Earned value management (EVM) is a project management approach that can enhance the probability of project success. It is applied widely across different industry sectors (e.g., energy, aerospace, construction, defense, and manufacturing), generally through the use of an earned value management system (EVMS). A holistic and up-to-date literature review on EVM and EVMS does not exist. A literature review can provide a comprehensive perspective on the topic, identifying and summarizing the existing body of knowledge, as a foundation to advance the state of practice of EVM/EVMS. Therefore, the objective of this paper is to investigate the EVM/EVMS state of the art by critically reviewing academic and industry publications, with a specific focus on the maturity of EVMS and the environment surrounding its implementation. By performing a systematic literature review, the authors identified 600 publications since the inception of the EVM concept in 1962, and then narrowed down this list to 160 relevant publications from the last decade for closer review. The findings include the discovery of eight emergent themes. Of these themes, “forecasting/prediction” constitutes the largest portion of the recent literature, followed by “application of EVMS.” One interesting finding is that EVMS maturity, although being a critical topic, is only discussed in one publication. Publications focused on EVM/EVMS have increased in the last decade and significant differences were found between academia and industry literature in terms of the limitations and extensions of EVM/EVMS, EVMS environment, and compliance. A key finding is that designing a reliable EVMS should combine both technical and social aspects of implementation. This forward-looking paper provides a state-of-the-art review while highlighting gaps in the existing EVM/EVMS body of knowledge and introducing new perspectives to support EVMS research and application.

Formats available

You can view the full content in the following formats:

Data Availability Statement

Some or all data, models, or code that support the findings of this study are available from the corresponding author upon reasonable request.

Acknowledgments

The authors would like to thank the US Department of Energy for supporting and funding this study through a project entitled “Improving the Reliability of EVMS Compliance Reviews and EVMS Maturity Level Assessments.” The authors also would like to thank all the government and industry professionals participating on the research team for their valuable input throughout the research process.

