Abstract

Construction industrialization (CI) has dramatically altered how architecture, engineering, and construction (AEC) companies design, manufacture, build, operate, and manage. Despite its growing relevance in both academia and companies in the last decades, the CI field has, however, been considered unclear, fragmented, and with a high level of misunderstandings. To address this knowledge gap through a systematic literature review, this paper provides a holistic and comprehensive conceptualization of the phenomenon and its theoretical basis for the global engineering and construction management community. In total, 102 articles from the last 11 years (2010–2021) from the Scopus and Web of Science databases were collected and analyzed. So, one primary contribution of this paper is the establishment of a definition for the CI concept. Another important contribution is the definition of a conceptual framework that introduces industrialization as a new way of operating the business, where five major dimensions, namely strategy, organization, business processes, supply chain planning, and resources, need to be aligned and managed simultaneously for competitive advantage. Furthermore, 10 design principles, five influencing factors, and 19 initiatives are presented to provide an integrated and holistic view of the concept. This article gives businesses a better knowledge of what industrialization in the construction industry actually means, enabling them to move forward with this transformation. Finally, the research provides a basis for improving future contributions in CI and adjacent management disciplines.

Practical Applications

CI has emerged as a dramatic change in the way construction companies operate. However, there is still much of uncertainty about what this transformation really means and what it encompasses. These are the main questions that, through a systematic literature review, this paper seeks to answer. As a first contribution, this paper presents a definition of CI. Furthermore, the paper also reinforces that industrialization is a new way of managing and producing where five major dimensions have to be handled simultaneously to achieve competitive advantage: strategy, organization, business processes, supply chain planning, and resources. Along with this contextualization, 10 design principles, five influencing factors, and 19 initiatives are also presented in a framework that assists in defining and representing the phenomenon. This article enables companies to take a step forward in this transformation by providing a greater understanding of what industrialization actually means in the construction sector. The contributions of this research are also targeted to managers and researchers with expertise in the fields of industrial engineering and management who want to contribute to bridge the gap between construction and management. Finally, this article also provides new guidelines for further contributions in the field of CI research.

Get full access to this article

View all available purchase options and get full access to this article.

Data Availability Statement

No data, models, or code were generated or used during the study.

