Technical Papers
Aug 11, 2021

Project Validation: A Set-Based and Concurrent Design Approach to Inform Owner’s Authorization Decision on Complex Projects

Publication: Journal of Construction Engineering and Management
Volume 147, Issue 10

Abstract

Strictly speaking, there is no way to have certainty of the outcomes or the value of decisions made early in a project. However, early decisions set the path to cost and schedule performance and influence life cycle costs. This study explored project validation as a novel set-based and concurrent design practice during the conceptual phase of complex projects. Because the construction literature obviates set-based design, a grounded theory method was leveraged to elicit a theoretical model that gave primacy to contextual and inductive evidence. The emerging theory guided the data collection, which included interviews, three expert workshops, and observations at validation sessions. Project validation aims at proving or disproving with null design whether the team can deliver a project that satisfies the owner’s business case and scope within the owner’s allowable constraints of costs, schedule, and acceptable risks. Also, it defines the basis of design and target costs and informs the owner’s decision to authorize (go) or not to authorize (no-go) the project. As a departure from the existing literature rooted in point-based design and programming approaches, decisions on concurrent sets of cross-functional design alternatives are purposely delayed during project validation. In doing so, the accumulation of additional information will, later on, enable the team to make design decisions with a systems engineering and value-adding perspective that drives innovation. The results of this study contribute to the advancement of design theory methodology and project definition.

Get full access to this article

View all available purchase options and get full access to this article.

Data Availability Statement

Some or all data, models, or code used during the study were provided by third-party organizations. Direct requests for these materials may be made to the provider as indicated in the Acknowledgments.

Acknowledgments

The authors want to acknowledge and thank the Lean Construction Institute (LCI) for the sponsorship and support of all the aspects of this research. The authors also want to thank all the subject matter experts that supported this research effort.