References

AACE (American Association of Cost Engineering). 2014a. Level of effort planning and execution on earned value projects: Within the framework of ANSI/EIA-748. Morgantown, WV: AACE.
AACE (American Association of Cost Engineering). 2014b. Required skills and knowledge of earned value management. Morgantown, WV: AACE.
Abba, W. 2000. “How earned value got to primetime: A short look back and a glance ahead.” In Proc., Project Management Institute Seminars and Symp. Newtown Square, PA: Project Management Institute.
Abba, W. F. 2017. “The evolution of earned value management.” Coll. Perform. Manage. 2: 9–12.
Abdel Razik, M. 2020. “Earned schedule as a tool to forecast indirect costs.” In Proc., EVP PSP, 2020 AACE Int. Transactions, EVM-3544. Morgantown, WV: American Association of Cost Engineering.
Agile Alliance. 2017. Agile practice guide. Newtown Square, PA: Project Management Institute.
Alhojailan, M. I. 2012. “Thematic analysis: A critical review of its process and evaluation.” West East J. Social Sci. 1 (1): 39–47.
Alleman, G. 2014. Performance-based project management: Increasing the probability of project success. New York: AMACOM.
Alleman, G., T. Coonce, and R. Price. 2018. “Increasing the probability of program success with continuous risk management.” Coll. Perform. Manage. 4: 27–46.
Alshaheen, A. 2018. “Forecasting project completion date using earned schedule and primavera P6TM.” Coll. Perform. Manage. 2: 11–22.
Alzraiee, H. 2018. “Integrating BIM and earned value management system to measure construction progress.” In Proc., Construction Research Congress 2018, 684–693. Reston, VA: ASCE.
Andersen, E. S., and S. A. Jessen. 2003. “Project maturity in organisations.” Int. J. Project Manage. 21 (6): 457–461. https://doi.org/10.1016/S0263-7863(02)00088-1.
Anderson, L. 2015. “Managing by exception–simplifying earned value for mainstream application.” Coll. Perform. Manage. 3: 29–30.
Aramali, V., G. E. Gibson Jr., M. El Asmar, and N. Cho. 2021. “Earned value management system state of practice: Identifying critical subprocesses, challenges, and environment factors of a high-performing EVMS.” J. Manage. Eng. 37 (4): 04021031. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000925.
Aramvareekul, P., and R. D. Stephens. 2014. “Planning for EVM within basic project controls deliverables.” In Proc., 2014 AACE Int. Transactions, EVM.1552. Morgantown, WV: American Association of Cost Engineering.
Babar, S., M. J. Thaheem, and B. Ayub. 2017. “Estimated cost at completion: Integrating risk into earned value management.” J. Constr. Eng. Manage. 143 (3): 04016104. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001245.
Baggett, K. S., Jr. 2014. “A systems-based framework for the assessment of performance measurement system implementations in R&D organizations.” Ph.D. dissertation, College of Engineering & Technology, Engineering Management, Old Dominion Univ.
Bain, R., and L. Polakovic. 2005. Traffic forecasting risk study update 2005: Through ramp-up and beyond. New York: Standard & Poor’s.
Baker, M. C. 2015. “A survival guide for using EVMS on small EPC projects.” In Proc., CCP CCT, 2015 AACE Int. Transactions, EVM.1896. Morgantown, WV: American Association of Cost Engineering.
Ballesteros-Pérez, P., E. Sanz-Ablanedo, D. Mora-Melia, M. C. González-Cruz, J. L. Fuentes-Bargues, and E. Pellicer. 2019. “Earned schedule min-max: Two new EVM metrics for monitoring and controlling projects.” Autom. Constr. 103 (Jul): 279–290. https://doi.org/10.1016/j.autcon.2019.03.016.
Batselier, J., and M. Vanhoucke. 2015a. “Construction and evaluation framework for a real-life project database.” Int. J. Project Manage. 33 (3): 697–710. https://doi.org/10.1016/j.ijproman.2014.09.004.
Batselier, J., and M. Vanhoucke. 2015b. “Evaluation of deterministic state-of-the-art forecasting approaches for project duration based on earned value management.” Int. J. Project Manage. 33 (7): 1588–1596. https://doi.org/10.1016/j.ijproman.2015.04.003.
Batselier, J., and M. Vanhoucke. 2017. “Improving project forecast accuracy by integrating earned value management with exponential smoothing and reference class forecasting.” Int. J. Project Manage. 35 (1): 28–43. https://doi.org/10.1016/j.ijproman.2016.10.003.
Baxter, G., and I. Sommerville. 2011. “Socio-technical systems: From design methods to systems engineering.” Interact. Comput. 23 (1): 4–17. https://doi.org/10.1016/j.intcom.2010.07.003.
Bembers, I., M. Jones, E. Knox, and J. Traczyk. 2017a. Better earned value management system implementation research study. Arlington, VA: Joint Space Cost Council.
Bembers, I., E. Knox, M. Jones, and J. Traczyk. 2017b. “EVM system’s high cost—Fact or fiction? Defense Acquisition University.” Coll. Perform. Manage. 1: 57–61.
Bergerud, C. 2017. “Adopting a flexible EVM strategy to optimize project performance.” In Proc., 2017 AACE Int. Transactions, EVM-2590. Morgantown, WV: American Association of Cost Engineering.
Bhaumik, H. 2016. “EVMS recommendations for multi-contract projects.” In Proc., 2016 AACE Int. Transactions, EVM-2141. Morgantown, WV: American Association of Cost Engineering.
Bider, I., and V. Klyukina. 2018. “Using a socio-technical systems approach for a sales process improvement.” In Proc., 2018 IEEE 22nd Int. Enterprise Distributed Object Computing Workshop (EDOCW), 48–58. New York: IEEE.
Blanco, F. 2011. “Revenue recognition methods and cost control through earned value management (EVM).” In Proc., 2016 AACE Int. Transactions, EVM.476. Morgantown, WV: American Association of Cost Engineering.
Bolinger, P., and S. Phillips. 2018. “On the psychology of human misjudgment: Charlie Munger on decision-making.” Coll. Perform. Manage. 4: 9–11.
Booth, A., A. Sutton, and D. Papaioannou. 2016. Systematic approaches to a successful literature review. London: SAGE.
Bowman, L., and M. Sabouri. 2014. “Effective use of earned value for controlling construction projects.” In Proc., 2014 AACE Int. Transactions, EVM.1747. Morgantown, WV: American Association of Cost Engineering.
