.
Chen, Y., S. Chen, C. Hu, L. Jin, and X. Zheng. 2020. “Novel probabilistic cost estimation model integrating risk allocation and claim in hydropower project.” J. Constr. Eng. Manage. 146 (8): 04020092. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001893.
Chen, Y., Z. Hu, and Q. Liu. 2019. “Exploring the properties of cost overrun risk propagation network (CORPN) for promoting cost management.” J. Civ. Eng. Manage. 25 (1): 1–18. https://doi.org/10.3846/jcem.2019.7462.
Chen, Y., L. Zhu, Z. Hu, S. Chen, and X. Zheng. 2022. “Risk propagation in multilayer heterogeneous network of coupled system of large engineering project.” J. Manage. Eng. 38 (3): 04022003. https://doi.org/10.1061/(ASCE)ME.1943-5479.0001022.
Cheung, S. O., K. Y. Li, and O. Y. Chow. 2020. “Reactive devaluation as a psychological impediment to construction dispute negotiation.” J. Manage. Eng. 36 (4): 04020025. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000787.
Elhag, T., S. Eapen, and T. Ballal. 2020. “Moderating claims and disputes through collaborative procurement.” Constr. Innovation 20 (1): 79–95. https://doi.org/10.1108/CI-02-2019-0020.
El-Sayegh, S., I. Ahmad, M. Aljanabi, R. Herzallah, S. Metry, and O. El-Ashwal. 2020. “Construction disputes in the UAE: Causes and resolution methods.” Buildings 10 (10): 171. https://doi.org/10.3390/buildings10100171.
Fang, C., F. Marle, E. Zio, and J. C. Bocquet. 2012. “Network theory-based analysis of risk interactions in large engineering projects.” Reliab. Eng. Syst. Saf. 106 (Oct): 1–10. https://doi.org/10.1016/j.ress.2012.04.005.
González, P., V. González, K. Molenaar, and F. Orozco. 2014. “Analysis of causes of delay and time performance in construction projects.” J. Constr. Eng. Manage. 140 (1): 04013027. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000721.
Guan, C., D. Dong, F. Shen, X. Gao, and L. Chen. 2022. “Hierarchical structure model of safety risk factors in new coastal towns: A systematic analysis using the DEMATEL-ISM-SNA method.” Int. J. Environ. Res. Public Health 19 (17): 10496. https://doi.org/10.3390/ijerph191710496.
Hayati, K., Y. Latief, and A. D. Rarasati. 2019. “Causes and problem identification in construction claim management.” IOP Conf. Ser.: Mater. Sci. Eng. 469 (1): 012082. https://doi.org/10.1088/1757-899X/469/1/012082.
Ismaila, U., W. Jung, and C. Y. Park. 2022. “Delay causes and types in Nigerian power construction projects.” Energies 15 (3): 814. https://doi.org/10.3390/en15030814.
Jagannathan, M., and V. S. K. Delhi. 2020. “Litigation in construction contracts: Literature review.” J. Leg. Aff. Dispute Resolut. Eng. Constr. 12 (1): 03119001. https://doi.org/10.1061/(ASCE)LA.1943-4170.0000342.
Kermanshachi, S., B. Rouhanizadeh, and B. Dao. 2020. “Application of Delphi method in identifying, ranking, and weighting project complexity indicators for construction projects.” J. Leg. Aff. Dispute Resolut. Eng. Constr. 12 (1): 04519033. https://doi.org/10.1061/(ASCE)LA.1943-4170.0000338.
Kikwasi, G. J. 2021. “Claims in construction projects: How causes are linked to effects?” J. Eng., Des. Technol. https://doi.org/10.1108/JEDT-06-2021-0312.
Kisi, K. P., N. Lee, R. Kayastha, and J. Kovel. 2020. “Alternative dispute resolution practices in international road construction contracts.” J. Leg. Aff. Dispute Resolut. Eng. Constr. 12 (2): 04520001. https://doi.org/10.1061/(ASCE)LA.1943-4170.0000373.
Kumar, R., K. C. Iyer, and S. P. Singh. 2021. “Understanding relationship between risks and claims for assessing risks with project data.” Eng. Constr. Archit. Manage. 28 (4): 1014–1037. https://doi.org/10.1108/ECAM-11-2019-0664.
Kumaraswamy, M. M. 1997. “Conflicts, claims and disputes in construction.” Eng. Constr. Archit. Manage. 4 (2): 95–111. https://doi.org/10.1108/eb021042.
Kumar Viswanathan, S., A. Panwar, S. Kar, R. Lavingiya, and K. N. Jha. 2020. “Causal modeling of disputes in construction projects.” J. Leg. Aff. Dispute Resolut. Eng. Constr. 12 (4): 04520035. https://doi.org/10.1061/(ASCE)LA.1943-4170.0000432.
Lee, J., Y. Ham, J. S. Yi, and J. Son. 2020. “Effective risk positioning through automated identification of missing contract conditions from the contractor’s perspective based on FIDIC contract cases.” J. Manage. Eng. 36 (3): 05020003. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000757.
Levin, P. 1998. Construction contract claims, changes & dispute resolution. Reston, VA: ASCE.
Li, Q., L. Song, G. F. List, Y. Deng, Z. Zhou, and P. Liu. 2017. “A new approach to understand metro operation safety by exploring metro operation hazard network (MOHN).” Saf. Sci. 93 (Aug): 50–61. https://doi.org/10.1016/j.ssci.2016.10.010.
Lin, S. C. 2015. “An analysis for construction engineering networks.” J. Constr. Eng. Manage. 141 (5): 04014096. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000956.
Love, P., P. Davis, J. Ellis, and S. O. Cheung. 2010. “Dispute causation: Identification of pathogenic influences in construction.” Eng. Constr. Archit. Manage. 17 (4): 404–423. https://doi.org/10.1108/09699981011056592.
