Technical Papers
Jun 17, 2022

Project Risk Costs: Estimation Overruns Caused When Using Only Expected Value for Contingency Calculations

Publication: Journal of Management in Engineering
Volume 38, Issue 5

Abstract

Real project experiences show that project actual risk cost is usually higher than expected. A significant reason for that overrun could be that the overall expected risk cost (ERc) is often calculated using only the deterministic expected value method (EV), i.e., the sum of the products of probability times the cost for each risk event. This article analyzes the reliability of the so-calculated ERc value by comparing the ERc to results obtained with the Monte Carlo simulation, using thousands of random analytical models and models from 271 real projects. This article addresses the theoretical basis of the EV method and the influence of the number of risk events, their correlation, and their statistical distribution. It proves that common project risk models do not meet the premises required to use the EV method and that this method, when used alone, often results in an underestimation of the ERc; project risk cost could actually be up to three times higher. This article proposes the application of an enlargement factor to the deterministic ERc to improve its level of certainty, and provides a formula obtained with multivariate regression analysis to calculate it.

Practical Applications

Project cost overrun is a fact in project management and a risk assessment is usually conducted to prevent it. The total expected cost of the risk events identified is used as a contingency sum to cover for risks that occur, and many companies calculate it as the sum of the products of probability times the cost for each risk event. This contingency sum affects project profitability and, if it is wrongly calculated, the related decision-making process could also be wrong. This article proves that this calculation method increases the chances of an unacceptable overrun in common projects and risk scenarios because it yields just an average that will overrun 50% of the time, and real values could easily be even three times higher. This simplified method should not be used for this purpose in common projects and risk scenarios. A more sophisticated method, such as the Monte Carlo simulation, could be used instead, but many companies do not have the knowledge and skills they require. For that reason, this article proposes the application of an enlargement factor to that sum to improve its level of certainty and provides a formula to calculate it.

Get full access to this article

View all available purchase options and get full access to this article.

Data Availability Statement

Real project data used in this study (a blind list of risk events with an estimation of their costs and likelihoods) are proprietary and confidential in nature and cannot be provided. The Excel files used to generate random simulation scenarios to apply the Monte Carlo simulation are available from the corresponding author upon reasonable request.

Acknowledgments

The author sincerely thanks the library of Escuela Técnica Superior de Ingenieros de Caminos, Canales y Puertos (Universidad Politécnica de Madrid) for its help; Palisade Corporation, for granting the use of @Risk for this article; and Mrs. Katherine Reddington for her continuous encouragement and her unlimited help. The author would also like to thank the reviewers of this paper for their incredible help to make this article better and their constructive comments.