Briner, R. B., and D. Denyer. 2012. “Systematic review and evidence synthesis as a practice and scholarship tool.” In Handbook of evidence-based management: Companies, classrooms and research, 112–129. Oxford, UK: Oxford University Press.
Bryde, D., C. Unterhitzenberger, and R. Joby. 2018. “Conditions of success for earned value analysis in projects.” Int. J. Project Manage. 36 (3): 474–484. https://doi.org/10.1016/j.ijproman.2017.12.002.
Carrico, K., E. Dembert, M. Hollowell, J. Johannsen, and J. Lund. 2019. “The power of projections: Innovative schedule forecasting techniques.” In Proc., CCP PSP, 2019 AACE Int. Transactions, CSC-3107. Morgantown, WV: American Association of Cost Engineering.
Chen, S., and X. Zhang. 2012. “An analytic review of earned value management studies in the construction industry.” In Proc., Construction Research Congress 2012: Construction Challenges in a Flat World, 236–246. Reston, VA: ASCE.
Chirinos, W. 2014. “Applying earned value to overcome challenges in oil and gas industry surface projects.” Coll. Perform. Manage. 4: 7–13.
Cho, N., M. El Asmar, G. E. Gibson Jr., and V. Aramali. 2020. “Earned value management system (EVMS) reliability: A review of existing EVMS literature.” In Proc., Construction Research Congress 2020, 631–639. Reston, VA: ASCE.
Christensen, D. S. 1994. “A review of cost/schedule control systems criteria literature.” Project Manage. J. 25 (3): 32–39.
Christensen, D. S. 1998. “The costs and benefits of the earned value management process.” J. Parametrics 18 (2): 1–16. https://doi.org/10.1080/10157891.1998.10462568.
Colin, J., A. Martens, M. Vanhoucke, and M. Wauters. 2015. “A multivariate approach for top-down project control using earned value management.” Decis. Support Syst. 79 (Nov): 65–76. https://doi.org/10.1016/j.dss.2015.08.002.
Colin, J., and M. Vanhoucke. 2015. “A comparison of the performance of various project control methods using earned value management systems.” Expert Syst. Appl. 42 (6): 3159–3175. https://doi.org/10.1016/j.eswa.2014.12.007.
Crawford, J. K. 2001. Project management maturity model: Providing a proven path to project management excellence. Boca Raton, FL: CRC Press.
Crowe, S., and A. Basche. 2011. “Preparing for a successful EVMS certification.” In Proc., 2011 AACE Int. Transactions, EVM-622. Morgantown, WV: American Association of Cost Engineering.
Crumrine, K. T., and J. D. Ritschel. 2013. “A comparison of earned value management and earned schedule as schedule predictors on DoD ACAT I programs.” Coll. Perform. Manage. 2: 37–44.
Cruzes, D. S., and T. Dyba. 2011. “Recommended steps for thematic synthesis in software engineering.” In Proc., 2011 Int. Symp. on Empirical Software Engineering and Measurement, 275–284. New York: IEEE.
DCMA (Defense Contract Management Agency). 2012. Earned value management system (EVMS) program analysis pamphlet (PAP). DCMA-EA PAM 200.1. Fort Lee, VA: DCMA.
Dekker, S. 2012. “Accepted standards and emerging trends in Over Target Baseline (OTB) contracts.” In Proc., AACE Int. Transactions, CSC.816. Morgantown, WV: American Association of Cost Engineering.
Demachkieh, F., and M. A. Abdul-Malak. 2018. “Synthesis of improvements to EVMS key parameters representation.” In Proc., Construction Research Congress 2018, 399–408. Reston, VA: ASCE.
Demachkieh, F., and M. A. Abdul-Malak. 2019. “Emergent EVM techniques for construction schedule performance measurement and control.” In Proc., 2019 AACE Int. Transactions, EVM-3271. Morgantown, WV: American Association of Cost Engineering.
Denyer, D., and D. Tranfield. 2009. “Producing a systematic review.” In The SAGE handbook of organizational research methods. London: SAGE.
Devanshu, V., P. M. Rajgor, and J. Pitroda. 2018. “A critical literature review on implementation of earn value management.” Int. J. Constructive Res. Civ. Eng. 4 (1): 39–43. https://doi.org/10.20431/2454-8693.0401004.
Dinsmore, P. C., and J. Cabanis-Brewin. 2014. The project management body of knowledge: Comprehension and practice: The AMA handbook of project management. New York: AMACOM.
DoD (Department of Defense). 2020. Work breakdown structures for defense material items. Arlington, VA: DoD.
Dodson, M., G. Defavari, and V. de Carvalho. 2015. “Quality: The third element of earned value management.” Procedia Comput. Sci. 64 (Jan): 932–939. https://doi.org/10.1016/j.procs.2015.08.610.
DOE. 2018a. Office of project management EVMS Compliance Review Standard Operating Procedure (ECRSOP). Washington, DC: DOE.
DOE. 2018b. Program and project management for the acquisition of capital assets. DOE O 413.3B. Washington, DC: DOE.
DOE. 2019. DOE EVMS gold card. Washington, DC: DOE.
DOE. 2020. Integrated project management—Earned value management system (EVMS). DOE G 413.3-10B. Washington, DC: DOE.
Driessnack, J. D. 2017. “The history of earned value management, the 60’s.” Coll. Perform. Manage. 2: 29–34.
Driessnack, J. D. 2019. “Earned value management standards structures, part 1—Why three.” Coll. Perform. Manage. 2: 34–38.
Efe, P., and O. Demirörs. 2013. “Applying EVM in a software company: Benefits and difficulties.” In Proc., 39th Euromicro Conf. on Software Engineering and Advanced Applications, 333–340. New York: IEEE.
El Asmar, M., G. E. Gibson Jr., D. Ramsey, A. Yussef, and Z. U. Din. 2018. The maturity and accuracy of front end engineering design (FEED) and its impact on project performance. Austin, TX: Construction Industry Institute.
Eldosouky, I. A., A. H. Ibrahim, and H. E. Mohammed. 2014. “Management of construction cost contingency covering upside and downside risks.” Alexandria Eng. J. 53 (4): 863–881. https://doi.org/10.1016/j.aej.2014.09.008.
Elghaish, F., S. Abrishami, M. R. Hosseini, S. Abu-Samra, and M. Gaterell. 2019. “Integrated project delivery with BIM: An automated EVM-based approach.” Autom. Constr. 106 (Oct): 102907. https://doi.org/10.1016/j.autcon.2019.102907.
