Impact of Using a Formalized Methodology for Conflict Detection Based on 4D-BIM

Publication: Journal of Construction Engineering and Management
Volume 150, Issue 7

Abstract

In construction projects, when resources assigned to two or more simultaneous activities share the same workspace, they generate time-space conflicts associated with congestion, safety, and quality issues. The use of building information modeling (BIM) methodologies, particularly four-dimensional (4D) models, offers the possibility to facilitate the identification of these types of conflicts. Existing literature has proposed formal methods for conflict detection; however, these largely focus on automating computational analyses without providing a practical and useful procedure for planners. Moreover, previous research has not evaluated the impact of using formal conflict detection methodologies. To address these gaps, this study proposes and evaluates the use of a formal conflict detection methodology in workspaces based on 4D-BIM. The research methodology includes a first stage that develops and validates the formalized conflict detection methodology through a literature review and interviews with field professionals. The second stage quantifies the impact of using the proposed methodology through an experiment that compares the effectiveness and efficiency of a group of planners in detecting conflicts using 4D-BIM models with and without the proposed methodology. The results demonstrate that the formalized methodology enhances the planning process by increasing the detection of conflicts from 18% to 82%. Additionally, the formalized methodology reduces review time by 23% and enhances user experience. These findings contribute to improving the planning process by managing and reducing time-space conflicts in construction schedules. Consequently, the construction process will become more efficient by averting issues related to productivity, safety, and quality based on the identification of workspace conflicts. Last, the proposed methodology contributes to a better adoption of BIM by providing a structured procedure for using the 4D-BIM model to support planning processes.

Practical Applications

This study lays the groundwork for companies aiming to enhance their conflict detection processes and refine planning and conflict management procedures. The practical contributions include achieving greater effectiveness and efficiency in identifying conflicts in workspaces. The proposed formalized methodology enhances productivity, reduces safety-related risks, and prevents quality issues in building projects by managing and mitigating time-space conflicts in construction programs. Additionally, the research contributes to the enrichment of BIM application in construction activity planning. It formalizes the use of BIM through a conflict detection methodology, particularly in the analysis of construction programs and the identification of workspace conflicts. The results further strengthen the application of the BIM methodology by facilitating the design of BIM processes associated with planning, incorporating the methodology proposed in this research. Furthermore, the study encourages the adoption of BIM in construction activity planning by evaluating the positive impact of the proposed formalized methodology, providing evidence for its implementation in organizations and highlighting its potential benefits in terms of effectiveness and efficiency.

Get full access to this article

View all available purchase options and get full access to this article.

Data Availability Statement

Some or all data, models, or code generated or used during the study are proprietary or confidential in nature and may only be provided with restrictions, including 4D-BIM models of case studies (anonymized name and owner of the projects).