References

AIA-AGC Project Delivery Primer Task Force. 2011. Primer on project delivery. Washington, DC: American Institute of Architects.
Allison, M., H. Ashcraft, R. Cheng, S. Klawens, and J. Pease. 2018. “Integrated project delivery: An action guide for leaders.” In Integrated project delivery alliance (IPDA), center for innovation in the design and construction industry (CIDCI). London: Charles Pankow Foundation.
Anderson, S., K. Molenaar, and C. Schexnayder. 2007. Guidance for cost estimation and management for highway projects during planning, programming, and preconstruction. Washington, DC: Transportation Research Board.
Back, E., and D. Grau. 2013. “Improving the predictability of project outcomes.” In Research summary 291-1. Austin, TX: Construction Industry Institute.
Ballard, G. 2008. “The lean project delivery system: An update.” Lean Construct. J. 2008 (Apr): 1–19.
Ballard, G., and A. Pennanen. 2013. “Conceptual estimating and target costing.” In Proc., 21st Int. IGLC Conf., 218–226. Torgarden, Norway: International Group for Lean Construction.
Ballard, G., and P. Reiser. 2004. “The St. Olaf College Fieldhouse Project: A case study in designing to target cost.” In Proc., 12th Annual Conf. of the Int. Group for Lean Construction, 234–249. Torgarden, Norway: International Group for Lean Construction.
Chiyoda Corporation. 2021. “FEED (front end engineering design).” Accessed March 3, 2021. https://www.chiyodacorp.com/en/service/ple/feed/.
Corbin, J., and A. L. Strauss. 2008. Basics of qualitative research: Techniques and procedures for developing grounded theory. 3rd ed. Los Angeles: Sage.
Daub, M., and F. Duddeck. 2019. “Maximizing flexibility for complex systems design to compensate lack-of-knowledge uncertainty.” J. Risk Uncertainty Eng. Syst. 5 (4): 4. https://doi.org/10.1115/1.4044045.
Denzin, N., and Y. Lincoln. 2000. Handbook of qualitative research. 2nd ed. Los Angeles: Sage.
Do, D., C. Chen, G. Ballard, and I. D. Tommelein. 2014. “Target value design as a method for controlling project cost overruns.” In Proc., 22nd Annual Conf. of the Int. Group for Lean Construction, 171–181. Torgarden, Norway: International Group for Lean Construction.
El Asmar, M., G. E. Gibson, D. Ramsey, A. Yussef, and Z. Ud Din. 2018. The maturity and accuracy of front end engineering design (FEED) and its impact on project performance. Austin, TX: Construction Industry Institute.
El Asmar, M., A. Hanna, and W. Loh. 2013. “Quantifying performance for the integrated project delivery system as compared to established delivery systems.” J. Constr. Eng. Manage. 139 (11): 04013012. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000744.
El Asmar, M., A. Hanna, and G. Whited. 2011. “New approach to developing conceptual cost estimates for highway projects.” J. Constr. Eng. Manage. 137 (11): 942–949. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000355.
Eppinger, S., and T. Browning. 2012. Design structure matrix methods and applications. Cambridge, MA: MIT Press.
Flyvbjerg, B. 2006. “From Nobel prize to project management: Getting risks right.” Project Manage. J. 37 (3): 5–15. https://doi.org/10.1177/875697280603700302.
Flyvbjerg, B., M. Holm, and S. Buhl. 2003. “How common and how large are cost overruns in transport infrastructure projects?” Transp. Rev. 23 (1): 71–88. https://doi.org/10.1080/01441640309904.
Gibson, E. 1996. PDRI: Project definition ratio index industrial projects. Austin, TX: Construction Industry Institute.
Gil, N., B. Kirkendall, D. Tommelein, and G. Ballard. 2000. “Lean product-process development process to support contractor involvement during design.” Comput. Civ. Build. Eng. 2000 (1): 1086–1093. https://doi.org/10.1061/40513(279)141.
Glaser, B. G. 1978. Theoretical sensitivity: Advances in methodology of grounded theory. Mill Valley, CA: Sociological Press.
Glaser, B. G. 1992. Basics of grounded theory analysis. Mill Valley, CA: Sociological Press.
Glaser, B. G., and A. L. Strauss. 1967. The discovery of grounded theory: Strategies for qualitative research. New York: Aldine Publishing Company.
Grau, D., E. Back, A. Abbaszadegan, and R. Sirven. 2014. The predictability index-A novel project performance metric to assess the early prediction of cost and time outcomes. Reston, VA: ASCE.
Grau, D., and W. Back. 2015. “The predictability index: Novel metric to assess cost and schedule performance.” J. Constr. Eng. Manage. 141 (12): 04015043. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000994.
Grau, D., W. E. Back, and N. Hossain. 2016. “Influence of risk and change events on cost, schedule, and predictability performances.” J. Civ. Eng. Educ. 142 (4): 04016006. https://doi.org/10.1061/(ASCE)EI.1943-5541.0000284.
Grau, D., F. Cruz-Rios, and R. Sherman. 2019. Project validation—A guide to improving owner value and team performance. Tempe, AZ: Arizona State Univ.
Griffith, A., G. E. Gibson, M. Hamilton, A. Tortora, and C. Wilson. 1999. “Project success index for capital facility construction projects.” J. Perform. Constr. Facil. 13 (1): 39–45. https://doi.org/10.1061/(ASCE)0887-3828(1999)13:1(39).
Hamilton, M., and G. Gibson. 1996. “Benchmarking preproject planning effort.” J. Manage. Eng. 12 (2): 25–33. https://doi.org/10.1061/(ASCE)0742-597X(1996)12:2(25).