Erez, S., and J. Sloan. 2017. “Case study: Using ISO 20000 to supplement earned value management.” In Proc., 2017 AACE Int. Transactions, EVM-2552. Morgantown, WV: American Association of Cost Engineering.
Farok, G., and J. A. Garcia. 2015. “Developing group leadership and communication skills for monitoring EVM in project management.” J. Mech. Eng. 45 (1): 53–60. https://doi.org/10.3329/jme.v45i1.24385.
Finefield, T. 2013a. “Earned value management guidelines: Accounting considerations, analysis and management reports, revisions and data maintenance.” Coll. Perform. Manage. 2: 7–18.
Finefield, T. 2013b. “Earned value management guidelines: Organization and planning, scheduling and budgeting.” Coll. Perform. Manage. 1: 5–13.
Fleming, Q. W., and C. W. Ervin. 1962. “Management aids for program control.” Aerosp. Manage. 5 (7): 26–30.
Fleming, Q. W., and J. M. Koppelman. 2010. Earned value project management. Newton Square, PA: Project Management Institute.
Frahm, V. L. 2012. “Designing a tailored earned value management system (EVMS).” In Proc., 2012 AACE Int. Transactions, EVM.1059. Morgantown, WV: American Association of Cost Engineering.
Frank, M., D. Kester, and K. Urschel. 2017. “The power of data: New thinking and technology can keep EVMS relevant.” Defense Acquisition Magazine, May 1, 2017.
GAO (Government Accountability Office). 2009. Cost estimating and assessment guide: Best practices for developing and managing capital program costs. Washington, DC: GAO.
GAO (Government Accountability Office). 2019. Cost and schedule performance of large facilities construction projects and opportunities to improve project management. Washington, DC: GAO.
Gareis, R., and M. Huemann. 2000. “Project management competences in the project-oriented organization.” In Vol. 3 of Gower handbook of project management. Aldershot, UK: Gower Publishing.
Garrett, G. A., and R. G. Rendon. 2006. US military program management: Lessons learned and best practices. San Francisco: Berrett-Koehler Publishers.
Giammalvo, P. D. 2012. “Real time’ performance reporting using earned value for the mining sector.” In Proc., 2012 AACE Int. TCM Conf. Transactions, EVM.1179. Morgantown, WV: American Association of Cost Engineering.
Gibson, G. E. J., M. El Asmar, and N. Cho. 2019. Project definition rating index: Maturity and accuracy total rating system (PDRI MATRS). Austin, TX: Construction Industry Institute.
Gonzales, M. T. 2016. “Implementing project controls: Preparing for the establishment of the integrated (cost and schedule) performance measurement baseline.” Coll. Perform. Manage. 2: 17–24.
Graham, D. 2018. “Cost risk management.” Coll. Perform. Manage. 1: 9–12.
Griffith, A., and G. E. Gibson Jr. 2001. “Alignment during preproject planning.” J. Manage. Eng. 17 (2): 69–76. https://doi.org/10.1061/(ASCE)0742-597X(2001)17:2(69).
Gupta, R. 2014. “Earned value management system.” Int. J. Emerging Eng. Res. Technol. 2 (4): 160–165.
Gustavus, R. L., and K. Hunter. 2012. “How the department of defense determines if EVM should be required and what contractual requirements are necessary if the answer is ‘yes.’” Coll. Perform. Manage. 1: 22–30.
Hammad, M. W., A. Abbasi, and M. J. Ryan. 2018. “Developing a novel framework to manage schedule contingency using theory of constraints and earned schedule method.” J. Constr. Eng. Manage. 144 (4): 04018011. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001178.
Hamzeh, A. M., and S. M. Mousavi. 2019. “A new fuzzy approach for project time assessment under uncertain conditions.” In Proc., 2019 15th Iran Int. Industrial Engineering Conf. (IIIEC), 76–80. New York: IEEE.
Hendiani, S., M. Bagherpour, A. Mahmoudi, and H. Liao. 2020. “Z-number based earned value management (ZEVM): A novel pragmatic contribution towards a possibilistic cost-duration assessment.” Comput. Ind. Eng. 143 (May): 106430. https://doi.org/10.1016/j.cie.2020.106430.
Hernández, J. I. M., J. R. O. Olaso, and J. R. Gómez. 2013. “Technical performance based earned value as a management tool for engineering projects.” Chap. 7 in Engineering management, 143–166. London: Intechopen.
Heron, R. A., E. T. White, J. D. Ritschel, and C. G. Keaton. 2015. “Forecasting DoD mid-acquisition space program EACs using WBS level 2 and 3 data.” Coll. Perform. Manage. 3: 9–14.
Humphrey, W. S. 1989. Managing the software process. Boston: Addison-Wesley Longman.
Humphreys, G. C. 2016. “EVMS—After the evolution: The long slow road.” Coll. Perform. Manage. 1: 19–22.
Humphreys, G. C. 2018. Project management using earned value. Irvine, CA: Humphreys & Associates.
Hunter, H., R. Fitzgerald, and D. Barlow. 2014. “Improved cost monitoring and control through the earned value management system.” Acta Astronaut. 93 (Jan): 497–500. https://doi.org/10.1016/j.actaastro.2012.09.010.
Infanti, M. 2011. “How to estimate and use management reserve in an earned value management system (EVMS).” Coll. Perform. Manage. 4: 32–37.
ISO. 2018. Earned value management in project and programme management. Geneva: ISO.
Jaeger, T. W. 2014. “Why earned value metrics sometimes deceive management.” In Proc., 2014 AACE Int. Transactions, EVM.1556. Morgantown, WV: American Association of Cost Engineering.
Jung, Y., B. S. Moon, and J. Y. Kim. 2011. “EVMS for nuclear power plant construction: Variables for theory and implementation.” In Proc., Computing in Civil Engineering, 728–735. Reston, VA: ASCE.
Kerby, J., M. Forbes, and S. Terrell. 2017. “Cutting the cost of earned value management.” Defense Acquisition Magazine, April 10, 2017.
Kerkhove, L.-P., and M. Vanhoucke. 2017. “Extensions of earned value management: Using the earned incentive metric to improve signal quality.” Int. J. Project Manage. 35 (2): 148–168. https://doi.org/10.1016/j.ijproman.2016.10.014.
Kersbergen, J. 2011. “The challenge for earned value in commercial industry.” Coll. Perform. Manage. 1: 18–20.