References

Addo, J. N. T. 2015. “Determination of contingency sum for building projects in Ghana.” Afr. J. Appl. Res. 1 (1): 247–261.
Aderbag, M. A., S. K. Elmabrouk, and M. A. Sherif. 2018. “Risk analysis related to costing and scheduling of construction projects.” In Proc., Int. Conf. on Industrial Engineering and Operations Management, 6–18. Southfield, MI: Industrial Engineering and Operations Management Society International.
Alashwal, A. M., and M. H. Al-Sabahi. 2019. “Risk factors in construction projects during unrest period in Yemen.” J. Constr. Dev. Countries 23 (2): 43–62. https://doi.org/10.21315/jcdc2018.23.2.4.
Allahaim, F. S., L. Liu, and X. Kong. 2016. “Developing risk-based cost contingency estimation model based on the influence of cost overrun causes.” In Proc., CIB World Building Congress, 726–739. Brisbane, QLD, Australia: Queensland Univ. of Technology.
Allahaim, F. S., L. Liu, and X. Kong. 2017. “A risk-based cost contingency estimation model for infrastructure projects.” In Proc., ICCREM 2016: BIM Application and Off-Site Construction, 1293–1303. Reston, VA: ASCE.
Amade, B., E. O. P. Akpan, F. P. O. Ukwuoma, and C. C. Alajemba. 2013. “Project cost contingency in the Nigerian construction industry.” Int. J. Res. Manage. Sci. Technol. 2 (2): 9–21.
ANSI/ASIS/RIMS (American National Standards Institute/American Society for Industrial Security/Risk and Insurance Management Society). 2015. Risk assessment. ANSI/ASIS/RIMS RA.1-2015. Alexandria, VA: ANSI/ASIS/RIMS.
Arikan, A. E. 2005. Development of a risk management decision support system for international construction projects. Ankara, Turkey: Middle East Technical Univ.
Baccarini, D. 2005. “Estimating project cost contingency–beyond the 10% syndrome.” In Proc., Australian Institute of Project Management Conf. Melbourne, Australia: Australian Institute of Project Management.
Baccarini, D., and P. E. D. Love. 2014. “Statistical characteristics of cost contingency in water infrastructure projects.” J. Constr. Eng. Manage. 140 (3): 04013063. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000820.
Bahamid, R. A., S. I. Doh, and M. A. Al-Sharaf. 2019. “Risk factors affecting the construction projects in the developing countries.” IOP Conf. Ser.: Earth Environ. Sci. 244 (1): 012040. https://doi.org/10.1088/1755-1315/244/1/012040.
Bakhshi, P., and A. Touran. 2014. “An overview of budget contingency calculation methods in construction industry.” Procedia Eng. 85 (Jan): 52–60. https://doi.org/10.1016/j.proeng.2014.10.528.
Banaitiene, N. 2012. Risk management—Current issues and challenges. Rijeka, Croatia: InTech.
Bañuls, V. A., C. López, M. Turoff, and F. Tejedor. 2006. “Predicting the impact of multiple risks on project performance: A scenario-based approach.” Project Manage. J. 48 (5): 95–114. https://doi.org/10.1177/875697281704800507.
Barraza, G. A. 2011. “Probabilistic estimation and allocation of project time contingency.” J. Constr. Eng. Manage. 137 (4): 259–265. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000280.
Barraza, G. A., and R. A. Bueno. 2007. “Cost contingency management.” J. Manage. Eng. 23 (3): 140–146. https://doi.org/10.1061/(ASCE)0742-597X(2007)23:3(140).
Bello, W. A., and K. T. Odusami. 2008. “The practice of contingency allocation in construction projects in Nigeria.” In The construction and building research, 1–15. Dublin, Ireland: Royal Institution of Chartered Surveyors.
Bello, W. A., and K. T. Odusami. 2013. “Weak management of the predictability of contingency allowance in construction projects in Nigeria.” In Proc., 29th Annual Association of Researchers in Construction Management Conf. (ARCOM 2013), edited by S. D. Smith and D. D. Ahiaga-Dagbui, 969–978. Reading, UK: Association of Researchers in Construction Management.
Bhargava, A., P. C. Anastasopoulos, S. Labi, K. C. Sinha, and F. L. Mannering. 2010. “Three-stage least-squares analysis of time and cost overruns in construction contracts.” J. Constr. Eng. Manage. 136 (11): 1207–1218. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000225.
