Delays and Financial Implications of COVID-19 for Contractors in Irrigation Projects

Publication: Journal of Construction Engineering and Management
Volume 148, Issue 9

Abstract

Construction project delays are costly to stakeholders. Therefore, extensive research has been carried out in various countries covering different types of construction projects to identify delay factors and mitigation strategies. However, the literature has not documented the impact of a once-in-a-century event such as the COVID-19 pandemic on construction projects’ schedules and costs. The present study uses a case study approach to examine the effect of the COVID-19 pandemic on three lift irrigation projects’ construction programs and the financial implications for the contractor in the Indian construction industry. The findings reveal that the main factors responsible for delays due to the COVID-19 pandemic were fear of an outbreak, imposition of a nationwide lockdown, late return of workers, resource shortages, and changes in operating procedures. Furthermore, the study found that the contract conditions and government directives allowed for time extensions in construction projects by recognizing the pandemic as a force majeure. However, such provisions did not protect contractors’ financial interests. This study evaluates the financial implications of the COVID-19 pandemic for the contractor in terms of worker compensation during the lockdown, idling of resources, overhead costs, cost escalation, and liquidity.

Practical Applications

The public health crisis from the COVID-19 pandemic led to a series of preventive measures from the government and organizations worldwide that caused severe disruptions in construction projects and disturbed the construction supply chain. This study recommends rethinking the scope and coverage of force majeure and excusable delay clauses in standard construction contracts beyond provisions for an extension of time to protect the financial interests of different stakeholders. The vagueness in assessing and compensating for the losses from unprecedented events such as the COVID-19 pandemic could expose construction organizations to significant financial risks and threaten their existence in a highly competitive industry. Therefore, construction organizations should carefully review the contract provisions of future projects for proper risk allocations to accommodate unprecedented events and pandemics to help them recover successfully from various disruptions and associated financial losses. Moreover, proper communication and negotiation, a supportive and collaborative project culture, and early government interventions are crucial in dealing with such events and avoiding disputes among project stakeholders.

Get full access to this article

View all available purchase options and get full access to this article.

Data Availability Statement

Some or all data, models, or code that support the findings of this study are available from the corresponding author on reasonable request.