Kerzner, H. 2017. Project management: A systems approach to planning, scheduling, and controlling. New York: Wiley.
Kester, D., D. Cottrell, and K. Carney. 2015. “Data driven EVMS compliance: An analytical approach that will transform the way we think about managing.” Coll. Perform. Manage. 2: 7–13.
Khamooshi, H., and A. Abdi. 2017. “Project duration forecasting using earned duration management with exponential smoothing techniques.” J. Manage. Eng. 33 (1): 04016032. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000475.
Khamooshi, H., and H. Golafshani. 2014. “EDM: Earned Duration Management, a new approach to schedule performance management and measurement.” Int. J. Project Manage. 32 (6): 1019–1041. https://doi.org/10.1016/j.ijproman.2013.11.002.
Kim, B.-C. 2015. “Dynamic control thresholds for consistent earned value analysis and reliable early warning.” J. Manage. Eng. 31 (5): 04014077. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000309.
Kim, B.-C. 2016. “Probabilistic evaluation of cost performance stability in earned value management.” J. Manage. Eng. 32 (1): 04015025. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000383.
Kim, B.-C., and H. J. Kim. 2014. “Sensitivity of earned value schedule forecasting to S-curve patterns.” J. Constr. Eng. Manage. 140 (7): 04014023. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000856.
Kim, B.-C., and J. K. Pinto. 2019. “What CPI=0.85 really means: A probabilistic extension of the estimate at completion.” J. Manage. Eng. 35 (2): 04018059. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000671.
Kim, B.-C., and K. F. Reinschmidt. 2010. “Probabilistic forecasting of project duration using Kalman filter and the earned value method.” J. Constr. Eng. Manage. 136 (8): 834–843. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000192.
Kim, B.-C., and K. F. Reinschmidt. 2011. “Combination of project cost forecasts in earned value management.” J. Constr. Eng. Manage. 137 (11): 958–966. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000352.
Kim, E., W. G. Wells Jr., and M. R. Duffey. 2003. “A model for effective implementation of earned value management methodology.” Int. J. Project Manage. 21 (5): 375–382. https://doi.org/10.1016/S0263-7863(02)00049-2.
King, J. S. 2018. “Methodologies for implementing program controls: Strategic methodologies for implementing program controls in change resistant defense contracting environments.” Master’s thesis, College of Business, Wilmington Univ.
Kranz, G. M. 2017. “Intelligently linking information for better performance management across industry and government.” Coll. Perform. Manage. 4: 11–13.
Kratzert, K., and J. R. Houser. 2011. “Cost of earned value management.” Coll. Perform. Manage. 3: 12–14.
Kwak, Y. H., and F. T. Anbari. 2012. “History, practices, and future of earned value management in government: Perspectives from NASA.” Project Manage. J. 43 (1): 77–90. https://doi.org/10.1002/pmj.20272.
Lappenbusch, C. F. J. 2017. “Misuse of earned value management results in erroneous conclusions.” In Proc., CCP EVP PSP, 2017 AACE Int. Transactions, EVM-2471. Morgantown, WV: American Association of Cost Engineering.
Laqua, R. 2018. “Why compliance needs to change.” Coll. Perform. Manage. 1: 13–19.
Lee, J.-S. 2016. “Estimating cumulative damages due to disruptions in repetitive construction.” J. Constr. Eng. Manage. 142 (11): 04016064. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001184.
Leon, H., H. Osman, M. Georgy, and M. Elsaid. 2018. “System dynamics approach for forecasting performance of construction projects.” J. Manage. Eng. 34 (1): 04017049. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000575.
Liggett, W., H. Hunter, and M. Jones. 2017. “Navigating an earned value management validation led by NASA: A contractor’s perspective and helpful hints.” In Proc., 2017 IEEE Aerospace Conf., 1–28. New York: IEEE.
Liggett, W., H. Hunter, and M. Jones. 2019. “So you passed an earned value management government validation-now what?” In Proc., 2019 IEEE Aerospace Conf., 1–10. New York: IEEE.
Lipke, W. 2011a. “Is something missing from project management.” Coll. Perform. Manage. 1: 23–28.
Lipke, W. 2011b. “Schedule adherence and rework.” Coll. Perform. Manage. 1: 9–18.
Lipke, W. 2019. “Earned schedule forecasting method selection.” Coll. Perform. Manage. 1: 21–28.
Lofgren, E. M. 2017. “Trust, but verify: An improved estimating technique using the integrated master schedule (IMS).” Coll. Perform. Manage. 4: 29–36.
Lorenz, A., H. S. Bosch, and K. Kuttler. 2012. “Implementation of earned value management tools in the Wendelstein 7-X project.” IEEE Trans. Plasma Sci. 40 (12): 3560–3565. https://doi.org/10.1109/TPS.2012.2220784.
Lucas, D. A. 2012. “Increasing project controls impact on a successful project.” In Vol. 54 of Proc., AACE Int., Cost Engineering. Morgantown, WV: American Association of Cost Engineering.
Lukas, A. J. 2018. “How to successfully use earned value on projects.” In Vol. 60 of Proc., Cost Engineering. Morgantown, WV: American Association of Cost Engineering.
Ma, X., and B. Yang. 2012. “Optimization study of earned value method in construction project management.” In Proc., 2012 Int. Conf. on Information Management, Innovation Management and Industrial Engineering, 201–204. New York: IEEE.
Mahmoudi, A., M. Bagherpour, and S. A. Javed. 2019. “Grey earned value management: Theory and applications.” IEEE Trans. Eng. Manage. 68 (6): 1703–1721. https://doi.org/10.1109/TEM.2019.2920904.
Martens, A., and M. Vanhoucke. 2017. “A buffer control method for top-down project control.” Eur. J. Oper. Res. 262 (1): 274–286. https://doi.org/10.1016/j.ejor.2017.03.034.
Martens, A., and M. Vanhoucke. 2020. “Integrating corrective actions in project time forecasting using exponential smoothing.” J. Manage. Eng. 36 (5): 04020044. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000806.
Martinelli, R., and J. Waddell. 2014. “A program management decision process.” Coll. Perform. Manage. 4: 7–16.