Birnin-Kebbi, U. M., and M. Usman. 2020. “Contingency allocation: A case of profesional absurdity.” Sospoly J. Eng. Entrepreneurship Environ. Stud. 3 (1): 1–9.
Bouayed, Z. 2016. “Using Monte Carlo simulation to mitigate the risk of project cost overruns.” Int. J. Saf. Secur. Eng. 6 (2): 293–300. https://doi.org/10.2495/SAFE-V6-N2-293-300.
Bromiley, P., M. McShane, A. Nair, and E. Rustambekov. 2015. “Enterprise risk management: Review, critique, and research directions.” Long Range Plann. 48 (4): 265–276. https://doi.org/10.1016/j.lrp.2014.07.005.
Burroughs, S. E., and G. Juntima. 2004. “Exploring techniques for contingency setting.” In PPG #08: Contingency, 4th ed., edited by P. C. Kul and B. Uppal. Fairmont, WV: Association for the Advancement of Cost Engineering.
Chen, L., Q. Lu, S. Li, W. He, and J. Yang. 2021. “Bayesian Monte Carlo simulation–driven approach for construction schedule risk inference.” J. Manage. Eng. 37 (2): 04020115. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000884.
Chen, P., and T. Peng. 2018. “Value-at-risk model analysis of Taiwanese high-tech facility construction.” J. Manage. Eng. 34 (2): 04017057. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000585.
Cheng, M., and Y. Lu. 2015. “Developing a risk assessment method for complex pipe jacking construction projects.” Autom. Constr. 58 (Oct): 48–59. https://doi.org/10.1016/j.autcon.2015.07.011.
CII (Construction Industry Institute). 2012. Applying probabilistic risk management in design and construction projects. Austin, TX: CII.
Cook, J. J. 2006. Estimating required contingency funds for construction projects using multiple linear regression. Wright-Patterson Air Force Base, OH: Air Force Institute of Technology.
Cretu, O., R. Stewart, and T. Berends. 2011. “The risk based estimate.” In Risk management for design and construction. Hoboken, NJ: Wiley.
Curtis, P., and M. Carey. 2012. “Develop assessment criteria.” In Risk assessment in practice. Durham, NC: Committee of Sponsoring Organizations of the Treadway Commission.
Dandage, R. V., S. S. Mantha, S. B. Rane, and V. Bhoola. 2018. “Analysis of interactions among barriers in project risk management.” J. Ind. Eng. Int. 14 (1): 153–169. https://doi.org/10.1007/s40092-017-0215-9.
De Marco, A., C. Rafele, and M. J. Thaheem. 2016a. “Dynamic management of risk contingency in complex design-build projects.” J. Constr. Eng. Manage. 142 (2): 04015080. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001052.
De Marco, A., M. Rosso, and T. Narbaev. 2016b. “Nonlinear cost estimates at completion adjusted with risk contingency.” J. Mod. Project Manage. 4 (2): 24–33. https://doi.org/10.19255/JMPM01102.
Deng, F., and H. Smyth. 2013. “Contingency-based approach to firm performance in construction: Critical review of empirical research.” J. Constr. Eng. Manage. 139 (10): 04013004. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000738.
Diab, M. F., A. Varma, and K. Panthi. 2017. “Modeling the construction risk ratings to estimate the contingency in highway projects.” J. Constr. Eng. Manage. 143 (8): 04017041. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001334.
Dziadosz, A., and M. Rejment. 2015. “Risk analysis in construction project-chosen methods.” Procedia Eng. 122 (Jan): 258–265. https://doi.org/10.1016/j.proeng.2015.10.034.
El-Adaway, I. H., and A. A. Kandil. 2010. “Construction risks: Single versus portfolio insurance.” J. Manage. Eng. 26 (1): 2–8. https://doi.org/10.1061/(ASCE)0742-597X(2010)26:1(2).
Elbarkouky, M. M. G., A. R. Fayek, N. B. Siraj, and N. Sadeghi. 2016. “Fuzzy arithmetic risk analysis approach to determine construction project contingency.” J. Constr. Eng. Manage. 142 (12): 04016070. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001191.
Eldosouky, I. A., A. H. Ibrahim, and H. E. Mohammed. 2014. “Management of construction cost contingency covering upside and downside risks.” Alexandria Eng. J. 53 (4): 863–881. https://doi.org/10.1016/j.aej.2014.09.008.