References

Abdellatif, H., and A. Alshibani. 2019. “Major factors causing delay in the delivery of manufacturing and building projects in Saudi Arabia.” Buildings 9 (4): 93–107. https://doi.org/10.3390/buildings9040093.
Agyekum-Mensah, G., and A. D. Knight. 2016. “The professional’s perspective on the causes of project delays in the construction industry.” Eng. Constr. Archit. Manage. 24 (5): 828–841. https://doi.org/10.1108/ECAM-03-2016-0085.
Aibinu, A. A., and H. A. Odeyinka. 2006. “Construction delays and their causative factors in Nigeria.” J. Constr. Eng. Manage. 132 (7): 667–677. https://doi.org/10.1061/(ASCE)0733-9364(2006)132:7(667).
Aigbavboa, C. O., D. O. Aghimien, W. D. Thwala, and M. N. Ngozwana. 2022. “Unprepared industry meet pandemic: COVID-19 and the South Africa construction industry.” J. Eng. Des. Technol. 20 (1): 183–200. https://doi.org/10.1108/JEDT-02-2021-0079.
Akshayah, N. K. R., and V. P. S. N. Nanyam. 2022. “COVID-19: Claims and dispute management in construction.” In Recent advancements in civil engineering. Lecture notes in civil engineering, 172, edited by B. Laishram and A. Tawalare. Singapore: Springer.
Alaghbari, W. E., M. R. A. Kadir, A. Salim, and D. Ernawati. 2007. “The significant factors causing delay of building construction projects in Malaysia.” Eng. Constr. Archit. Manage. 14 (2): 192–206. https://doi.org/10.1108/09699980710731308.
Al-Mhdawi, M. K. S., M. P. Brito, M. Abdul Nabi, I. H. El-Adaway, and B. S. Onggo. 2022. “Capturing the impact of COVID-19 on construction projects in developing countries: A case study of Iraq.” J. Manage. Eng. 38 (1): 05021015. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000991.
Alsharef, A., S. Banerjee, S. M. Uddin, A. Albert, and E. Jaselskis. 2021. “Early impacts of the COVID-19 pandemic on the United States construction industry.” Int. J. Environ. Res. Public Health 18 (4): 1559. https://doi.org/10.3390/ijerph18041559.
Amoah, C., and F. Simpeh. 2021. “Implementation challenges of COVID-19 safety measures at construction sites in South Africa.” J. Facil. Manage. 19 (1): 111–128. https://doi.org/10.1108/JFM-08-2020-0061.
Ansah, R. H., and S. Sorooshian. 2018. “4P delays in project management.” Eng. Constr. Archit. Manage. 25 (1): 62–76. https://doi.org/10.1108/ECAM-09-2016-0199.
Assaad, R., and I. H. El-adaway. 2021. “Guidelines for responding to COVID-19 pandemic: Best practices, impacts, and future research directions.” J. Manage. Eng. 37 (3): 06021001. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000906.
Assaf, S. A., and S. Al-Hejji. 2006. “Causes of delay in large construction projects.” Int. J. Project Manage. 24 (4): 349–357. https://doi.org/10.1016/j.ijproman.2005.11.010.
Bozorg-Haddad, O., H. Orouji, S. Mohammad-Azari, H. Loaiciga, and M. Mariño. 2016. “Construction risk management of irrigation dams.” J. Irrig. Drain. Eng. 142 (5): 04016009. https://doi.org/10.1061/(ASCE)IR.1943-4774.0001001.
Briggs, B., C. J. Friedland, I. Nahmens, C. Berryman, and Y. Zhu. 2022. “Industrial construction safety policies and practices with cost impacts in a COVID-19 pandemic environment: A Louisiana DOW case study.” J. Loss Prev. Process Ind. 76 (May): 104723. https://doi.org/10.1016/j.jlp.2021.104723.
CHAS (Contractors Health and Safety Assessment Scheme). 2021. “The impact of COVID-19 on the construction industry (according to business owners).” Accessed July 10, 2021. https://www.chas.co.uk/blog/covid-impact-on-construction-industry/.
Chen, L., Q. Lu, and X. Zhao. 2020. “Rethinking the construction schedule risk of infrastructure projects based on dialectical systems and network theory.” J. Manage. Eng. 36 (5): 04020066. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000829.
Chih, Y. Y., C. Y. L. Hsiao, A. Zolghadr, and N. Naderpajouh. 2022. “Resilience of organizations in the construction industry in the face of COVID-19 disturbances: Dynamic capabilities perspective.” J. Manage. Eng. 38 (2): 04022002. https://doi.org/10.1061/(ASCE)ME.1943-5479.0001014.
Elnaggar, S. M., and H. Elhegazy. 2022. “Study the impact of the COVID-19 pandemic on the construction industry in Egypt.” Structures 35 (Jan): 1270–1277. https://doi.org/10.1016/j.istruc.2021.09.028.
Gamil, Y., and A. Alhagar. 2020. “The impact of pandemic crisis on the survival of construction industry: A case of COVID-19.” Mediterr. J. Soc. Sci. 11 (4): 122–128. https://doi.org/10.36941/mjss-2020-0047.
GFR (General Financial Rules). 2017. “Ministry of Finance, Government of India, New Delhi.” Accessed August 10, 2021. https://doe.gov.in/sites/default/files/GFR2017_0.pdf.