References

Altaf, M. S., A. Bouferguene, H. Liu, M. Al-Hussein, and H. Yu. 2018. “Integrated production planning and control system for a panelized home prefabrication facility using simulation and RFID.” Autom. Constr. 85 (Feb): 369–383. https://doi.org/10.1016/j.autcon.2017.09.009.
Arashpour, M., Y. Bai, G. Aranda-mena, A. Bab-Hadiashar, R. Hosseini, and P. Kalutara. 2017. “Optimizing decisions in advanced manufacturing of prefabricated products: Theorizing supply chain configurations in off-site construction.” Autom. Constr. 84 (Sep): 146–153. https://doi.org/10.1016/j.autcon.2017.08.032.
Arashpour, M., R. Wakefield, B. Abbasi, M. Arashpour, and R. Hosseini. 2018. “Optimal process integration architectures in off-site construction: Theorizing the use of multi-skilled resources.” Archit. Eng. Des. Manage. 14 (1–2): 46–59. https://doi.org/10.1080/17452007.2017.1302406.
Arashpour, M., R. Wakefield, B. Abbasi, E. W. M. Lee, and J. Minas. 2016. “Off-site construction optimization: Sequencing multiple job classes with time constraints.” Autom. Constr. 71 (Part 2): 262–270. https://doi.org/10.1016/j.autcon.2016.08.001.
Arif, M., and C. Egbu. 2010. “Making a case for offsite construction in China.” Eng. Constr. Archit. Manage. 17 (6): 536–548. https://doi.org/10.1108/09699981011090170.
Arif, M., J. Goulding, and F. P. Rahimian. 2012. “Promoting off-site construction: Future challenges and opportunities.” J. Archit. Eng. 18 (2): 75–78. https://doi.org/10.1061/(ASCE)AE.1943-5568.0000081.
Ayinla, K. O., F. Cheung, and A. R. Tawil. 2019. “Demystifying the concept of offsite manufacturing method: Towards a robust definition and classification system.” Constr. Innovation 20 (2): 223–246. https://doi.org/10.1108/CI-07-2019-0064.
Balaguer, C., M. Abderrahim, J. M. Navarro, S. Boudjabeur, S. Slavenburg, D. Seward, T. Bock, R. Wing, and B. Atkin. 2002. “FutureHome: An integrated construction automation approach.” IEEE Robot. Autom. Mag. 9 (1): 55–66. https://doi.org/10.1109/100.993155.
Bendi, D., M. Q. Rana, M. Arif, J. S. Goulding, and A. Sawhney. 2020. “An off-site construction readiness maturity model for the Indian construction sector.” Constr. Innovation 21 (1): 1471–4175. https://doi.org/10.1108/CI-07-2020-0121.
Bildsten, L. 2014. “Buyer-supplier relationships in industrialized building.” Construct. Manage. Econ. 32 (1–2): 146–159. https://doi.org/10.1080/01446193.2013.812228.
Bortolini, R., C. T. Formoso, and D. D. Viana. 2019. “Site logistics planning and control for engineer-to-order prefabricated building systems using BIM 4D modeling.” Autom. Constr. 98 (Nov): 248–264. https://doi.org/10.1016/j.autcon.2018.11.031.
Brege, S., L. Stehn, and T. Nord. 2014. “Business models in industrialized building of multi-storey houses.” Construct. Manage. Econ. 32 (1–2): 208–226. https://doi.org/10.1080/01446193.2013.840734.
Bueno, A., M. Godinho Filho, and A. G. Frank. 2020. “Smart production planning and control in the Industry 4.0 context: A systematic literature review.” Comput. Ind. Eng. 149 (Aug): 106774. https://doi.org/10.1016/j.cie.2020.106774.
Burgess, K., P. J. Singh, and R. Koroglu. 2006. “Supply chain management: A structured literature review and implications for future research.” Int. J. Oper. Prod. Manage. 26 (7): 703–729. https://doi.org/10.1108/01443570610672202.
Choi, J. O., J. T. O’Connor, Y. H. Kwak, and B. K. Shrestha. 2019. “Modularization business case analysis model for industrial projects.” J. Manage. Eng. 35 (3): 04019004. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000683.
Correia, J., M. Sutrisna, and A. Zaman. 2020. “Factors influencing the implementation of off-site manufacturing in commercial projects in Western Australia: A proposed research agenda.” J. Eng. Des. Technol. 18 (6): 1449–1468. https://doi.org/10.1108/JEDT-09-2019-0246.
Čuš-Babič, N., P. Podbreznik, and D. Rebolj. 2010. “Integrating resource production and construction using BIM.” Autom. Constr. 19 (5): 539–543. https://doi.org/10.1016/j.autcon.2009.11.005.
Čuš-Babič, N., D. Rebolj, M. Nekrep-Perc, and P. Podbreznik. 2014. “Supply-chain transparency within industrialized construction projects.” Comput. Ind. 65 (2): 345–353. https://doi.org/10.1016/j.compind.2013.12.003.
Dallasega, P. 2018. “Industry 4.0 fostering construction supply chain management: Lessons learned from engineer-to-order suppliers.” IEEE Eng. Manage. Rev. 46 (3): 49–55. https://doi.org/10.1109/EMR.2018.2861389.
Das, P., S. Perera, S. Senaratne, and R. Osei-Keyi. 2020. “Developing a construction business model transformation canvas.” Constr. Archit. Manage. 28 (5): 1423–1439. https://doi.org/10.1108/ECAM-09-2020-0712.
