Factors Causing the Time Delay in Projects: Empirical Evidence from Pakistani Construction Industry

Publication: ICCREM 2020: Intelligent Construction and Sustainable Buildings

ABSTRACT

Construction firms are of crucial importance when it comes to the development of the nation. Given the complex web of communication and sets of preferences, the construction industry faces innumerable challenges. Of most criticalities that are commonly observed in the industry, it is the time overrun that accounts for most of the adversities faced by the construction industry of Pakistan. These factors may include communication and coordination factors, contract management factors, design and documentation factors, and finance management factors. The concurrent study aims to determine the magnitude and prioritize these designated factors upon the time overruns in the surveyed firms that may further lead to delineations such as cost overruns. To accomplish the research objectives a survey was carried out, being based upon 113 construction projects being run under supervision of respective firms. As per our deduction it was the lack of coordination in the design phase that did account for the time delays in the subjected firms. While contract management factors marked the poor project management as the leading factor to cause the time related adversities. In the similar context, design and documentation factors classified the design changes during construction as important consideration. Whereas finance management factors indicated the monthly payment difficulties from the agencies to lead to the time delay in the construction projects on the national scale. The concurrent study is of vital importance in terms of bridging the contextual gap by surveying the construction firms in a developing nation such as Pakistan. Moreover, the theoretical progression was addressed by the current study by including the designated factors cumulatively in a single model and testing for them statistically.

Get full access to this article

View all available purchase options and get full access to this chapter.

REFERENCES

Aibinu, A.A. and Jagboro, G.O. (2002). “The effects of construction delays on project delivery in Nigerian construction industry.” International Journal of Project Management, 20(8), 593-599.
Alaghbari, W.E., Razali, A., Kadir, M., Salim, A. and Ernawati. (2007). “The significant factors causing delay of building construction projects in Malaysia.” Engineering Construction and Architectural Management, 14(2), 192-206.
Assaf, S.A. and Al-Hejji, S. (2006). “Causes of delay in large construction projects.” International Journal of Project Management, 24(4), 349-357.
Chan, A.P.C. (2001). “Time cost relationship of public sector projects in Malaysia.” International Journal of Project Management, 19(4), 223-229.
Enshassi, A., Al-Najjar, J. and Kumaraswamy, M. (2009). “Delays and cost overruns in the construction projects in the Gaza Strip.” Journal of Financial Management of Property and Construction, 14(2), 126-151.
Enshassi, A., Liska, R., El-Sawalhi, N.I. and Tadwan, I. (2003). “Contributors to construction delays in Palestine.” Journal of American Institute of Constructors, 27(2), 45-53.
Famiyeh, S., Amoatey, C.T., Adaku, E. and Agbenohevi, C.S. (2017). “Major causes of construction time and cost overruns: a case of selected educational sector projects in Ghana.” Journal of Engineering, Design and Technology, 15(2), 181-198.
Faridi, A.S. and El-Sayegh, S.M. (2006). “Significant factors causing delay in the UAE construction industry.” Construction Management and Economics, 24(11), 1167-1176.
Kaliba, C., Muya, M. and Mumba, K. (2009). “Cost escalation and schedule delay in road construction projects in Zambia.” International Journal of Project Management, 27(5), 522-531.
Kaming, P.F., Olomolaiye, P.O., Holt, G.D. and Harris, F.C. (1997). “Factors influencing construction time and cost overruns on high-rise projects in Indonesia.” Construction Management and Economics, 15(1), 83-94.
Koushki, P.A., Al-Rashid, K. and Kartam, N. (2005). “Delays and cost increases in the construction of private residential projects in Kuwait.” Journal of Construction Management and Economics, 23(3), 285-294.
Maqsoom, A. and Charoenngam, C. (2014). “Motives and competitive assets of Pakistani international construction contracting firms: impact of size and international experience.” Journal of Financial Management of Property and Construction, 19(2), 138-151.
Maqsoom, A., Choudhry, R.M., Umer, M. and Mehmood, T. (2019). “Influencing factors indicating time delay in construction projects: impact of firm size and experience.” International Journal of Construction Management, (2019), 1-12.
Mezher, T.C. and Tawil, W. (1998). “Causes of delay in the construction industry in Lebanon.” Engineering Construction and Architectural Management, 5(3), 252-260.
Odeh, A.M. and Battaineh, H.T. (2002). “Causes of construction delay: traditional contracts.” International Journal of Project Management, 20(1), 67-73.
Razzaq, A., Thaheem, M.J., Maqsoom, A. and Gabriel, H.F. (2018). “Critical external risks in international joint ventures for construction industry in Pakistan.” International Journal of Civil Engineering, 16(2), 189-205.
Stumpf, G. (2000). “Schedule delay analysis.” Construction Engineering Journal, 42(7), 32-43.