Ergin, A. A. 2005. “Determination of contingency for international constructional projects during bidding stage.” Master’s thesis, Dept. of Civil Engineering, Middle East Univ.
Ernevad, K. D. 2014. “Suitability for quantitative risk analysis in small company business expansion project: Cost estimation decision model.” Master’s thesis, School of Industrial Engineering and Management, Royal Institute of Technology.
Firmenich, J. 2017. “Customisable framework for project risk management.” Construct. Innovation 17 (1): 68–89. https://doi.org/10.1108/CI-04-2015-0022.
Goodpasture, J. 2004. “Special topics in quantitative management.” In Quantitative methods in project management. Plantation, FL: J. Ross Publishing.
Gupta, P., and V. Gupta. 2012. “A survey of text question answering techniques.” Int. J. Comput. Appl. 53 (4): 1–8. https://doi.org/10.5120/8406-2030.
Gupta, V. K., and J. J. Thakkar. 2018. “A quantitative risk assessment methodology for construction project.” Sādhanā 43 (7): 116. https://doi.org/10.1007/s12046-018-0846-6.
Hamid, R. A., and F. J. Kehinde. 2017. “Choosing an appropriate contingency sum estimating methods for highway construction projects in Nigeria: A literature review.” Plann. Malaysia J. 15 (1): 13–20. https://doi.org/10.21837/pmjournal.v15.i6.217.
Hammad, M. W., A. Abbasi, and M. J. Ryan. 2016. “Allocation and management of cost contingency in projects.” J. Manage. Eng. 32 (6): 04016014. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000447.
Hobbs, B., and Y. Petit. 2017. “Agile methods on large projects in large organizations.” Project Manage. J. 48 (3): 3–19. https://doi.org/10.1177/875697281704800301.
Hollmann, J. K. 2009a. Recommended practices for risk analysis and cost contingency estimating. Fairmont, WV: American Association of Cost Engineering International.
Hollmann, J. K. 2009b. Risk analysis and contingency determination using expected value. Fairmont, WV: American Association of Cost Engineering International.
Hoseini, E., P. van Veen, M. Bosch-Rekveldt, and M. Hertogh. 2020. “Cost performance and cost contingency during project execution: Comparing client and contractor perspectives.” J. Manage. Eng. 36 (4): 05020006. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000772.
Hu, Y., A. P. C. Chan, Y. Le, and R. Jin. 2015. “From construction megaproject management to complex project management: Bibliographic analysis.” J. Manage. Eng. 31 (4): 04014052. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000254.
Hulett, D. T. 2011. Integrated cost and schedule risk analysis using Monte Carlo simulation of a CPM model. Fairmont, WV: American Association of Cost Engineering International.
Imbeah, W., and S. Guikema. 2009. “Managing construction projects using the advanced programmatic risk analysis and management model.” J. Constr. Eng. Manage. 135 (8): 772–781. https://doi.org/10.1061/(ASCE)0733-9364(2009)135:8(772).
Institution of Civil Engineers and Institute and Faculty of Actuaries. 2004. Risk analysis and management for projects: A strategic framework for managing project risk and its financial implications. 3rd ed. London: Institution of Civil Engineers Publishing.
ISO (International Organization for Standardization). 2019. Risk management—Risk assessment techniques. Geneva: ISO.
Izadi Moud, H., I. Flood, X. Zhang, B. Abbasnejad, P. Rahgozar, and M. McIntyre. 2021. “Quantitative assessment of proximity risks associated with unmanned aerial vehicles in construction.” J. Manage. Eng. 37 (1): 04020095. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000852.
Jarkas, A. M., and T. C. Haupt. 2015. “Major construction risk factors considered by general contractors in Qatar.” J. Eng. Des. Technol. 13 (1): 165–194. https://doi.org/10.1108/JEDT-03-2014-0012.
Jayasudha, K., and B. Vidivelli. 2016. “Analysis of major risks in construction projects.” ARPN J. Eng. Appl. Sci. 11 (11): 6943–6950.