Hari, A., S. Shoval, and J. Kasser. 2008. “Conceptual design to cost: A new systems engineering tool.” In Proc., 18th Annual Int. Symp. of INCOSE, 6th Biennial European Systems Engineering Conf. Utrecht, Holland: International Council on Systems Engineering. https://doi.org/10.1002/j.2334-5837.2008.tb00826.x.
He, X., R. Liu, and C. Anumba. 2021. “Data-driven insights on the knowledge gaps of conceptual cost estimation modeling.” J. Constr. Eng. Manage. 147 (2): 04020165. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001963.
Jarde, A., and S. Alkass. 2007. “Computer-integrated system for estimating the costs of building project.” J. Constr. Eng. Manage. 13 (4): 205–223. https://doi.org/10.1061/(ASCE)1076-0431(2007)13:4(205).
Kahneman, D., and D. Lovallo. 1993. “Timid choices and bold forecasts: A cognitive perspective on risk taking.” Manage. Sci. 39 (1): 17–31. https://doi.org/10.1287/mnsc.39.1.17.
Kennedy, B. M., D. K. Sobek, and M. N. Kennedy. 2013. “Reducing rework by applying set-based practices early in the systems engineering process.” Syst. Eng. 17 (3): 278–296. https://doi.org/10.1002/sys.21269.
Kim, B. C., and K. F. Reinschmidt. 2010. “Probabilistic forecasting of project duration using Kalman filter and the earned value method.” J. Constr. Eng. Manage. 136 (8): 834–843. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000192.
Kim, B. C., and K. F. Reinschmidt. 2011. “Combination of project cost forecasts in earned value management.” J. Constr. Eng. Manage. 137 (11): 958–966. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000352.
Lane, R., and G. Woodman. 2000. “‘Wicked problems, righteous solutions’ back to the future on large complex projects.” In Proc., 9th Annual Conf. Int. Group for Lean Construction, 1–12. Torgarden, Norway: International Group for Lean Construction.
Martin, P. Y., and B. A. Turner. 1986. “Grounded theory and organizational research.” J. Appl. Behavioral Sci. 22 (2): 141–157.
McDevitt, C. A., E. C. Cahill, and C. Stambaugh. 2004. “System-level application of the evolutionary product development process to manufactured goods.” Syst. Eng. 7 (2): 144–152. https://doi.org/10.1002/sys.20000.
Meier, C., A. Yassine, and T. Browning. 2007. “Design process sequencing with competent genetic algorithms.” J. Mech. Des. 129 (6): 566–585. https://doi.org/10.1115/1.2717224.
Mulva, S. P., and J. Dai. 2012. Performance assessment. Austin, TX: Univ. of Texas at Austin.
National Academy Press. 2001. Progress in improving project management at the department of energy: 2001 assessment. Washington, DC: National Academies Press.
NCMS (National Center for Manufacturing Sciences). 2000. Product development process—Methodology and performance measures. Ann Arbor, MI: NCMS.
Oberlender, G., and S. Trost. 2001. “Predicting accuracy of early cost estimates based on estimate quality.” J. Constr. Eng. Manage. 127 (3): 173–182. https://doi.org/10.1061/(ASCE)0733-9364(2001)127:3(173).
Oberlender, G. D. 2009. “Quantitative prediction of estimate accuracy.” In Research summary, 131. Austin, TX: Construction Industry Institute.
Orlikowski, W. T. 1993. “CASE tools as organizational change: Investigating incremental and radical changes in systems development.” MIS Quart. 17 (3): 309–340.
Pettigrew, A. M. 1990. “Longitudinal field research on change: Theory and practice.” Organ. Sci. 1 (3): 267–292.
Sobek, D., A. C. Ward, and J. K. Liker. 1999. “Toyota’s principles of set-based concurrent engineering.” Sloan Manage. Rev. 40 (2): 31–40.
Strauss, A. 1987. Qualitative analysis for social scientists. Cambridge, UK: Cambridge University Press.
Tuholski, S., and I. Tommelein. 2010. “Design structure matrix implementation on a seismic retrofit.” J. Manage. Eng. 26 (3): 144–152. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000016.
Urquhart, C. 2013. Grounded theory for qualitative research: A practical guide. Los Angeles: Sage.
Wimpenny, P., and J. Gass. 2000. “Interviewing in phenomenology and grounded theory: Is there a difference?” J. Adv. Nurs. 31 (6): 1485–1492. https://doi.org/10.1046/j.1365-2648.2000.01431.x.
Yassine, A. A., D. E. Whitney, J. Lavine, and T. Zambito. 2000. “Do-it-right first-time (DRFT) approach to design structure matrix (DSM) restructuring.” In Proc., ASME 2000 Int. Design Engineering Technical Conf. New York: American Society of Mechanical Engineers.
Yussef, A., G. Gibson, M. Asmar, and D. Ramsey. 2019. “Quantifying FEED maturity and its impact on project performance in large industrial projects.” J. Manage. Eng. 35 (5): 4019021. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000702.
Yussef, A., G. Gibson, D. Ramsey, and M. Asmar. 2018. “Front end engineering design (FEED) for large industrial projects: FEED maturity and its impact on project cost and schedule performance.” Constr. Res. Congr. 2018 (1): 1–8. https://doi.org/10.1061/9780784481295.001.
Zhang, S., G. Migliaccio, P. Zandbergen, and M. Guindani. 2014. “Empirical assessment of geographically based surface interpolation methods for adjusting construction cost estimates by project location.” J. Constr. Eng. Manage. 140 (6): 4014015. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000850.