Mahamid, I., A. Bruland, and N. Dmaidi. 2012. “Causes of delay in road construction projects.” J. Manage. Eng. 28 (3): 300–310. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000096.
Mashwama, X. N., C. Aigbavboa, and D. Thwala. 2016. “Investigation of construction stakeholders’ perception on the effects & cost of construction dispute in Swaziland.” Procedia Eng. 164 (Sep): 196–205. https://doi.org/10.1016/j.proeng.2016.11.610.
Mehany, M. S. H. M., and N. Grigg. 2015. “Causes of road and bridge construction claims: Analysis of Colorado department of transportation projects.” J. Leg. Aff. Dispute Resolut. Eng. Constr. 7 (2): 04514006. https://doi.org/10.1061/(ASCE)LA.1943-4170.0000162.
Mishmish, M., and S. M. El-Sayegh. 2018. “Causes of claims in road construction projects in the UAE.” Int. J. Construct. Manage. 18 (1): 26–33. https://doi.org/10.1080/15623599.2016.1230959.
Muhsen, H. K., and S. E. Rezouki. 2022. “The causes influencing the occurrence of variation orders in the construction of buildings.” J. Eng. 28 (8): 34–53. https://doi.org/10.31026/j.eng.2022.08.03.
Nabi, M. A., and I. H. El-adaway. 2021. “Understanding the key risks affecting cost and schedule performance of modular construction projects.” J. Manage. Eng. 37 (4): 04021023. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000917.
Naji, K. K., M. Gunduz, and A. F. Naser. 2022. “An adaptive neurofuzzy inference system for the assessment of change order management performance in construction.” J. Manage. Eng. 38 (2): 04021098. https://doi.org/10.1061/(ASCE)ME.1943-5479.0001017.
Parchami Jalal, M., E. Noorzai, and T. Yavari Roushan. 2019. “Root cause analysis of the most frequent claims in the building industry through the SCoP3E Ishikawa diagram.” J. Leg. Aff. Dispute Resolut. Eng. Constr. 11 (2): 04519004. https://doi.org/10.1061/(ASCE)LA.1943-4170.0000289.
Parvaneh, S., M. Akbar, and P. Majid. 2018. “Causes of delays in construction industry and comparative delay analysis techniques with SCL protocol.” Eng. Constr. Archit. Manage. 25 (4): 497–533. https://doi.org/10.1108/ECAM-10-2016-0220.
Prasad, K. V., V. Vasugi, R. Venkatesan, and N. Bhat. 2019. “Analysis of causes of delay in Indian construction projects and mitigation measures.” J. Financ. Manage. Property Constr. 24 (1): 58–78. https://doi.org/10.1108/JFMPC-04-2018-0020.
Ramachandra, T., and J. O. B. Rotimi. 2015. “Mitigating payment problems in the construction industry through analysis of construction payment disputes.” J. Leg. Aff. Dispute Resolut. Eng. Constr. 7 (1): A4514005. https://doi.org/10.1061/(ASCE)LA.1943-4170.0000156.
Seo, W., and Y. Kang. 2020. “Performance indicators for the claim management of general contractors.” J. Manage. Eng. 36 (6): 04020070. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000835.
Seo, W., Y. H. Kwak, and Y. Kang. 2021. “Relationship between consistency and performance in the claim management process for construction projects.” J. Manage. Eng. 37 (6): 04021068. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000973.
Shaikh, H. H., N. Y. Zainun, and S. H. Khahro. 2020a. “Claims in construction projects: A comprehensive literature review.” IOP Conf. Ser.: Earth Environ. Sci. 498 (1): 012095. https://doi.org/10.1088/1755-1315/498/1/012095.
Shaikh, H. H., N. Y. Zainun, S. H. Khahro, and T. H. Ali. 2020b. “Timely identification of claims in construction industry: A blessing in disguise.” Int. J. Adv. Sci. Technol. 29 (9s): 7050–7056.
Shakeri, H., and M. Khalilzadeh. 2020. “Analysis of factors affecting project communications with a hybrid DEMATEL-ISM approach (A case study in Iran).” Heliyon 6 (8): e04430. https://doi.org/10.1016/j.heliyon.2020.e04430.
Shen, W., W. Tang, W. Yu, C. F. Duffield, F. K. P. Hui, Y. Wei, and J. Fang. 2017. “Causes of contractors’ claims in international engineering-procurement-construction projects.” J. Civ. Eng. Manage. 23 (6): 727–739. https://doi.org/10.3846/13923730.2017.1281839.
Soomro, M. A., and X. Zhang. 2015. “Roles of private-sector partners in transportation public-private partnership failures.” J. Manage. Eng. 31 (4): 04014056. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000263.
Tan, T., K. Chen, F. Xue, and W. Lu. 2019. “Barriers to building information modeling (BIM) implementation in China’s prefabricated construction: An interpretive structural modeling (ISM) approach.” J. Cleaner Prod. 219 (May): 949–959. https://doi.org/10.1016/j.jclepro.2019.02.141.
Thomas, R., and M. Wright. 2020. Construction contract claims. London: Bloomsbury Publishing.
Zaneldin, E. K. 2006. “Construction claims in United Arab Emirates: Types, causes, and frequency.” Int. J. Project Manage. 24 (5): 453–459. https://doi.org/10.1016/j.ijproman.2006.02.006.
Zaneldin, E. K. 2018. “Investigating the types, causes and severity of claims in construction projects in the UAE.” Int. J. Construct. Manage. 20 (5): 385–401. https://doi.org/10.1080/15623599.2018.1484863.
Zhou, Z., J. Irizarry, and Q. Li. 2014. “Using network theory to explore the complexity of subway construction accident network (SCAN) for promoting safety management.” Saf. Sci. 64 (May): 127–136. https://doi.org/10.1016/j.ssci.2013.11.029.