Jung, J. H., D. Y. Kim, and H. K. Lee. 2016. “The computer-based contingency estimation through analysis cost overrun risk of public construction project.” KSCE J. Civ. Eng. 20 (4): 1119–1130. https://doi.org/10.1007/s12205-015-0184-8.
Jung, W., and S. H. Han. 2017. “Which risk management is most crucial for controlling project cost?” J. Manage. Eng. 33 (5): 04017029. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000547.
Kaplinski, O. 2013. “Risk management of construction works by means of the utility theory: A case study.” Procedia Eng. 57 (Jan): 533–539. https://doi.org/10.1016/j.proeng.2013.04.068.
KarimiAzari, A., N. Mousavi, S. F. Mousavi, and S. Hosseini. 2011. “Risk assessment model selection in construction industry.” Expert Syst. Appl. 38 (8): 9105–9111. https://doi.org/10.1016/j.eswa.2010.12.110.
Keshk, A. M., I. Maarouf, and Y. Annany. 2018. “Special studies in management of construction project risks, risk concept, plan building, risk quantitative and qualitative analysis, risk response strategies.” Alexandria Eng. J. 57 (4): 3179–3187. https://doi.org/10.1016/j.aej.2017.12.003.
Konduru, K., A. C. Shurtleff, S. Bavari, and G. Kaplan. 2018. “High degree of correlation between Ebola virus BSL-4 neutralization assays and pseudotyped VSV BSL-2 fluorescence reduction neutralization test.” J. Virol. Methods 254 (Apr): 1–7. https://doi.org/10.1016/j.jviromet.2018.01.003.
Kuo, R. J., Y. Nugroho, and F. E. Zulvia. 2019. “Application of particle swarm optimization algorithm for adjusting project contingencies and response strategies under budgetary constraints.” Comput. Ind. Eng. 135 (Sep): 254–264. https://doi.org/10.1016/j.cie.2019.05.022.
Lam, T. Y. M., and N. Siwingwa. 2017. “Risk management and contingency sum of construction projects.” J. Financ. Manage. Property Constr. 22 (3): 237–251. https://doi.org/10.1108/JFMPC-10-2016-0047.
Larsen, J. K., G. Q. Shen, S. M. Lindhard, and T. D. Brunoe. 2016. “Factors affecting schedule delay, cost overrun, and quality level in public construction projects.” J. Manage. Eng. 32 (1): 04015032. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000391.
Lhee, S. C. 2014. “Finding significant factors to affect cost contingency on construction projects using ANOVA statistical method-focused on transportation construction projects in the US.” Archit. Res. 16 (2): 75–80. https://doi.org/10.5659/AIKAR.2014.16.2.75.
Lhee, S. C., R. R. A. Issa, and I. Flood. 2012. “Prediction of financial contingency for asphalt resurfacing projects using artificial neural networks.” J. Constr. Eng. Manage. 138 (1): 22–30. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000408.
Likert, R. 1932. “A technique for the measurement of attitudes.” Arch. Psychol. 22 (140): 21–55.
Liu, M., F. H. Griffis, and A. J. Bates. 2013. “Compensation structure and contingency allocation in integrated project delivery.” In Proc., ASEE Annual Conf. and Exposition, 1. Atlanta: American Society for Engineering Education.
Love, P. E. D., C. Sing, B. Carey, and J. T. Kim. 2015. “Estimating construction contingency: Accommodating the potential for cost overruns in road construction projects.” J. Infrastruct. Syst. 21 (2): 04014035. https://doi.org/10.1061/(ASCE)IS.1943-555X.0000221.
Mak, S., and D. Picken. 2000. “Using risk analysis to determine construction project contingencies.” J. Constr. Eng. Manage. 126 (2): 130–136. https://doi.org/10.1061/(ASCE)0733-9364(2000)126:2(130).
Ministerio de Trabajo, Migraciones y Seguridad Social. 1993. NTP 330: Sistema simplificado de evaluación de riesgos de accidente. Madrid, Spain: Notas Técnicas de Prevención, Instituto Nacional de Seguridad, Salud y Bienestar en el Trabajo.
Mishra, S., and B. Mishra. 2016. “A study on risk factors involved in the construction projects.” Int. J. Innovative Res. Sci. Eng. Technol. 5 (2): 1190–1196. https://doi.org/10.15680/IJIRSET.2016.0502005.
NASA (National Aeronautics and Space Administration). 2011. Probabilistic risk assessment procedures guide for NASA managers and practitioners. Washington, DC: NASA.
Nassar, K. 2002. “Cost contingency analysis for construction projects using spreadsheets.” Cost Eng. 44 (9): 26–31.