Information & Authors

Information

Published In

Go to ICCREM 2020
ICCREM 2020: Intelligent Construction and Sustainable Buildings
Pages: 611 - 621
Editors: Yaowu Wang, Ph.D., Harbin Institute of Technology, Thomas Olofsson, Ph.D., Luleå University of Technology, and Geoffrey Q. P. Shen, Ph.D., Hong Kong Polytechnic University
ISBN (Online): 978-0-7844-8323-7

History

Published online: Oct 14, 2020
Published in print: Oct 14, 2020

Permissions

Request permissions for this article.

Authors

Affiliations

Ahsen Maqsoom [email protected]
Assistant Professor, Dept. of Civil Engineering, COMSATS Univ. Islamabad, Wah Campus, Wah Cantt, Pakistan (corresponding author). E-mail: [email protected]
Muhammad Umer [email protected]
Research Assistant, Dept. of Management Science, COMSATS Univ. Islamabad, Wah Campus, Wah Cantt, Pakistan. E-mail: [email protected]
Rafiq Muhammad Choudhry [email protected]
Professor, Dept. of Civil Engineering, ImamDin Univ., Dammam, Saudi Arabia. E-mail: [email protected]
Hafiz Zahoor [email protected]
Assistant Professor, Dept. of Construction Engineering Management, National Univ. of Science and Technology, Risalpur Campus, Risalpur, Pakistan. E-mail: [email protected]
Mubeenul Basharat [email protected]
Lecturer, Dept. of Computer Science, COMSATS Univ. Islamabad, Wah Campus, WahCantt, Pakistan. E-mail: [email protected]

Metrics & Citations

Metrics

Citations

Download citation

If you have the appropriate software installed, you can download article citation data to the citation manager of your choice. Simply select your manager software from the list below and click Download.

View Options

Get Access

Access content

Please select your options to get access

Log in/Register Log in via your institution (Shibboleth)
ASCE Members: Please log in to see member pricing

Purchase

Save for later Information on ASCE Library Cards
ASCE Library Cards let you download journal articles, proceedings papers, and available book chapters across the entire ASCE Library platform. ASCE Library Cards remain active for 24 months or until all downloads are used. Note: This content will be debited as one download at time of checkout.

Terms of Use: ASCE Library Cards are for individual, personal use only. Reselling, republishing, or forwarding the materials to libraries or reading rooms is prohibited.
ASCE Library Card (5 downloads)
$105.00
Add to cart
ASCE Library Card (20 downloads)
$280.00
Add to cart
Buy Single Paper
$35.00
Add to cart
Buy E-book
$194.00
Add to cart

Get Access

Access content

Please select your options to get access

Log in/Register Log in via your institution (Shibboleth)
ASCE Members: Please log in to see member pricing

Purchase

Save for later Information on ASCE Library Cards
ASCE Library Cards let you download journal articles, proceedings papers, and available book chapters across the entire ASCE Library platform. ASCE Library Cards remain active for 24 months or until all downloads are used. Note: This content will be debited as one download at time of checkout.

Terms of Use: ASCE Library Cards are for individual, personal use only. Reselling, republishing, or forwarding the materials to libraries or reading rooms is prohibited.
ASCE Library Card (5 downloads)
$105.00
Add to cart
ASCE Library Card (20 downloads)
$280.00
Add to cart
Buy Single Paper
$35.00
Add to cart
Buy E-book
$194.00
Add to cart

Media

Figures

Other

Tables

Share

Share

Copy the content Link

Share with email

Email a colleague

Share