González, P., V. González, M. Molenaar, and F. Orozo. 2014. “Analysis of causes of delay and time performance in construction projects.” J. Constr. Eng. Manage. 140 (1): 1–9. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000721.
Gunduz, M., Y. Nielsen, and M. Ozdemir. 2013. “Quantification of delay factors using relative importance index method for construction projects in Turkey.” J. Manage. Eng. 29 (2): 133–139. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000129.
Hansen, S. 2020. “Does the COVID-19 outbreak constitute a force majeure event? A pandemic impact on construction contracts.” J. Civ. Eng. Forum 6 (1): 201–214. https://doi.org/10.22146/jcef.54997.
Hasan, A., and K. N. Jha. 2016. “Acceptance of the incentive/disincentive contracting strategy in developing construction markets: Empirical study from India.” J. Constr. Eng. Manage. 142 (2): 04015064. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001048.
Hendrickson, C., and L. R. Rilett. 2020. “The COVID-19 pandemic and transportation engineering.” J. Transp. Eng. 146 (7): 01820001. https://doi.org/10.1061/JTEPBS.0000418.
Iqbal, M., N. Ahmad, M. Waqas, and M. Abrar. 2021. “COVID-19 pandemic and construction industry: Impacts, emerging construction safety practices, and proposed crisis management.” Braz. J. Oper. Prod. Manage. 18 (2): 1–17. https://doi.org/10.14488/BJOPM.2021.034.
Iyer, K. C, R. Kumar, and S. P. Singh. 2020. “Understanding the role of contractor capability in risk management: A comparative case study of two similar projects.” Construct. Manage. Econ. 38 (3): 223–238. https://doi.org/10.1080/01446193.2019.1590614.
Jang, Y., I. Jeong, and Y. K. Cho. 2020. “Business failure prediction of construction contractors using a LSTM RNN with accounting, construction market, and macroeconomic variables.” J. Manage. Eng. 36 (2): 04019039. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000733.
Kamal, A., M. Abas, D. Khan, and R. W. Azfar. 2022. “Risk factors influencing the building projects in Pakistan: From perspective of contractors, clients and consultants.” Int. J. Constr. Manage. 26 (6): 1141–1157. https://doi.org/10.1080/15623599.2019.1683693.
Langley, A. 1999. “Strategies for theorizing from process data.” Acad. Manage. Rev. 24 (4): 691–710. https://doi.org/10.5465/amr.1999.2553248.
Lekshmi, S. A., and V. Unnikrishnan. 2018. “Planning and delay analysis of a residential complex: A case study.” Int. J. Civ. Eng. Technol. 9 (6): 1191–1201.
Ling, F. Y., Z. Zhang, and A. Y. Yew. 2022. “Impact of COVID-19 pandemic on demand, output, and outcomes of construction projects in Singapore.” J. Manage. Eng. 38 (2): 04021097. https://doi.org/10.1061/(ASCE)ME.1943-5479.0001020.
Long, N. D., S. Ogunlana, T. Quang, and K. C. Lam. 2004. “Large construction projects in developing countries: A case study from Vietnam.” Int. J. Project Manage. 22 (7): 553–561. https://doi.org/10.1016/j.ijproman.2004.03.004.
MHA (Ministry of Home Affairs). 2020a. Office memorandum. New Delhi, India: Government of India.
MHA (Ministry of Home Affairs). 2020b. Order. No. 40-3/2020-DM-I(A), Dated April 15, 2020. New Delhi, India: Government of India.
MHA (Ministry of Home Affairs). 2020c. Order. No. 40-3/2020-DM-I(A), Dated March 29, 2020. New Delhi, India: Government of India.
Morris, G. D. L. 2020. “6 critical COVID-19 risks for the construction industry.” Accessed November 11, 2021. https://riskandinsurance.com/6-critical-covid-19-risks-for-the-construction-industry/.
Nagata, M. F., W. A. Manginelli, J. C. Lowe, and T. J. Trauner. 2018. Construction delays. 3rd ed. Oxford: Butterworth-Heinemann.
Ogunnusi, M., M. Hamma-Adama, H. Salman, and T. Kouider. 2020. “COVID-19 pandemic: The effects and prospects in the construction industry.” Int. J. Real Estate Stud. 14 (2): 120–128.
Onubi, H. O., N. A. Yusof, and A. S. Hassan. 2021. “Perceived COVID-19 safety risk and safety behavior on construction sites: Role of safety climate and firm size.” J. Constr. Eng. Manage. 147 (11): 04021153. https://doi.org/10.1061/(ASCE)CO.1943-7862.0002201.
Pasco, R. F., S. J. Fox, S. C. Johnston, M. Pignone, and L. A. Meyers. 2020. “Estimated association of construction work with risks of COVID-19 infection and hospitalization in Texas.” JAMA Network Open 3 (10): e2026373. https://doi.org/10.1001/jamanetworkopen.2020.26373.
Pirzadeh, P., and H. Lingard. 2021. “Working from home during the COVID-19 pandemic: Health and well-being of project-based construction workers.” J. Constr. Eng. Manage. 147 (6): 04021048. https://doi.org/10.1061/(ASCE)CO.1943-7862.0002102.
PWC (Price Waterhouse and Coopers). 2020. “COVID-19: What it means for engineering and construction.” Accessed May 28, 2020. www.pwc.com/us/en/library/covid-19/coronavirus-impacts-engineering-construction.html.