Information & Authors

Information

Published In

Go to Journal of Construction Engineering and Management
Journal of Construction Engineering and Management
Volume 147Issue 10October 2021

History

Received: Sep 21, 2020
Accepted: May 21, 2021
Published online: Aug 11, 2021
Published in print: Oct 1, 2021
Discussion open until: Jan 11, 2022

Permissions

Request permissions for this article.

Authors

Affiliations

Associate Professor, School of Sustainable Engineering and the Built Environment, Arizona State Univ., P.O. Box 873005, Tempe, AZ 85287-3005 (corresponding author). ORCID: https://orcid.org/0000-0001-5530-1626. Email: [email protected]
Fernanda Cruz Rios [email protected]
Postdoctoral Associate, Swanson School of Engineering, Univ. of Pittsburgh, Pittsburgh, PA 15261. Email: [email protected]
Rachael Sherman, A.M.ASCE [email protected]
Assistant Professor, School of Engineering Technology and Construction Management, Univ. of North Carolina at Charlotte, Charlotte, NC 28223. Email: [email protected]

Metrics & Citations

Metrics

Citations

Download citation

If you have the appropriate software installed, you can download article citation data to the citation manager of your choice. Simply select your manager software from the list below and click Download.

View Options

Get Access

Access content

Please select your options to get access

Log in/Register Log in via your institution (Shibboleth)
ASCE Members: Please log in to see member pricing

Purchase

Save for later Information on ASCE Library Cards
ASCE Library Cards let you download journal articles, proceedings papers, and available book chapters across the entire ASCE Library platform. ASCE Library Cards remain active for 24 months or until all downloads are used. Note: This content will be debited as one download at time of checkout.

Terms of Use: ASCE Library Cards are for individual, personal use only. Reselling, republishing, or forwarding the materials to libraries or reading rooms is prohibited.
ASCE Library Card (5 downloads)
$105.00
Add to cart
ASCE Library Card (20 downloads)
$280.00
Add to cart
Buy Single Article
$35.00
Add to cart

Get Access

Access content

Please select your options to get access

Log in/Register Log in via your institution (Shibboleth)
ASCE Members: Please log in to see member pricing

Purchase

Save for later Information on ASCE Library Cards
ASCE Library Cards let you download journal articles, proceedings papers, and available book chapters across the entire ASCE Library platform. ASCE Library Cards remain active for 24 months or until all downloads are used. Note: This content will be debited as one download at time of checkout.

Terms of Use: ASCE Library Cards are for individual, personal use only. Reselling, republishing, or forwarding the materials to libraries or reading rooms is prohibited.
ASCE Library Card (5 downloads)
$105.00
Add to cart
ASCE Library Card (20 downloads)
$280.00
Add to cart
Buy Single Article
$35.00
Add to cart

Media

Figures

Other

Tables

Share

Share

Copy the content Link

Share with email

Email a colleague

Share