Information & Authors

Information

Published In

Go to Journal of Management in Engineering
Journal of Management in Engineering
Volume 39Issue 5September 2023

History

Received: Aug 23, 2022
Accepted: May 11, 2023
Published online: Jul 4, 2023
Published in print: Sep 1, 2023
Discussion open until: Dec 4, 2023

Permissions

Request permissions for this article.

ASCE Technical Topics:

Authors

Affiliations

Longhui Liao [email protected]
Assistant Professor, Key Laboratory for Resilient Infrastructures of Coastal Cities, Ministry of Education, Shenzhen Univ., Shenzhen 518060, China. Email: [email protected]
Graduate Student, Key Laboratory for Resilient Infrastructures of Coastal Cities, Ministry of Education, Shenzhen Univ., Shenzhen 518060, China. Email: [email protected]
Chuchu Zheng [email protected]
Engineer, Performance Support Center, Power China Huadong Engineering Corporation Limited, Hangzhou 310000, China. Email: [email protected]
Graduate Student, Key Laboratory for Resilient Infrastructures of Coastal Cities, Ministry of Education, Shenzhen Univ., Shenzhen 518060, China. Email: [email protected]
Lecturer, College of Hydraulic & Environmental Engineering, China Three Gorges Univ., Yichang 443002, China (corresponding author). Email: [email protected]

Metrics & Citations

Metrics

Citations

Download citation

If you have the appropriate software installed, you can download article citation data to the citation manager of your choice. Simply select your manager software from the list below and click Download.

Cited by

  • Investigating Causes of Disputes Resulting in Litigation in Airport Development Projects in the United States Using Graph-Based Techniques, Journal of Management in Engineering, 10.1061/JMENEA.MEENG-5903, 40, 3, (2024).
  • A Classification Model Using Personal Biometric Characteristics to Identify Individuals Vulnerable to an Extremely Hot Environment, Journal of Management in Engineering, 10.1061/JMENEA.MEENG-5495, 40, 2, (2024).

View Options

Get Access

Access content

Please select your options to get access

Log in/Register Log in via your institution (Shibboleth)
ASCE Members: Please log in to see member pricing

Purchase

Save for later Information on ASCE Library Cards
ASCE Library Cards let you download journal articles, proceedings papers, and available book chapters across the entire ASCE Library platform. ASCE Library Cards remain active for 24 months or until all downloads are used. Note: This content will be debited as one download at time of checkout.

Terms of Use: ASCE Library Cards are for individual, personal use only. Reselling, republishing, or forwarding the materials to libraries or reading rooms is prohibited.
ASCE Library Card (5 downloads)
$105.00
Add to cart
ASCE Library Card (20 downloads)
$280.00
Add to cart
Buy Single Article
$35.00
Add to cart

Get Access

Access content

Please select your options to get access

Log in/Register Log in via your institution (Shibboleth)
ASCE Members: Please log in to see member pricing

Purchase

Save for later Information on ASCE Library Cards
ASCE Library Cards let you download journal articles, proceedings papers, and available book chapters across the entire ASCE Library platform. ASCE Library Cards remain active for 24 months or until all downloads are used. Note: This content will be debited as one download at time of checkout.

Terms of Use: ASCE Library Cards are for individual, personal use only. Reselling, republishing, or forwarding the materials to libraries or reading rooms is prohibited.
ASCE Library Card (5 downloads)
$105.00
Add to cart
ASCE Library Card (20 downloads)
$280.00
Add to cart
Buy Single Article
$35.00
Add to cart

Media

Figures

Other

Tables

Share

Share

Copy the content Link

Share with email

Email a colleague

Share