References

Akinci, B., M. Fischen, R. Levitt, and R. Carlson. 2002a. “Formalization and automation of time-space conflict analysis.” J. Comput. Civ. Eng. 16 (2): 124–134. https://doi.org/10.1061/(ASCE)0887-3801(2002)16:2(124).
Akinci, B., M. Fischer, and J. Kunz. 2002b. “Automated generation of work spaces required by construction activities.” J. Constr. Eng. Manage. 128 (4): 306–315. https://doi.org/10.1061/(ASCE)0733-9364(2002)128:4(306).
Akinci, B., M. Fischer, J. Kunz, and R. Levitt. 2002c. “Representing work spaces generically in construction method models.” J. Constr. Eng. Manage. 128 (4): 296–305. https://doi.org/10.1061/(ASCE)0733-9364(2002)128:4(296).
Caldart, C. W., and S. Scheer. 2022. “Construction site design planning using 4D BIM modeling.” Gestão Produção 29 (5): 312. https://doi.org/10.1590/1806-9649-2022v29e5312.
Clayton, M., J. Kunz, and M. Fischer. 1998. The Charrette test method. Technical Rep. No. 120. Standford, CA: Center for Integrated Facility Engineering at Stanford Univ.
Darwiche, A., R. E. Levitt, and B. Hayes-Roth. 1988. “OARPLAN: Generating project plans by reasoning about objects, actions and resources.” Artif. Intell. Eng. Des. Anal. Manuf. 2 (3): 169–181. https://doi.org/10.1017/S0890060400000639.
Guo, S.-J. 2002. “Identification and resolution of work space conflicts in building construction.” J. Constr. Eng. Manage. 128 (4): 287–295. https://doi.org/10.1061/(ASCE)0733-9364(2002)128:4(287).
Hartmann, T., J. Gao, and M. Fischer. 2008. “Areas of application for 3D and 4D models on construction projects.” J. Constr. Eng. Manage. 134 (10): 776–785. https://doi.org/10.1061/(ASCE)0733-9364(2008)134:10(776).
Hosny, A., M. Nik-Bakht, and O. Moselhi. 2020. “Workspace planning in construction: Non-deterministic factors.” Autom. Constr. 116 (Aug): 103222. https://doi.org/10.1016/j.autcon.2020.103222.
Hosny, A., M. Nik-Bakht, and O. Moselhi. 2022. “Physical distancing analytics for construction planning using 4D BIM.” J. Comput. Civ. Eng. 36 (4): 04022012. https://doi.org/10.1061/(ASCE)CP.1943-5487.0001023.
Ignatova, E. V. 2018. “Workspace planning based on the analysis of BIM collisions.” Mater. Sci. Forum 931 (Mar): 1286–1290. https://doi.org/10.4028/www.scientific.net/MSF.931.1286.
Kassem, M., N. Dawood, and R. Chavada. 2015. “Construction workspace management within an industry foundation class-compliant 4D tool.” Autom. Constr. 52 (Apr): 42–58. https://doi.org/10.1016/j.autcon.2015.02.008.
Kumar, S. S. 2015. “A BIM-based framework for site layout optimization and material logistics planning on congested construction sites.” Doctoral dissertation, Dept. of Civil and Environmental Engineering, Hong Kong Univ. of Science and Technolog.
Lai, K. F., and Y. C. Chan. 2020. “Review of construction workspace definition and case studies.” In Proc., 37th Int. Symp. on Automation and Robotics in Construction (ISARC 2020). Taipéi, Taiwan: National Taiwan Univ. https://doi.org/10.22260/ISARC2020/0043.
Ma, H., H. Zhang, and P. Chang. 2020. “4D-based workspace conflict detection in prefabricated building constructions.” J. Constr. Eng. Manage. 146 (9): 1–11. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001883.
Matas, A. 2018. “Diseño del formato de escalas tipo Likert: Un estado de la cuestión.” Rev. Electronica de Investigacion Educativa 20 (1): 38–47. https://doi.org/10.24320/redie.2018.20.1.1347.
Mirzaei, A., F. Nasirzadeh, M. Parchami Jalal, and Y. Zamani. 2018. “4D-BIM dynamic time-space conflict detection and quantification system for building construction projects.” J. Constr. Eng. Manage. 144 (7): 04018056. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001504.
Moon, H., N. Dawood, and L. Kang. 2014a. “Development of workspace conflict visualization system using 4D object of work schedule.” Adv. Eng. Inf. 28 (1): 50–65. https://doi.org/10.1016/j.aei.2013.12.001.
Moon, H., V. R. Kamat, and L. Kang. 2014b. “Grid cell-based algorithm for workspace overlapping analysis considering multiple allocations of construction resources.” J. Asian Archit. Build. Eng. 13 (2): 341–348. https://doi.org/10.3130/jaabe.13.341.
Mourgues, C., M. Fischer, and J. Kunz. 2012. “Method to produce field instructions from product and process models for cast-in-place concrete operations.” Autom. Constr. 22 (Mar): 233–246. https://doi.org/10.1016/j.autcon.2011.07.007.
Riley, D. R., and V. E. Sanvido. 1997. “Space planning method for multistory building construction.” J. Constr. Eng. Manage. 123 (2): 171–180. https://doi.org/10.1061/(ASCE)0733-9364(1997)123:2(171).
Su, X., and H. Cai. 2014. “Life cycle approach to construction workspace modeling and planning.” J. Constr. Eng. Manage. 140 (7): 04014019. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000855.
Sulankivi, K., S. Zhang, J. Teizer, M. Charles, M. Kiviniemi, I. Romo, and L. Granholm. 2013. “Utilization of BIM-based automated safety checking in construction planning.” In Proc., CIB World Building Conf. 2013, 11. Espoo, Finland: VTT Technical Research Center of Finland.
Trebbe, M., T. Hartmann, and A. Dorée. 2015. “4D CAD models to support the coordination of construction activities between contractors.” Autom. Constr. 49 (Jan): 83–91. https://doi.org/10.1016/j.autcon.2014.10.002.
Wu, I., and Y. Chiu. 2010. “4D Workspace conflict detection and analysis system.” In Proc., 10th Int. Conf. on Construction Applications of Virtual Reality, 1–8. Kaohsiung City, Taiwan: National Kaohsiung Univ. of Applied Sciences.
Zhang, J. P., and Z. Z. Hu. 2010. “BIM-and 4D-based integrated solution of analysis and management for conflicts and structural safety problems during construction: 1 Principles and methodologies.” Autom. Constr. 20: 155–166. https://doi.org/10.1016/j.autcon.2010.09.013.