Marzouk, M., and M. Hisham. 2014. “Implementing earned value management using bridge information modeling.” KSCE J. Civ. Eng. 18 (5): 1302–1313. https://doi.org/10.1007/s12205-014-0455-9.
McGrath, M. T. 2012. “Earned value management: Transitioning from discouragement to a glimmer of hope.” In Proc., 2012 IEEE Aerospace Conf., 1–11. New York: IEEE.
McGregor, J. S. 2019a. Department of defense earned value management implementation guide (EVMIG). Arlington, VA: Department of Defense.
McGregor, J. S. 2019b. Department of defense earned value management system interpretation guide (EVMSIG). Arlington, VA: Department of Defense.
McNamee, E. M., C. E. Hanner, and C. W. Immonen. 2017. “Improving EVMS compliance through data integration.” In Proc., 2017 AACE Int. Transactions, EVM-2581. Morgantown, WV: American Association of Cost Engineering.
McNamee, E. M., and C. W. Immonen. 2019. “Use of earned value management as a communication tool with the project team and the client.” In Proc., 2019 AACE Int. Transactions, EVM-3155. Morgantown, WV: American Association of Cost Engineering.
Melamed, D., and R. C. Plumery. 2015. “A critical analysis of the ANSI/EIA standard for EVMS and the TCM framework.” In Proc., 2015 AACE Int. Transactions, EVM.2041. Morgantown, WV: American Association of Cost Engineering.
Miguel, A., W. Madria, and R. Polancos. 2019. “Project management model: Integrating earned schedule, quality, and risk in earned value management.” In Proc., 2019 IEEE 6th Int. Conf. on Industrial Engineering and Applications (ICIEA), 622–628. New York: IEEE.
Mishakova, A., A. Vakhrushkina, V. Murgul, and T. Sazonova. 2016. “Project control based on a mutual application of pert and earned value management methods.” Procedia Eng. 165 (Jan): 1812–1817. https://doi.org/10.1016/j.proeng.2016.11.927.
Morad, M., and S. M. El-Sayegh. 2016. “Use of earned value management in the UAE construction industry.” In Proc., 2016 Int. Conf. on Industrial Engineering, Management Science and Application (ICIMSA), 1–5. New York: IEEE.
Morin, B. J. 2016. “How it all began: The creation of earned value and the evolution of C/SPCS and C/SCSC.” Coll. Perform. Manage. 1: 15–17.
Mortaji, S. T. H., R. Noorossana, and M. Bagherpour. 2015. “Project completion time and cost prediction using change point analysis.” J. Manage. Eng. 31 (5): 04014086. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000329.
Naderpour, A., and M. Mofid. 2011. “Improving construction management of an educational center by applying earned value technique.” Procedia Eng. 14 (Jan): 1945–1952. https://doi.org/10.1016/j.proeng.2011.07.244.
Narbaev, T., and A. De Marco. 2014. “An earned schedule-based regression model to improve cost estimate at completion.” Int. J. Project Manage. 32 (6): 1007–1018. https://doi.org/10.1016/j.ijproman.2013.12.005.
NASA (National Aeronautics and Space Administration). 2018a. Earned value management (EVM) implementation handbook. Washington, DC: NASA.
NASA (National Aeronautics and Space Administration). 2018b. Earned value management reference guide for project-control account managers. Washington, DC: NASA.
NDIA (National Defense Industrial Association). 2016. ANSI/EIA 748 earned value management system acceptance guide. Arlington, VA: Integrated Program Management Division.
NDIA (National Defense Industrial Association). 2018a. Earned value management systems EIA-748-D intent guide. Arlington, VA: Integrated Program Management Division.
NDIA (National Defense Industrial Association). 2018b. Earned value management systems application guide. Arlington, VA: Integrated Program Management Division.
NDIA (National Defense Industrial Association). 2020. Earned value management system guideline scalability guide. Arlington, VA: Integrated Program Management Division.
Netto, J. T., N. L. F. de Oliveira, A. P. A. Freitas, and J. A. N. dos Santos. 2020. “Critical factors and benefits in the use of earned value management in construction.” Braz. J. Oper. Prod. Manage. 17 (1): 1–10. https://doi.org/10.14488/BJOPM.2020.007.
Nizam, A., and A. Elshannaway. 2019. “Review of earned value management (EVM) methodology, its limitations, and applicable extensions.” J. Manage. Eng. Integr. 12 (1): 59–70.
Nouban, F., N. Alijl, and M. Tawalbeh. 2020. “Integrated earned value analysis and their impact on project success.” Int. J. Adv. Eng. Sci. Appl. 1 (1): 34–39. https://doi.org/10.47346/ijaesa.v1i1.18.
Oien, A. M. L. 2015. “EVM and agile: Complementary control loops of a project management system.” Coll. Perform. Manage. 3: 17–25.
Ong, H. Y., C. Wang, and N. Zainon. 2018. “Developing a quality-embedded EVM tool to facilitate the iron triangle in architectural, construction, and engineering practices.” J. Constr. Eng. Manage. 144 (9): 04018079. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001533.
Orgut, R. E., M. Batouli, J. Zhu, A. Mostafavi, and E. J. Jaselskis. 2020. “Critical factors for improving reliability of project control metrics throughout project life cycle.” J. Manage. Eng. 36 (1): 04019033. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000710.
Pajares, J., and A. Lopez-Paredes. 2011. “An extension of the EVM analysis for project monitoring: The cost control index and the schedule control index.” Int. J. Project Manage. 29 (5): 615–621. https://doi.org/10.1016/j.ijproman.2010.04.005.
Picornell, M., E. Pellicer, C. Torres-Machí, and M. Sutrisna. 2017. “Implementation of earned value management in unit-price payment contracts.” J. Manage. Eng. 33 (3): 06016001. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000500.
Plemmons, M. E., and T. R. Hodges. 2011. “Transforming earned value management through systems integration.” In Proc., 2011 AACE Int. Transactions, EVM-520. Morgantown, WV: American Association of Cost Engineering.
PMI (Project Management Institute). 2013. Organizational project management maturity model (OPM3) knowledge foundation. Newtown Square, PA: Project Management Institute.