Nawaz, A., A. Waqar, S. A. R. Shah, M. Sajid, and M. I. Khalid. 2019. “An innovative framework for risk management in construction projects in developing countries: Evidence from Pakistan.” Risks 7 (1): 24. https://doi.org/10.3390/risks7010024.
Nieto-Morote, A., and F. Ruz-Vila. 2011. “A fuzzy approach to construction project risk assessment.” Int. J. Project Manage. 29 (2): 220–231. https://doi.org/10.1016/j.ijproman.2010.02.002.
Otali, M., and I. A. Odesola. 2014. “Effectiveness evaluation of contingency sum as a risk management tool for construction projects in Niger Delta, Nigeria.” Ethiopian J. Environ. Stud. Manage. 7 (6): 588–598. https://doi.org/10.4314/ejesm.v7i6.1.
Para-González, L., C. Mascaraque-Ramírez, and A. E. Madrid. 2018. “Obtaining the budget contingency reserve through the Monte Carlo method: Study of a ferry construction project.” Brodogradnja 69 (3): 79–95. https://doi.org/10.21278/brod69305.
PMI (Project Management Institute). 2013. A guide to the project management body of knowledge PMBOK guide. Newtown Square, PA: PMI.
PMI (Project Management Institute). 2017a. A guide to the project management body of knowledge PMBOK guide. Newtown Square, PA: PMI.
PMI (Project Management Institute). 2017b. Construction extension to the PMBOK guide. Newtown Square, PA: PMI.
PMI (Project Management Institute). 2021. A guide to the project management body of knowledge PMBOK guide. Newtown Square, PA: PMI.
Polat, G. 2012. “ANN approach to determine cost contingency in international construction project.” J. Appl. Manage. Investments 1 (2): 195–201.
Raftery, J. 1994. Risk analysis in project management. London: Spon Press.
Rani, H. A. 2017. “The analysis of importance index to the dominant category causing contractor contingency cost in Aceh Province.” Int. J. Struct. Civ. Eng. Res. 6 (3): 1–5.
Renault, B. Y., and J. N. Agumba. 2016. “Risk management in the construction industry: A new literature review.” MATEC Web Conf. 66 (4): 00008. https://doi.org/10.1051/matecconf/20166600008.
Renault, B. Y., J. N. Agumba, and O. A. Balogun. 2016. “Drivers for and obstacles to enterprise risk management in construction firms: A literature review.” Procedia Eng. 164 (Jan): 402–408. https://doi.org/10.1016/j.proeng.2016.11.637.
Renuka, S. M., and C. Umarani. 2019. “Effect of critical risk factors causing cost deviation in medium sized construction projects.” J. Constr. Dev. Countries 23 (2): 63–85. https://doi.org/10.21315/jcdc2018.23.2.5.
Rezaie, K., M. S. Amalnik, A. Gereie, B. Ostadi, and M. Shakhseniaee. 2007. “Using extended Monte Carlo simulation method for the improvement of risk management: Consideration of relationships between uncertainties.” Appl. Math. Comput. 190 (2): 1492–1501. https://doi.org/10.1016/j.amc.2007.02.038.
Rostami, A., J. Sommerville, I. L. Wong, and C. Lee. 2015. “Risk management implementation in small and medium enterprises in the UK construction industry.” Eng. Constr. Archit. Manage. 22 (1): 91–107. https://doi.org/10.1108/ECAM-04-2014-0057.
Rubbini, C. 2005. “Decisiones Bajo Incertidumbre. Microeconomía II.” Universidad de La Plata. Accessed December 2, 2016. http://www.depeco.econo.unlp.edu.ar/wp/wp-content/uploads/2017/05/docen10.pdf.
Salah, A., and O. Moselhi. 2015. “Contingency modelling for construction projects using fuzzy-set theory.” Eng. Constr. Archit. Manage. 22 (2): 214–241. https://doi.org/10.1108/ECAM-03-2014-0039.
Samantra, C., S. Datta, and S. S. Mahapatra. 2017. “Fuzzy based risk assessment module for metropolitan construction project: An empirical study.” Eng. Appl. Artif. Intell. 65 (Oct): 449–464. https://doi.org/10.1016/j.engappai.2017.04.019.
Schuyler, J. 2001. Risk and decision analysis in projects. Princeton, NJ: Project Management Institute.
Siraj, N. B., and A. R. Fayek. 2019. “Risk identification and common risks in construction: Literature review and content analysis.” J. Constr. Eng. Manage. 145 (9): 03119004. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001685.