Raoufi, M., and A. R. Fayek. 2022. “New modes of operating for construction organizations during the COVID-19 pandemic: Challenges, actions, and future best practices.” J. Manage. Eng. 38 (2): 04021091. https://doi.org/10.1061/(ASCE)ME.1943-5479.0001009.
Rehman, M. S. U., M. T. Shafiq, and M. Afzal. 2022. “Impact of COVID-19 on project performance in the UAE construction industry.” J. Eng. Des. Technol. 20 (1): 245–266. https://doi.org/10.1108/JEDT-12-2020-0481.
RICS (Royal Institution of Chartered Surveyors). 2021. “More common, more costly: Is COVID-19 causing conflict in the construction sector?” Accessed January 28, 2022. https://www.rics.org/en-in/wbef/megatrends/markets-geopolitics/more-common-more-costly-is-covid-19-causing-conflict-in-the-construction-sector/.
Salami, B. A., S. O. Ajayi, and A. S. Oyegoke. 2021. “Tackling the impacts of Covid-19 on construction projects: An exploration of contractual dispute avoidance measures adopted by construction firms.” Int. J. Constr. Manage. (Aug). https://doi.org/10.1080/15623599.2021.1963561.
Salami, B. A., S. O. Ajayi, and A. S. Oyegoke. 2022. “Coping with the COVID-19 pandemic: An exploration of the strategies adopted by construction firms.” J. Eng. Des. Technol. 20 (1): 159–182. https://doi.org/10.1108/JEDT-01-2021-0054.
Santoso, D. S., and S. Soeng. 2016. “Analyzing delays of road construction projects in Cambodia: Causes and effects.” J. Manage. Eng. 32 (6): 05016020. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000467.
Sepasgozar, S. M. E., R. Karimi, S. Shirowzhan, M. Mojtahedi, S. Ebrahimzadeh, and D. McCarthy. 2019. “Delay causes and emerging digital tools: A novel model of delay analysis, including integrated project delivery and PMBOK.” Buildings 9 (9): 191–227. https://doi.org/10.3390/buildings9090191.
Sierra, F. 2022. “COVID-19: Main challenges during construction stage.” Eng. Constr. Archit. Manage. 29 (4): 1817–1834. https://doi.org/10.1108/ECAM-09-2020-0719.
Sinesilassie, E. G., S. Z. S. Tabish, and K. N. Jha. 2017. “Critical factors affecting schedule performance: A case of Ethiopian public construction projects–engineers’ perspective.” Eng. Constr. Archit. Manage. 24 (5): 757–773. https://doi.org/10.1108/ECAM-03-2016-0062.
Stanford, M. S., and K. R. Molenaar. 2020. “Cost implications of indefinite delivery–indefinite quantity contracting in the US defense sector.” J. Manage. Eng. 36 (5): 04020065. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000827.
Strickland, J. T. 2020. “Addressing financial impacts of the COVID-19 crisis on construction companies.” Accessed July 13, 2020. https://www.natlawreview.com/article/addressing-financial-impacts-covid-19-crisis-construction-companies.
Thi, C. H., and F. W. Swierczek. 2010. “Critical success factors in project management: Implication from Vietnam.” Asia Pac. Bus. Rev. 16 (4): 567–589. https://doi.org/10.1080/13602380903322957.
Trauner, T., Jr., W. Manginelli, J. Lowe, M. Nagata, and B. Furniss. 2009. Construction delays: Understanding them clearly, analyzing them correctly. Philadelphia, PA: Elsevier.
Vu, H. A., V. H. Cu, L. X. Min, and J. Q. Wang. 2017. “Risk analysis of schedule delays in international highway projects in Vietnam using a structural equation model.” Eng. Constr. Archit. Manage. 24 (6): 1018–1039. https://doi.org/10.1108/ECAM-06-2016-0138.
Wang, T. K., D. N. Ford, H. Y. Chong, and W. Zhang. 2018. “Causes of delays in the construction phase of Chinese building projects.” Eng. Constr. Archit. Manage. 25 (11): 1534–1551. https://doi.org/10.1108/ECAM-10-2016-0227.
Wu, Z., T. Nisar, D. Kapletia, and G. Prabhakar. 2017. “Risk factors for project success in the Chinese construction industry.” J. Manuf. Technol. Manage. 28 (7): 850–866. https://doi.org/10.1108/JMTM-02-2017-0027.
Yap, J. B. H., K. Shavarebi, and M. Skitmore. 2021. “Capturing and reusing knowledge: Analyzing the what, how and why for construction planning and control.” Prod. Plann. Control 32 (11): 875–888. https://doi.org/10.1080/09537287.2020.1774676.
Yin, R. K. 2009. Case study research: Design and methods. London: SAGE.
Yuan, T., P. Xiang, H. Li, and L. Zhang. 2020. “Identification of the main risks for international rail construction projects based on the effects of cost-estimating risks.” J. Cleaner Prod. 274 (Nov): 122904. https://doi.org/10.1016/j.jclepro.2020.122904.
Zou, P., G. Zhang, and J. Wang. 2007. “Understanding the key risks in construction projects in China.” Int. J. Project Manage. 25 (6): 601–614. https://doi.org/10.1016/j.ijproman.2007.03.001.