Doran, D., and M. Giannakis. 2011. “An examination of a modular supply chain: A construction sector perspective.” Supply Chain Manage. 16 (4): 260–270. https://doi.org/10.1108/13598541111139071.
Du, J., H. Jing, K. K. R. Choo, V. Sugumaran, and D. Castro-Lacouture. 2020. “An ontology and multi-agent based decision support framework for prefabricated component supply chain.” Inf. Syst. Front. 22 (6): 1467–1485. https://doi.org/10.1007/s10796-019-09941-x.
Durdyev, S., and S. Ismail. 2019. “Offsite manufacturing in the construction industry for productivity improvement.” Eng. Manage. J. 31 (1): 35–46. https://doi.org/10.1080/10429247.2018.1522566.
Ekanayake, E. M. A. C., G. Q. Shen, and M. M. M. Kumaraswamy. 2020. “Identifying supply chain capabilities of construction firms in industrialized construction.” Prod. Plann. Control 32 (4): 303–321. https://doi.org/10.1080/09537287.2020.1732494.
Eriksson, P. E., S. Olander, H. Szentes, and K. Widén. 2014. “Managing short-term efficiency and long-term development through industrialized construction.” Construct. Manage. Econ. 32 (1–2): 97–108. https://doi.org/10.1080/01446193.2013.814920.
Fargnoli, M., and M. Lombardi. 2020. “Building information modelling (BIM) to enhance occupational safety in construction activities: Research trends emerging from one decade of studies.” Buildings 10 (6): 98. https://doi.org/10.3390/buildings10060098.
Gan, X., R. Chang, J. Zuo, T. Wen, and G. Zillante. 2018. “Barriers to the transition towards off-site construction in China: An interpretive structural modeling approach.” J. Cleaner Prod. 197 (Mar): 8–18. https://doi.org/10.1016/j.jclepro.2018.06.184.
Gao, S., R. Jin, and W. Lu. 2020. “Design for manufacture and assembly in construction: A review.” Build. Res. Inf. 48 (5): 538–550. https://doi.org/10.1080/09613218.2019.1660608.
García de Soto, B., I. Agustí-Juan, J. Hunhevicz, S. Joss, K. Graser, G. Habert, and B. T. B. Adey. 2018. “Productivity of digital fabrication in construction: Cost and time analysis of a robotically built wall.” Autom. Constr. 92 (Aug): 297–311. https://doi.org/10.1016/j.autcon.2018.04.004.
Gbadamosi, A.-Q., A. M. Mahamadu, L. O. Oyedele, O. Akinade, P. Manu, L. Mahdjoubi, and C. Aigbavboa. 2019. “Offsite construction: Developing a BIM-Based optimizer for assembly.” J. Cleaner Prod. 215 (Apr): 1180–1190. https://doi.org/10.1016/j.jclepro.2019.01.113.
Ghadge, A., H. Wurtmann, and S. Seuring. 2020. “Managing climate change risks in global supply chains: A review and research agenda.” Int. J. Prod. Res. 58 (1): 44–64. https://doi.org/10.1080/00207543.2019.1629670.
Girmscheid, G., and T. Rinas. 2012. “Business design modeling for industrialization in construction: Cooperative approach.” J. Archit. Eng. 18 (2): 164–175. https://doi.org/10.1061/(ASCE)AE.1943-5568.0000089.
Goulding, J. S., F. Pour Rahimian, M. Arif, and M. D. Sharp. 2015. “New offsite production and business models in construction: Priorities for the future research agenda.” Archit. Eng. Des. Manage. 11 (3): 163–184. https://doi.org/10.1080/17452007.2014.891501.
Hall, D. M., J. K. Whyte, and J. Lessing. 2020. “Mirror-breaking strategies to enable digital manufacturing in Silicon Valley construction firms: A comparative case study.” Construct. Manage. Econ. 38 (4): 322–339. https://doi.org/10.1080/01446193.2019.1656814.
Hammad, A., A. Akbarnezhad, P. Wu, X. Wang, and A. Haddad. 2019. “Building information modelling-based framework to contrast conventional and modular construction methods through selected sustainability factors.” J. Cleaner Prod. 228 (Aug): 1264–1281. https://doi.org/10.1016/j.jclepro.2019.04.150.
Hammad, A., O. Salem, M. Hastak, and M. Syal. 2008. “Decision support system for manufactured housing facility layout.” J. Archit. Eng. 14 (2): 36–46. https://doi.org/10.1061/(ASCE)1076-0431(2008)14:2(36).
Hammad, A. W., H. Grzybowska, M. Sutrisna, A. Akbarnezhad, and A. Haddad. 2020. “A novel mathematical optimisation model for the scheduling of activities in modular construction factories.” Construct. Manage. Econ. 38 (6): 534–551. https://doi.org/10.1080/01446193.2019.1682174.
Hong, J., G. Q. Shen, Z. Li, B. Zhang, and W. Zhang. 2018. “Barriers to promoting prefabricated construction in China: A cost–benefit analysis.” J. Cleaner Prod. 172 (Jan): 649–660. https://doi.org/10.1016/j.jclepro.2017.10.171.
Hosseini, M. R., I. Martek, E. K. Zavadskas, A. A. Aibinu, M. Arashpour, and N. Chileshe. 2018. “Critical evaluation of off-site construction research: A Scientometric analysis.” Autom. Constr. 87 (Oct): 235–247. https://doi.org/10.1016/j.autcon.2017.12.002.