Steinberg, R. M., M. E. A. Everson, F. J. Martens, and L. E. Nottingham. 2004a. Enterprise risk management—Integrated framework. Jersey City, NJ: Committee of Sponsoring Organizations of the Treadway Commission.
Steinberg, R. M., M. E. A. Everson, F. J. Martens, and L. E. Nottingham. 2004b. Enterprise risk management—Integrated framework. Application techniques. Jersey City, NJ: Committee of Sponsoring Organizations of the Treadway Commission.
Tanner, P., and R. Hingorani. 2015. “Acceptable risks to persons associated with building structures.” Struct. Concr. 16 (3): 314–322. https://doi.org/10.1002/suco.201500012.
Taroun, A. 2014. “Towards a better modelling and assessment of construction risk: Insights from a literature review.” Int. J. Project Manage. 32 (1): 101–115. https://doi.org/10.1016/j.ijproman.2013.03.004.
Timurlenk, Ö., and K. Kaptan. 2012. “Country risk.” Procedia-Social Behav. Sci. 62 (Oct): 1089–1094. https://doi.org/10.1016/j.sbspro.2012.09.186.
Touran, A. 1993. “Probabilistic cost estimating with subjective correlations.” J. Constr. Eng. Manage. 119 (1): 58–71. https://doi.org/10.1061/(ASCE)0733-9364(1993)119:1(58).
Touran, A. 2003. “Calculation of contingency in construction projects.” IEEE Trans. Eng. Manage. 50 (2): 135–140. https://doi.org/10.1109/TEM.2003.810824.
Touran, A., and E. P. Wiser. 1992. “Monte Carlo technique with correlated random variables.” J. Constr. Eng. Manage. 118 (2): 258–272. https://doi.org/10.1061/(ASCE)0733-9364(1992)118:2(258).
van Niekerk, M., and J. Bekker. 2014. “Developing a tool for project contingency estimation in a large portfolio of construction projects.” S. Afr. J. Ind. Eng. 25 (3): 96–111.
Vegas-Fernández, F. 2017. “Sistema de información de riesgos: Factor de Visibilidad.” El Profesional de la Informacion 26 (6): 1065–1075. https://doi.org/10.3145/epi.2017.nov.06.
Vegas-Fernández, F. 2019. Factor de visibilidad. Nuevo indicador para la evaluación cuantitativa de riesgos. Madrid, Spain: Universidad Politécnica de Madrid.
Vegas-Fernández, F. 2020. “Intelligent information extraction from scholarly document databases.” J. Intell. Stud. Bus. 10 (2): 44–61. https://doi.org/10.37380/jisib.v10i2.584.
Vegas-Fernández, F., and F. Rodríguez López. 2019. “Risk management improvement drivers for effective risk-based decision-making.” J. Bus. Econ. Finance 8 (4): 223–234. https://doi.org/10.17261/Pressacademia.2019.1166.
von Neumann, J., and O. Morgenstern. 1944. Theory of games and economic behavior. Princeton, NJ: Princeton University Press.
Williams, T. 2017. “The nature of risk in complex projects.” Project Manage. J. 48 (4): 55–66. https://doi.org/10.1177/875697281704800405.
Willumsen, P., J. Oehmen, V. Stingl, and J. Geraldi. 2019. “Value creation through project risk management.” Int. J. Project Manage. 37 (5): 731–749. https://doi.org/10.1016/j.ijproman.2019.01.007.
Won, J. W., W. Jung, S. H. Han, S. Yun, and B. Koo. 2019. “What enables a high-risk project to yield high return from a construction contractor’s perspective?” Sustainability (Switzerland) 11 (21): 5971. https://doi.org/10.3390/su11215971.
Yang, L., J. Lou, and X. Zhao. 2021. “Risk response of complex projects: Risk association network method.” J. Manage. Eng. 37 (4): 05021004. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000916.
Zacharias, O., D. Panopoulos, and D. T. Askounis. 2008. “Large scale program risk analysis using a risk breakdown structure.” Eur. J. Econ. Finance Administrative Sci. 12 (10): 170–181.
Zhao, J. 2007. “Significance of risk quantification.” In Proc., Palisade @RISK Conf. 2007, 1–11. Miami, FL: Palisade Corporation.
Zio, E. 2018. “The future of risk assessment.” Reliab. Eng. Syst. Saf. 177 (Sep): 176–190. https://doi.org/10.1016/j.ress.2018.04.020.
Zou, P. X. W., Y. Chen, and T. Chan. 2010. “Understanding and improving your risk management capability: Assessment model for construction organizations.” J. Constr. Eng. Manage. 136 (8): 854–863. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000175.