PMI (Project Management Institute). 2017. PMI Lexicon of project management terms. Newtown Square, PA: Project Management Institute.
PMI (Project Management Institute). 2018. The standard for organizational project management. Newtown Square, PA: Project Management Institute.
PMI (Project Management Institute). 2019a. The standard for earned value management. Newtown Square, PA: Project Management Institute.
PMI (Project Management Institute). 2019b. The standard for risk management in portfolios, programs and projects. Newtown Square, PA: Project Management Institute.
Ramahatra, N. 2011. “Small projects, big savings by implementing best practices with earned value management (lessons learned).” Coll. Perform. Manage. 3: 17–24.
Rezouki, S. E., and S. B. Mortadha. 2020. “The factors affecting on earned value management.” IOP Conf. Ser.: Mater. Sci. Eng. 901 (1): 012023. https://doi.org/10.1088/1757-899X/901/1/012023.
Richey, K. A. 2017. GAO best practice guides light the way. Fort Belvoir, VA: Defense Acquisition University Press.
Rowe, F. 2014. “What literature review is not: Diversity, boundaries and recommendations.” Eur. J. Inf. Syst. 23 (3): 241–255. https://doi.org/10.1057/ejis.2014.7.
Rybina, E., D. Skorobogatov, S. T. Regan, and J. K. Owen. 2015. “CIS: Utilization of earned value management for monitoring production facilities.” In Proc., 2015 AACE Int. Transactions, EVM-1848. Morgantown, WV: American Association of Cost Engineering.
Scheepbouwer, E., A. Ezz, B. Guo, and D. V. Der Walt. 2018. “Risk management and the effects on project success.” In Proc., Construction Research Congress 2018, 460–470. Reston, VA: ASCE.
Shi, H. 2019. “Accurate quantity update: A key for project management success.” In Proc., CCP PSP, 2019 AACE Int. Transactions, TCM-A3106. Morgantown, WV: American Association of Cost Engineering.
Siu, M.-F., and M. Lu. 2011. “Scheduling simulation-based techniques for earned value management on resource-constrained schedules under delayed scenarios.” In Proc., 2011 Winter Simulation Conf. (WSC), 3455–3466. New York: IEEE.
Solomon, P. J., and R. R. Young. 2007. Performance-based earned value. New York: Wiley.
Song, J., A. Martens, and M. Vanhoucke. 2020. “The impact of a limited budget on the corrective action taking process.” Eur. J. Oper. Res. 286 (3): 1070–1086. https://doi.org/10.1016/j.ejor.2020.03.069.
Sowers, D., and H. Jarnagan. 2019. “Program management lessons learned: Alaskan way viaduct replacement program.” In Proc., 2019 AACE International Transactions, PM-3105. Morgantown, WV: American Association of Cost Engineering.
Steege, A. W. V. D. 2019. “Unpacking earned value management for oil and gas projects.” In Proc., CCP, 2019 AACE International Transactions, EVM-3165. Morgantown, WV: American Association of Cost Engineering.
Stratton, R. W. 2000. The EVM maturity model—EVM3. Newtown Square, PA: Project Management Institute.
Stratton, R. W. 2006. The earned value management maturity model. San Francisco: Berrett-Koehler Publishers.
Stratton, R. W. 2016. “Making EVM work in agile development projects.” Coll. Perform. Manage. 2: 7–16.
Sutrisna, M., E. Pellicer, C. Torres-Machi, and M. Picornell. 2020. “Exploring earned value management in the Spanish construction industry as a pathway to competitive advantage.” Int. J. Construct. Manage. 20 (1): 1–12. https://doi.org/10.1080/15623599.2018.1459155.
Tariq, S., N. Ahmad, M. U. Ashraf, A. M. Alghamdi, and A. S. Alfakeeh. 2020. “Measuring the impact of scope changes on project plan using EVM.” IEEE Access 8 (Aug): 154589–154613. https://doi.org/10.1109/ACCESS.2020.3018169.
Valdés-Souto, F. 2016. “Earned scope management: A case of study of scope performance using COSMIC (ISO 19761) with a real project.” In Proc., 2016 Joint Conf. of the Int. Workshop on Software Measurement and the Int. Conf. on Software Process and Product Measurement (IWSM-MENSURA), 53–64. New York: IEEE.
Vanhoucke, M. 2012. “Dynamic scheduling: Integrating schedule risk analysis with earned value management.” Coll. Perform. Manage. 2: 11–13.
Vanhoucke, M. 2017. “About academic research on earned value management inspired by the college of performance management.” Coll. Perform. Manage. 3: 28–35.
Vanhoucke, M., P. Andrade, F. Salvaterra, and B. Jordy. 2015. “Introduction to earned duration.” Coll. Perform. Manage. 2: 15–27.
Votto, R., L. Lee Ho, and F. Berssaneti. 2020. “Applying and assessing performance of earned duration management control charts for EPC project duration monitoring.” J. Constr. Eng. Manage. 146 (3): 04020001. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001765.
Walker, G. 2015. “Come back sociotechnical systems theory, all is forgiven….” Civ. Eng. Environ. Syst. 32 (1–2): 170–179. https://doi.org/10.1080/10286608.2015.1024112.
Wauters, M., and M. Vanhoucke. 2016. “A comparative study of artificial intelligence methods for project duration forecasting.” Expert Syst. Appl. 46 (Mar): 249–261. https://doi.org/10.1016/j.eswa.2015.10.008.
Wibiksana, R. 2012. “Earned value management: Adapted for use in underground mining operations.” Coll. Perform. Manage. 3: 16–19.
Willems, L. L., and M. Vanhoucke. 2015. “Classification of articles and journals on project control and earned value management.” Int. J. Project Manage. 33 (7): 1610–1634. https://doi.org/10.1016/j.ijproman.2015.06.003.
Wolf, L. D. 2014. “Project controls personnel: Finding the ‘right stuff’.” Coll. Perform. Manage. 3: 9–14.
Yussef, A., G. E. Gibson Jr., M. El Asmar, and D. Ramsey. 2019. “Quantifying FEED maturity and its impact on project performance in large industrial projects.” J. Manage. Eng. 35 (5): 04019021. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000702.
Zhan, Z., C. Wang, J. B. H. Yap, S. Samsudin, and H. Abdul-Rahman. 2019. “Earned value analysis, implementation barriers, and maturity level in oil & gas production.” S. Afr. J. Ind. Eng. 30 (4): 44–59. https://doi.org/10.7166/30-4-2030.