Hou, L., Y. Tan, W. Luo, S. Xu, C. Mao, and S. Moon. 2020. “Towards a more extensive application of off-site construction: A technological review.” Int. J. Constr. Manage. 22 (11): 2154–2165. https://doi.org/10.1080/15623599.2020.1768463.
Hsu, P. Y., P. Angeloudis, and M. Aurisicchio. 2018. “Optimal logistics planning for modular construction using two-stage stochastic programming.” Autom. Constr. 94 (Sep): 47–61. https://doi.org/10.1016/j.autcon.2018.05.029.
Hussein, M., A. E. E. Eltoukhy, A. Karam, I. A. Shaban, and T. Zayed. 2021. “Modelling in off-site construction supply chain management: A review and future directions for sustainable modular integrated construction.” J. Cleaner Prod. 310 (Aug): 127503. https://doi.org/10.1016/j.jclepro.2021.127503.
Hussein, M., and T. Zayed. 2021. “Critical factors for successful implementation of just-in-time concept in modular integrated construction: A systematic review and meta-analysis.” J. Cleaner Prod. 284 (Feb): 124716. https://doi.org/10.1016/j.jclepro.2020.124716.
Hwang, B. G., M. Shan, and K. Y. Looi. 2018. “Key constraints and mitigation strategies for prefabricated prefinished volumetric construction.” J. Cleaner Prod. 183 (May): 183–193. https://doi.org/10.1016/j.jclepro.2018.02.136.
Innella, F., M. Arashpour, and Y. Bai. 2019. “Lean methodologies and techniques for modular construction: Chronological and critical review.” J. Constr. Eng. Manage. 145 (12): 04019076. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001712.
Isaac, S., T. Bock, and Y. Stoliar. 2016. “A methodology for the optimal modularization of building design.” Autom. Constr. 65 (May): 116–124. https://doi.org/10.1016/j.autcon.2015.12.017.
Jang, J., S. Ahn, S. H. Cha, K. Cho, C. Koo, and T. W. Kim. 2021. “Toward productivity in future construction: Mapping knowledge and finding insights for achieving successful offsite construction projects.” J. Comput. Des. Eng. 8 (1): 1–14. https://doi.org/10.1093/jcde/qwaa071.
Jiang, R., C. Mao, L. Hou, C. Wu, and J. Tan. 2018. “A SWOT analysis for promoting off-site construction under the backdrop of China’s new urbanization.” J. Cleaner Prod. 173 (Feb): 225–234. https://doi.org/10.1016/j.jclepro.2017.06.147.
Jin, R., S. Gao, A. Cheshmehzangi, and E. Aboagye-Nimo. 2018. “A holistic review of off-site construction literature published between 2008 and 2018.” J. Cleaner Prod. 202 (Nov): 1202–1219. https://doi.org/10.1016/j.jclepro.2018.08.195.
Jonsson, H., and M. Rudberg. 2014. “Classification of production systems for industrialized building: A production strategy perspective.” Construct. Manage. Econ. 32 (1–2): 53–69. https://doi.org/10.1080/01446193.2013.812226.
Jonsson, H., and M. Rudberg. 2015. “Production system classification matrix: Matching product standardization and production-system design.” J. Constr. Eng. Manage. 141 (6): 05015004. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000965.
Kamar, K. A. M., Z. A. Hamid, M. K. Ghani, A. H. A. Rahim, M. Z. M. Zain, and F. Ambon. 2012. “Business strategy of large contractors in adopting industrialised building system (IBS): The Malaysian case.” J. Eng. Sci. Technol. 7 (6): 774–784.
Kedir, F., and D. M. Hall. 2021. “Resource efficiency in industrialized housing construction—A systematic review of current performance and future opportunities.” J. Cleaner Prod. 286 (Mar): 125443. https://doi.org/10.1016/j.jclepro.2020.125443.
Kitchenham, B., O. Pearl Brereton, D. Budgen, M. Turner, J. Bailey, and S. Linkman. 2009. “Systematic literature reviews in software engineering—A systematic literature review.” Inf. Software Technol. 51 (1): 7–15. https://doi.org/10.1016/j.infsof.2008.09.009.
Lambert, D. M., and M. C. Cooper. 2000. “Issues in supply chain management.” Ind. Marketing Manage. 29 (1): 65–83. https://doi.org/10.1016/S0019-8501(99)00113-3.
Larsen, M. S. S., S. M. Lindhard, T. D. Brunoe, K. Nielsen, and J. K. Larsen. 2019. “Mass customization in the house building industry: Literature review and research directions.” Front. Built Environ. 5 (Oct): 1–12. https://doi.org/10.3389/fbuil.2019.00115.
Larsson, J., P. E. Eriksson, T. Olofsson, and P. Simonsson. 2014. “Industrialized construction in the Swedish infrastructure sector: Core elements and barriers.” Construct. Manage. Econ. 32 (1–2): 83–96. https://doi.org/10.1080/01446193.2013.833666.
Lekan, A., A. Clinto, O. Fayomi, and O. James. 2020. “Lean thinking and industrial 4.0 approach to achieving construction 4.0 for industrialization and technological development.” Buildings 10 (12): 221. https://doi.org/10.3390/buildings10120221.