Information & Authors

Information

Published In

Go to Journal of Construction Engineering and Management
Journal of Construction Engineering and Management
Volume 148Issue 9September 2022

History

Received: Nov 16, 2021
Accepted: Apr 6, 2022
Published online: Jul 5, 2022
Published in print: Sep 1, 2022
Discussion open until: Dec 5, 2022

Permissions

Request permissions for this article.

ASCE Technical Topics:

Authors

Affiliations

Mohammad Essa Abubakar [email protected]
Postgraduate, Dept. of Civil Engineering, Indian Institute of Technology Delhi, New Delhi 110016, India. Email: [email protected]
Lecturer, School of Architecture and Built Environment, Faculty of Science, Engineering and Built Environment, Deakin Univ., Geelong, VIC 3220, Australia (corresponding author). ORCID: https://orcid.org/0000-0003-2031-4288. Email: [email protected]
Kumar Neeraj Jha, Ph.D. [email protected]
Professor, Dept. of Civil Engineering, Indian Institute of Technology Delhi, New Delhi 110016, India. Email: [email protected]

Metrics & Citations

Metrics

Citations

Download citation

If you have the appropriate software installed, you can download article citation data to the citation manager of your choice. Simply select your manager software from the list below and click Download.

Cited by

  • A Synthesis of Literature on the Effects of COVID-19 on Construction Industry, Practice Periodical on Structural Design and Construction, 10.1061/PPSCFX.SCENG-1466, 29, 3, (2024).
  • Evaluation of Cost Overrun in Construction Projects during COVID-19 Pandemic, Journal of Legal Affairs and Dispute Resolution in Engineering and Construction, 10.1061/JLADAH.LADR-1080, 16, 1, (2024).
  • Evolvement of Excusable Delay Clauses in Government Contracts since the COVID-19 Pandemic, Journal of Legal Affairs and Dispute Resolution in Engineering and Construction, 10.1061/JLADAH.LADR-1059, 16, 1, (2024).
  • No Scheduling Problem but Rather a Rescheduling Problem: Measuring Robustness of Schedule Network in Construction Projects, Journal of Construction Engineering and Management, 10.1061/JCEMD4.COENG-13781, 150, 2, (2024).
  • Exploring Farmers’ Willingness to Engage in Participatory Irrigation Infrastructure Programs: Evidence from a Water-Stressed Region, Journal of Construction Engineering and Management, 10.1061/JCEMD4.COENG-13542, 150, 6, (2024).
  • A Critical Review of Impacts from the COVID-19 Pandemic in Construction Projects: What Have We Learned?, Construction Research Congress 2024, 10.1061/9780784485286.062, (621-631), (2024).

View Options

Get Access

Access content

Please select your options to get access

Log in/Register Log in via your institution (Shibboleth)
ASCE Members: Please log in to see member pricing

Purchase

Save for later Information on ASCE Library Cards
ASCE Library Cards let you download journal articles, proceedings papers, and available book chapters across the entire ASCE Library platform. ASCE Library Cards remain active for 24 months or until all downloads are used. Note: This content will be debited as one download at time of checkout.

Terms of Use: ASCE Library Cards are for individual, personal use only. Reselling, republishing, or forwarding the materials to libraries or reading rooms is prohibited.
ASCE Library Card (5 downloads)
$105.00
Add to cart
ASCE Library Card (20 downloads)
$280.00
Add to cart
Buy Single Article
$35.00
Add to cart

Get Access

Access content

Please select your options to get access

Log in/Register Log in via your institution (Shibboleth)
ASCE Members: Please log in to see member pricing

Purchase

Save for later Information on ASCE Library Cards
ASCE Library Cards let you download journal articles, proceedings papers, and available book chapters across the entire ASCE Library platform. ASCE Library Cards remain active for 24 months or until all downloads are used. Note: This content will be debited as one download at time of checkout.

Terms of Use: ASCE Library Cards are for individual, personal use only. Reselling, republishing, or forwarding the materials to libraries or reading rooms is prohibited.
ASCE Library Card (5 downloads)
$105.00
Add to cart
ASCE Library Card (20 downloads)
$280.00
Add to cart
Buy Single Article
$35.00
Add to cart

Media

Figures

Other

Tables

Share

Share

Copy the content Link

Share with email

Email a colleague

Share