Information & Authors

Information

Published In

Go to Journal of Management in Engineering
Journal of Management in Engineering
Volume 38Issue 3May 2022

History

Published online: Feb 3, 2022
Published in print: May 1, 2022
Discussion open until: Jul 3, 2022

Authors

Affiliations

Ph.D. Candidate, School of Sustainable Engineering and the Built Environment, Arizona State Univ., Tempe, AZ 85287-3005 (corresponding author). ORCID: https://orcid.org/0000-0002-1631-5360. Email: [email protected]
Hala Sanboskani, S.M.ASCE [email protected]
Ph.D. Student, School of Sustainable Engineering and the Built Environment, Arizona State Univ., Tempe, AZ 85287-3005. Email: [email protected]
G. Edward Gibson Jr., Ph.D., Dist.M.ASCE [email protected]
P.E.
Professor, School of Sustainable Engineering and the Built Environment, Arizona State Univ., Tempe, AZ 85287-3005. Email: [email protected]
Associate Professor and Co-Director, National Center of Excellence on SMART Innovations, School of Sustainable Engineering and the Built Environment, Arizona State Univ., Tempe, AZ 85287-3005. ORCID: https://orcid.org/0000-0003-0011-6903. Email: [email protected]
Namho Cho, Ph.D., S.M.ASCE [email protected]
Design Project Manager, Design & Construction, Univ. of Iowa, Iowa City, IA 52240. Email: [email protected]

Metrics & Citations

Metrics

Citations

Download citation

If you have the appropriate software installed, you can download article citation data to the citation manager of your choice. Simply select your manager software from the list below and click Download.

Cited by

  • End-Users Engagement for Enacting Value of Complex Projects: An Ecological Perspective, Journal of Management in Engineering, 10.1061/JMENEA.MEENG-5724, 40, 3, (2024).
  • Linear Methods for Estimating Schedule Time Earned: Theory and Application, Journal of Management in Engineering, 10.1061/JMENEA.MEENG-5618, 40, 1, (2024).
  • Green and Sustainable Construction Industry: A Systematic Literature Review of the Contractor’s Green Construction Capability, Buildings, 10.3390/buildings13020470, 13, 2, (470), (2023).
  • Novel Earned Value Management System Maturity Framework and Its Relation to Project Performance, Journal of Construction Engineering and Management, 10.1061/JCEMD4.COENG-12985, 149, 6, (2023).
  • Employing Technology to Enable Remote Research Charrettes as a Method for Engaging Industry and Uncovering Best Practices: A Novel Approach for a Post-COVID-19 World, Journal of Construction Engineering and Management, 10.1061/(ASCE)CO.1943-7862.0002375, 148, 11, (2022).

View Options

Media

Figures

Other

Tables

Share

Share

Copy the content Link

Share with email

Email a colleague

Share