Lessing, J. 2015. “Business models for product-oriented house-building companies—Experience from two Swedish case studies.” Constr. Innovation 15 (4): 449–472. https://doi.org/10.1108/CI-02-2015-0009.
Lessing, J., L. Stehn, and A. Ekholm. 2015. “Industrialised house-building—Development and conceptual orientation of the field.” Constr. Innovation 15 (3): 378–399. https://doi.org/10.1108/CI-06-2014-0032.
Li, L., Z. Li, X. Li, S. Zhang, and X. Luo. 2020. “A new framework of industrialized construction in China: Towards on-site industrialization.” J. Cleaner Prod. 244 (Jan): 118469. https://doi.org/10.1016/j.jclepro.2019.118469.
Li, L., Z. Li, G. Wu, and X. Li. 2018. “Critical success factors for project planning and control in prefabrication housing production: A China study.” Sustainability 10 (3): 836. https://doi.org/10.3390/su10030836.
Li, Z., G. Q. Shen, and X. Xue. 2014. “Critical review of the research on the management of prefabricated construction.” Habitat Int. 43 (Jul): 240–249. https://doi.org/10.1016/j.habitatint.2014.04.001.
Liu, G., J. H. Nzige, and K. Li. 2019. “Trending topics and themes in offsite construction(OSC) research: The application of topic modeling.” Constr. Innovation 19 (3): 343–366. https://doi.org/10.1108/CI-03-2018-0013.
Liu, K., Y. Su, and S. Zhang. 2018. “Evaluating supplier management maturity in prefabricated construction project-survey analysis in China.” Sustainability 10 (9): 3046. https://doi.org/10.3390/su10093046.
Liu, Y., J. Dong, and L. Shen. 2020. “A conceptual development framework for prefabricated construction supply chain management: An integrated overview.” Sustainability 12 (5): 1878. https://doi.org/10.3390/su12051878.
Luo, T., X. Xue, Y. Tan, Y. Wang, and Y. Zhang. 2020. “Exploring a body of knowledge for promoting the sustainable transition to prefabricated construction.” Eng. Constr. Archit. Manage. 28 (9): 2637–2666. https://doi.org/10.1108/ECAM-03-2020-0154.
Mao, C., Q. Shen, W. Pan, and K. Ye. 2015. “Major barriers to off-site construction: The developer’s perspective in China.” J. Manage. Eng. 31 (3): 04014043. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000246.
Mao, C., F. Xie, L. Hou, P. Wu, J. Wang, and X. Wang. 2016. “Cost analysis for sustainable off-site construction based on a multiple-case study in China.” Habitat Int. 57 (Oct): 215–222. https://doi.org/10.1016/j.habitatint.2016.08.002.
Marjaba, G. E., and S. E. Chidiac. 2016. “Sustainability and resiliency metrics for buildings—Critical review.” Build. Environ. 101 (May): 116–125. https://doi.org/10.1016/j.buildenv.2016.03.002.
Mehrotra, N., M. Syal, and M. Hastak. 2005. “Manufactured housing production layout design.” J. Archit. Eng. 11 (1): 25–34. https://doi.org/10.1061/(ASCE)1076-0431(2005)11:1(25).
Meiling, J., F. Backlund, and H. Johnsson. 2012. “Managing for continuous improvement in off-site construction: Evaluation of lean management principles.” Eng. Constr. Archit. Manage. 19 (2): 141–158. https://doi.org/10.1108/09699981211206089.
Mostafa, S., V. W. Tam, J. Dumrak, and S. Mohamed. 2020. “Leagile strategies for optimizing the delivery of prefabricated house building projects.” Int. J. Constr. Manage. 20 (8): 867–881. https://doi.org/10.1080/15623599.2018.1494674.
Muñoz-La Rivera, F., J. Mora-Serrano, I. Valero, and E. Oñate. 2020. “Methodological-technological framework for construction 4.0.” In Archives of computational methods in engineering. Berlin: Springer Nature. https://doi.org/10.1007/s11831-020-09455-9.
Nabi, M., and I. H. El-adaway. 2020. “Modular construction: Determining decision-making factors and future research needs.” J. Manage. Eng. 36 (6): 04020085. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000859.
Nadim, W., and J. S. Goulding. 2011. “Offsite production: A model for building down barriers A European construction industry perspective.” Eng. Constr. Archit. Manage. 18 (1): 82–101. https://doi.org/10.1108/09699981111098702.
Nawari, N. O. 2012. “BIM standard in off-site construction.” J. Archit. Eng. 18 (2): 107–113. https://doi.org/10.1061/(ASCE)AE.1943-5568.0000056.
O’Connor, J. T., W. J. O’Brien, and J. O. Choi. 2014. “Critical success factors and enablers for optimum and maximum industrial modularization.” J. Constr. Eng. Manage. 140 (6): 04014012. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000842.
Patrucco, A., F. Ciccullo, and M. Pero. 2020. “Industry 4.0 and supply chain process re-engineering: A coproduction study of materials management in construction.” Bus. Process Manage. J. 26 (5): 1093–1119 https://doi.org/10.1108/BPMJ-04-2019-0147.