Information & Authors

Information

Published In

Go to Journal of Management in Engineering
Journal of Management in Engineering
Volume 38Issue 5September 2022

History

Received: Aug 31, 2021
Accepted: Mar 22, 2022
Published online: Jun 17, 2022
Published in print: Sep 1, 2022
Discussion open until: Nov 17, 2022

Permissions

Request permissions for this article.

ASCE Technical Topics:

Authors

Affiliations

Civil Engineer, Escuela Técnica Superior de Ingenieros de Caminos, Canales y Puertos, Universidad Politécnica de Madrid, c/ Profesor Aranguren 3, Madrid 28043, Spain. ORCID: https://orcid.org/0000-0003-1968-9891. Email: [email protected]

Metrics & Citations

Metrics

Citations

Download citation

If you have the appropriate software installed, you can download article citation data to the citation manager of your choice. Simply select your manager software from the list below and click Download.

Cited by

  • End-Users Engagement for Enacting Value of Complex Projects: An Ecological Perspective, Journal of Management in Engineering, 10.1061/JMENEA.MEENG-5724, 40, 3, (2024).
  • Sensitivity of Cost Overrun Propensity and Severity to Highway Project Bundling, Journal of Management in Engineering, 10.1061/JMENEA.MEENG-5425, 40, 2, (2024).

View Options

Get Access

Access content

Please select your options to get access

Log in/Register Log in via your institution (Shibboleth)
ASCE Members: Please log in to see member pricing

Purchase

Save for later Information on ASCE Library Cards
ASCE Library Cards let you download journal articles, proceedings papers, and available book chapters across the entire ASCE Library platform. ASCE Library Cards remain active for 24 months or until all downloads are used. Note: This content will be debited as one download at time of checkout.

Terms of Use: ASCE Library Cards are for individual, personal use only. Reselling, republishing, or forwarding the materials to libraries or reading rooms is prohibited.
ASCE Library Card (5 downloads)
$105.00
Add to cart
ASCE Library Card (20 downloads)
$280.00
Add to cart
Buy Single Article
$35.00
Add to cart

Get Access

Access content

Please select your options to get access

Log in/Register Log in via your institution (Shibboleth)
ASCE Members: Please log in to see member pricing

Purchase

Save for later Information on ASCE Library Cards
ASCE Library Cards let you download journal articles, proceedings papers, and available book chapters across the entire ASCE Library platform. ASCE Library Cards remain active for 24 months or until all downloads are used. Note: This content will be debited as one download at time of checkout.

Terms of Use: ASCE Library Cards are for individual, personal use only. Reselling, republishing, or forwarding the materials to libraries or reading rooms is prohibited.
ASCE Library Card (5 downloads)
$105.00
Add to cart
ASCE Library Card (20 downloads)
$280.00
Add to cart
Buy Single Article
$35.00
Add to cart

Media

Figures

Other

Tables

Share

Share

Copy the content Link

Share with email

Email a colleague

Share