Information & Authors

Information

Published In

Go to Journal of Construction Engineering and Management
Journal of Construction Engineering and Management
Volume 150Issue 7July 2024

History

Received: Aug 21, 2023
Accepted: Jan 29, 2024
Published online: Apr 24, 2024
Published in print: Jul 1, 2024
Discussion open until: Sep 24, 2024

Permissions

Request permissions for this article.

Authors

Affiliations

Martín Flores, Aff.M.ASCE [email protected]
Researcher, School of Civil Engineering, Pontificia Universidad Católica de Chile, Santiago de Chile 7820436, Chile (corresponding author). Email: [email protected]
Claudio Mourgues [email protected]
Associate Professor, School of Civil Engineering, Pontificia Universidad Católica de Chile, Santiago de Chile 7820436, Chile. Email: [email protected]

Metrics & Citations

Metrics

Citations

Download citation

If you have the appropriate software installed, you can download article citation data to the citation manager of your choice. Simply select your manager software from the list below and click Download.

View Options

Get Access

Access content

Please select your options to get access

Log in/Register Log in via your institution (Shibboleth)
ASCE Members: Please log in to see member pricing

Purchase

Save for later Information on ASCE Library Cards
ASCE Library Cards let you download journal articles, proceedings papers, and available book chapters across the entire ASCE Library platform. ASCE Library Cards remain active for 24 months or until all downloads are used. Note: This content will be debited as one download at time of checkout.

Terms of Use: ASCE Library Cards are for individual, personal use only. Reselling, republishing, or forwarding the materials to libraries or reading rooms is prohibited.
ASCE Library Card (5 downloads)
$105.00
Add to cart
ASCE Library Card (20 downloads)
$280.00
Add to cart
Buy Single Article
$35.00
Add to cart

Get Access

Access content

Please select your options to get access

Log in/Register Log in via your institution (Shibboleth)
ASCE Members: Please log in to see member pricing

Purchase

Save for later Information on ASCE Library Cards
ASCE Library Cards let you download journal articles, proceedings papers, and available book chapters across the entire ASCE Library platform. ASCE Library Cards remain active for 24 months or until all downloads are used. Note: This content will be debited as one download at time of checkout.

Terms of Use: ASCE Library Cards are for individual, personal use only. Reselling, republishing, or forwarding the materials to libraries or reading rooms is prohibited.
ASCE Library Card (5 downloads)
$105.00
Add to cart
ASCE Library Card (20 downloads)
$280.00
Add to cart
Buy Single Article
$35.00
Add to cart

Media

Figures

Other

Tables

Share

Share

Copy the content Link

Share with email

Email a colleague

Share