Peltokorpi, A., H. Olivieri, A. D. Granja, and O. Seppänen. 2018. “Categorizing modularization strategies to achieve various objectives of building investments.” Construct. Manage. Econ. 36 (1): 32–48. https://doi.org/10.1080/01446193.2017.1353119.
Qi, B., S. Qian, and A. Costin. 2020. “A predictive analysis on emerging technology utilization in industrialized construction in the United States and China.” Algorithms 13 (8): 180. https://doi.org/10.3390/a13080180.
Qi, B., M. Razkenari, A. Costin, C. Kibert, and M. Fu. 2021. “A systematic review of emerging technologies in industrialized construction.” J. Build. Eng. 39 (Feb): 102265. https://doi.org/10.1016/j.jobe.2021.102265.
Rahman, M. M. 2014. “Barriers of implementing modern methods of construction.” J. Manage. Eng. 30 (1): 69–77. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000173.
Ramaji, I. J., and A. M. Memari. 2016. “Product architecture model for multistory modular buildings.” J. Constr. Eng. Manage. 142 (10): 04016047. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001159.
Razkenari, M., A. Fenner, A. Shojaei, H. Hakim, and C. Kibert. 2020. “Perceptions of offsite construction in the United States: An investigation of current practices.” J. Build. Eng. 29 (May): 101138. https://doi.org/10.1016/j.jobe.2019.101138.
Sabet, P., and H. Chong. 2019. “Interactions between building information modelling and off-site manufacturing for productivity improvement.” Int. J. Managing Projects Bus. 13 (2): 233–255. https://doi.org/10.1108/IJMPB-08-2018-0168.
Sadafi, N., M. F. M. Zain, and M. Jamil. 2012. “Adaptable industrial building system: Construction industry perspective.” J. Archit. Eng. 18 (2): 140–147. https://doi.org/10.1061/(ASCE)AE.1943-5568.0000075.
Salvendy, G. 2001. Handbook of industrial engineering technology and operations management. Edited by G. Salvendy, 3rd ed. New York: Wiley-Interscience.
Sepasgozar, M. E. 2020. “Digital technology utilisation decisions for facilitating the implementation of Industry 4.0 technologies.” In Construction innovation. Bingley, UK: Emerald Publishing Limited. https://doi.org/10.1108/CI-02-2020-0020.
Seuring, S., and M. Müller. 2008. “From a literature review to a conceptual framework for sustainable supply chain management.” J. Cleaner Prod. 16 (15): 1699–1710. https://doi.org/10.1016/j.jclepro.2008.04.020.
Shafiee, S., P. Piroozfar, L. Hvam, E. R. P. Farr, G. Q. Huang, W. Pan, A. Kudsk, J. B. Rasmussen, and M. Korell. 2020. “Modularisation strategies in the AEC industry: A comparative analysis.” Archit. Eng. Des. Manage. 16 (4): 270–292. https://doi.org/10.1080/17452007.2020.1735291.
Song, J., W. R. Fagerlund, C. T. Haas, C. B. Tatum, and J. A. Vanegas. 2005. “Considering prework on industrial projects.” J. Constr. Eng. Manage. 131 (6): 723–733. https://doi.org/10.1061/(ASCE)0733-9364(2005)131:6(723).
Sutrisna, M., C. D. D. Ramanayaka, and J. S. Goulding. 2018. “Developing work breakdown structure matrix for managing offsite construction projects.” Archit. Eng. Des. Manage. 14 (5): 381–397. https://doi.org/10.1080/17452007.2018.1477728.
Sutrisna, M., V. Ramnauth, and A. Zaman. 2020. “Towards adopting off-site construction in housing sectors as a potential source of competitive advantage for builders.” Archit. Eng. Des. Manage. 18 (3): 165–183. https://doi.org/10.1080/17452007.2020.1807306.
Tang, X., H.-Y. Chong, and W. Zhang. 2019. “Relationship between BIM implementation and performance of OSM projects.” J. Manage. Eng. 35 (5): 04019019. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000704.
Taylor, M. D. 2010. “A definition and valuation of the UK offsite construction sector.” Construct. Manage. Econ. 28 (8): 885–896. https://doi.org/10.1080/01446193.2010.480976.
Teng, Y., C. Mao, G. Liu, and X. Wang. 2017. “Analysis of stakeholder relationships in the industry chain of industrialized building in China.” J. Cleaner Prod. 152 (May): 387–398. https://doi.org/10.1016/j.jclepro.2017.03.094.
Thomé, A. M. T., L. F. Scavarda, and A. J. Scavarda. 2016. “Conducting systematic literature review in operations management.” Prod. Plann. Control 27 (5): 408–420. https://doi.org/10.1080/09537287.2015.1129464.
Tsz Wai, C., P. Wai Yi, O. Ibrahim Olanrewaju, S. Abdelmageed, M. Hussein, S. Tariq, and T. Zayed. 2021. “A critical analysis of benefits and challenges of implementing modular integrated construction.” Int. J. Constr. Manage. (Mar): 1–24. https://doi.org/10.1080/15623599.2021.1907525.
Viking, A., and S. Lidelöw. 2015. “Exploring industrialized housebuilders’ interpretations of local requirements using institutional logics.” Construct. Manage. Econ. 33 (5–6): 484–494. https://doi.org/10.1080/01446193.2015.1050966.
Wang, G., H. Liu, H. Li, X. Luo, and J. Liu. 2020. “A building project-based industrialized construction maturity model involving organizational enablers: A multi-case study in China.” Sustainability 12 (10): 4029. https://doi.org/10.3390/su12104029.
Woodhead, R., P. Stephenson, and D. Morrey. 2018. “Digital construction: From point solutions to IoT ecosystem.” Autom. Constr. 93 (Sep): 35–46. https://doi.org/10.1016/j.autcon.2018.05.004.
Wu, G., R. Yang, L. Li, X. Bi, B. Liu, S. Li, and S. Zhou. 2019. “Factors influencing the application of prefabricated construction in China: From perspectives of technology promotion and cleaner production.” J. Cleaner Prod. 219 (May): 753–762. https://doi.org/10.1016/j.jclepro.2019.02.110.
Wuni, I., and G. Shen. 2019a. “Holistic review and conceptual framework for the drivers of offsite construction: A total interpretive structural modelling approach.” Buildings 9 (5): 117. https://doi.org/10.3390/buildings9050117.
Wuni, I. Y., and G. Q. Shen. 2019b. “Towards a decision support for modular integrated construction: An integrative review of the primary decision-making actors.” Int. J. Constr. Manage. 22 (5): 929–948. https://doi.org/10.1080/15623599.2019.1668633.
Wuni, I. Y., and G. Q. Shen. 2020a. “Barriers to the adoption of modular integrated construction: Systematic review and meta-analysis, integrated conceptual framework, and strategies.” J. Cleaner Prod. 249 (Mar): 119347. https://doi.org/10.1016/j.jclepro.2019.119347.
Wuni, I. Y., and G. Q. Shen. 2020b. “Critical success factors for management of the early stages of prefabricated prefinished volumetric construction project life cycle.” Eng. Constr. Archit. Manage. 27 (9): 2315–2333. https://doi.org/10.1108/ECAM-10-2019-0534.
Wuni, I. Y., and G. Q. Shen. 2020c. “Critical success factors for modular integrated construction projects: A review.” Build. Res. Inf. 48 (7): 763–784. https://doi.org/10.1080/09613218.2019.1669009.
Wuni, I. Y., G. Q. Shen, and A. Darko. 2021a. “Best practices for implementing industrialized construction projects: Lessons from nine case studies.” In Construction innovation. Bingley, UK: Emerald Publishing Limited. https://doi.org/10.1108/CI-04-2021-0070/FULL/XML.
Wuni, I. Y., G. Q. Shen, A. J. Ogungbile, and J. Z. Ayitey. 2021b. “Four-pronged decision support framework for implementing industrialized construction projects.” In Construction innovation. London: Taylor & Francis. https://doi.org/10.1108/CI-11-2020-0184.
Wuni, I. Y., G. Q. Shen, and R. Osei-Kyei. 2020. “Quantitative evaluation and ranking of the critical success factors for modular integrated construction projects.” Int. J. Constr. Manage. 22 (11): 2108–2120. https://doi.org/10.1080/15623599.2020.1766190.
Xu, Z., T. Zayed, and Y. Niu. 2020. “Comparative analysis of modular construction practices in mainland China, Hong Kong and Singapore.” J. Cleaner Prod. 245 (Feb): 118861. https://doi.org/10.1016/j.jclepro.2019.118861.
Xue, H., S. Zhang, Y. Su, Z. Wu, and R. J. Yang. 2018a. “Effect of stakeholder collaborative management on off-site construction cost performance.” J. Cleaner Prod. 184 (May): 490–502. https://doi.org/10.1016/j.jclepro.2018.02.258.
Xue, X., X. Zhang, L. Wang, M. Skitmore, and Q. Wang. 2018b. “Analyzing collaborative relationships among industrialized construction technology innovation organizations: A combined SNA and SEM approach.” J. Cleaner Prod. 173 (Feb): 265–277. https://doi.org/10.1016/j.jclepro.2017.01.009.
Yin, X., H. Liu, Y. Chen, and M. Al-Hussein. 2019. “Building information modelling for off-site construction: Review and future directions.” Autom. Constr. 101 (Jan): 72–91. https://doi.org/10.1016/j.autcon.2019.01.010.
Yu, H., M. Al-Hussein, S. Al-Jibouri, and A. Telyas. 2013. “Lean transformation in a modular building company: A case for implementation.” J. Manage. Eng. 29 (1): 103–111. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000115.
Zakaria, S. A. S., T. Gajendran, T. Rose, and G. Brewer. 2018. “Contextual, structural and behavioural factors influencing the adoption of industrialised building systems: A review.” Archit. Eng. Des. Manage. 14 (1–2): 3–26. https://doi.org/10.1080/17452007.2017.1291410.
Zhang, X., M. Skitmore, and Y. Peng. 2014. “Exploring the challenges to industrialized residential building in China.” Habitat Int. 41 (Mar): 176–184. https://doi.org/10.1016/j.habitatint.2013.08.005.
Zhang, Y., Z. Lei, S. Han, A. Bouferguene, and M. Al-Hussein. 2020. “Process-oriented framework to improve modular and offsite construction manufacturing performance.” J. Constr. Eng. Manage. 146 (9): 04020116. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001909.

Information & Authors

Information

Published In

Go to Journal of Construction Engineering and Management
Journal of Construction Engineering and Management
Volume 149Issue 2February 2023

History

Published online: Nov 30, 2022
Published in print: Feb 1, 2023
Discussion open until: Apr 30, 2023

Permissions

Request permissions for this article.

Authors

Affiliations

Ph.D. Student, ALGORITMI Research Centre, Dept. of Systems and Production, Univ. of Minho, Braga, Portugal; dstgroup, Rua Pitancinhos, Palmeira, Braga 4700-727, Portugal (corresponding author). ORCID: https://orcid.org/0000-0002-9555-6591. Email: [email protected]
Maria Sameiro Carvalho, Ph.D. [email protected]
Professor, ALGORITMI Research Centre, Dept. of Systems and Production, Univ. of Minho, Braga, Portugal. Email: [email protected]
Carina Pimentel, Ph.D. [email protected]
Professor, Governance, Competitiveness and Public Policies Research Unit, Department of Economics, Management, Industrial Engineering and Tourism, Univ. of Aveiro, Aveiro, Portugal. Email: [email protected]
Claudia Duarte, Ph.D. [email protected]
dstgroup, Rua Pitancinhos, Palmeira, Braga 4700-727, Portugal. Email: [email protected]

Metrics & Citations

Metrics

Citations

Download citation

If you have the appropriate software installed, you can download article citation data to the citation manager of your choice. Simply select your manager software from the list below and click Download.

Cited by

  • Accelerating the Circular Economy Transition: A Construction Value Chain-Structured Portfolio of Strategies and Implementation Insights, Journal of Construction Engineering and Management, 10.1061/JCEMD4.COENG-14550, 150, 8, (2024).
  • Strategic Workforce Planning for Production of Prefabricated Bathroom Units: An Advanced Markovian Approach, Journal of Construction Engineering and Management, 10.1061/JCEMD4.COENG-14514, 150, 8, (2024).
  • Development of an Integrated Hybrid Risk Assessment System for Construction Disputes during the Preconstruction Phase Using the Delphi Method, Journal of Construction Engineering and Management, 10.1061/JCEMD4.COENG-14492, 150, 7, (2024).
  • Ameliorating Supply Chains of Prefabricated Housebuilding: An Integrated Performance Framework, Journal of Construction Engineering and Management, 10.1061/JCEMD4.COENG-14404, 150, 6, (2024).
  • Developing Collaborative Driving Mechanism of Prefabricated Buildings Using Multiagent Stochastic Evolutionary Game, Journal of Construction Engineering and Management, 10.1061/JCEMD4.COENG-14396, 150, 6, (2024).
  • Deciphering the Key Characteristics of On-Site Industrialized Construction: Inspiration from China, Journal of Construction Engineering and Management, 10.1061/JCEMD4.COENG-14150, 150, 4, (2024).
  • Promoting the Application of Off-Site Construction in China’s Residential Building Industry from the Angle of Ecosystem, Systems, 10.3390/systems11030140, 11, 3, (140), (2023).

View Options

Get Access

Access content

Please select your options to get access

Log in/Register Log in via your institution (Shibboleth)
ASCE Members: Please log in to see member pricing

Purchase

Save for later Information on ASCE Library Cards
ASCE Library Cards let you download journal articles, proceedings papers, and available book chapters across the entire ASCE Library platform. ASCE Library Cards remain active for 24 months or until all downloads are used. Note: This content will be debited as one download at time of checkout.

Terms of Use: ASCE Library Cards are for individual, personal use only. Reselling, republishing, or forwarding the materials to libraries or reading rooms is prohibited.
ASCE Library Card (5 downloads)
$105.00
Add to cart
ASCE Library Card (20 downloads)
$280.00
Add to cart
Buy Single Article
$35.00
Add to cart

Get Access

Access content

Please select your options to get access

Log in/Register Log in via your institution (Shibboleth)
ASCE Members: Please log in to see member pricing

Purchase

Save for later Information on ASCE Library Cards
ASCE Library Cards let you download journal articles, proceedings papers, and available book chapters across the entire ASCE Library platform. ASCE Library Cards remain active for 24 months or until all downloads are used. Note: This content will be debited as one download at time of checkout.

Terms of Use: ASCE Library Cards are for individual, personal use only. Reselling, republishing, or forwarding the materials to libraries or reading rooms is prohibited.
ASCE Library Card (5 downloads)
$105.00
Add to cart
ASCE Library Card (20 downloads)
$280.00
Add to cart
Buy Single Article
$35.00
Add to cart

Media

Figures

Other

Tables

Share

Share

Copy the content Link

Share with email

Email a colleague

Share