Integrated Framework for Quantifying and Applying Nonworking Days to Planning and Scheduling for Determining Reasonable Construction Time

Publication: Journal of Management in Engineering
Volume 38, Issue 4

Abstract

Determining a reasonable construction time (RCT) is crucial in project planning and schedule management. Construction projects are exposed to the external environment, including rainfall, extreme temperatures, snowfall, and high wind speed, and the RCT should be evaluated considering these risks. The risks can be reflected by activity duration using nonworking days (NWDs). However, current construction planning and scheduling practices are ineffective for dealing with of NWD characteristics because working days (WDs) and NWDs are mixed in most schedule performance data used for schedule development. Activity durations estimated using historical performance data may not appropriately reflect the activity characteristics (work type, region, and work timing), leading to an unreasonable construction time for a project. Here, we propose an activity duration segmentation method (ADSM) for determining the RCT. The ADSM can evaluate the combined effects of weather factors according to work type and determine the operation rate, which depends on start date, work type, region, and activity duration. This leads to the separation of WDs and NWDs for determining the RCT. Case-based and comparative analyses were conducted to validate the proposed method. The mean absolute percentage error (MAPE), used to validate the ADSM, was 5.79%. The results of the present study show that NWDs can be determined by considering the characteristics of the various activities (e.g., sensitivities toward environmental conditions, start date) and the environmental conditions of the project (weather conditions at the project location, working hour patterns). The ADSM suggests an integrated framework for combining activity characteristics and project environmental conditions when determining NWDs of each activity. The ADSM can be used by project owners for determining the RCT or the contract time, which varies according to activity characteristics. Also, a construction scheduler can assess to what extent the construction schedule will be influenced by NWDs.

Get full access to this article

View all available purchase options and get full access to this article.

Data Availability Statement

Data generated or analyzed during this study are available from the corresponding author upon request.

Acknowledgments

This work is supported by the Korean Agency for Infrastructure Technology Advancement (KAIA) grant funded by the Ministry of Land, Infrastructure, and Transport (Grant 21ORPS-B158109-03).

References

Apipattanavis, S., K. Sabol, K. R. Molenaar, B. Rajagopalan, Y. Xi, B. Blackard, and S. Patil. 2010. “Integrated framework for quantifying and predicting weather-related highway construction delays.” J. Constr. Eng. Manage. 136 (11): 1160–1168. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000199.
Awada, M., F. J. Srour, and I. M. Srour. 2021. “Data-driven machine learning approach to integrate field submittals in project scheduling.” J. Manage. Eng. 37 (1): 04020104. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000873.
Ballesteros-Pérez, P., M. L. del Campo-Hitschfeld, M. A. González-Naranjo, and M. C. González-Cruz. 2015. “Climate and construction delays: Case study in Chile.” Eng. Constr. Archit. Manage. 22 (6): 596–621. https://doi.org/10.1108/ECAM-02-2015-0024.
Ballesteros-Pérez, P., S. T. Smith, J. G. Lloyd-Papworth, and P. Cooke. 2018. “Incorporating the effect of weather in construction scheduling and management with sine wave curves: Application in the United Kingdom.” Construct. Manage. Econ. 36 (12): 666–682. https://doi.org/10.1080/01446193.2018.1478109.
Bang, J.-D., S.-H. Song, G.-H. Cho, J.-R. Sohn, and J.-W. Kim. 2015. “A study on non-working day calculation standards and days of non-working for estimation of optimum duration in the frame work of apartment building construction.” J. Archit. Inst. Korea Struct. Constr. 31 (10): 21–28. https://doi.org/10.5659/JAIK_SC.2015.31.10.21.
Chang, C.-K., A. S. Hanna, J. A. Lackney, and K. T. Sullivan. 2005. “Quantifying the impact of schedule compression on construction labor productivity.” In Proc., Construction Research Congress 2005: Broadening Perspectives, 1–10. Reston, VA: ASCE.
Chen, L., Q. Lu, and X. Zhao. 2020. “Rethinking the construction schedule risk of infrastructure projects based on dialectical systems and network theory.” J. Manage. Eng. 36 (5): 04020066. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000829.
Cho, K., T. Kim, and T. Hong. 2020. “Estimating a risk-integrated schedule delay for an office building renovation project by considering the project’s attributes.” J. Manage. Eng. 36 (2): 04019040. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000732.
David, M., L. Adelard, P. Lauret, and F. Garde. 2010. “A method to generate typical meteorological years from raw hourly climatic databases.” Build. Environ. 45 (7): 1722–1732. https://doi.org/10.1016/j.buildenv.2010.01.025.
Dytczak, M., G. Ginda, N. Szklennik, and T. Wojtkiewicz. 2013. “Weather influence–aware robust construction project structure.” Procedia Eng. 57 (Jan): 244–253. https://doi.org/10.1016/j.proeng.2013.04.034.
Fan, R. Y. C., S. T. Ng, and J. M. Wong. 2010. “Reliability of the Box–Jenkins model for forecasting construction demand covering times of economic austerity.” Construct. Manage. Econ. 28 (3): 241–254. https://doi.org/10.1080/01446190903369899.
González, P., V. González, K. Molenaar, and F. Orozco. 2014. “Analysis of causes of delay and time performance in construction projects.” J. Constr. Eng. Manage. 140 (1): 04013027. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000721.
Hegazy, T., and W. Menesi. 2010. “Critical path segments scheduling technique.” J. Constr. Eng. Manage. 136 (10): 1078–1085. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000212.
Herroelen, W., and R. Leus. 2005. “Project scheduling under uncertainty: Survey and research potentials.” Eur. J. Oper. Res. 165 (2): 289–306. https://doi.org/10.1016/j.ejor.2004.04.002.
Hwang, S., M. Park, H.-S. Lee, and H. Kim. 2012. “Automated time-series cost forecasting system for construction materials.” J. Constr. Eng. Manage. 138 (11): 1259–1269. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000536.
Ibbs, W., and X. Sun. 2017. “Weather’s effect on construction labor productivity.” J. Leg. Aff. Dispute Resolut. Eng. Constr. 9 (2): 04517002. https://doi.org/10.1061/(ASCE)LA.1943-4170.0000212.
Islip, D., J. Z. Wei, and R. H. Kwon. 2021. “Managing construction risk with weather derivatives.” Eng. Econ. 66 (2): 150–184. https://doi.org/10.1080/0013791X.2020.1733721.
Jang, M.-H., Y.-S. Yoon, S.-W. Suh, and S.-J. Ko. 2008. “Method of using weather information for support to manage building construction projects.” In Proc., AEI 2008: Building Integration Solutions, 1–10. Reston, VA: ASCE.
Ji, S.-H., M. Park, and H.-S. Lee. 2010. “Data preprocessing–based parametric cost model for building projects: Case studies of Korean construction projects.” J. Constr. Eng. Manage. 136 (8): 844–853. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000197.
Jung, M., M. Park, H.-S. Lee, and H. Kim. 2016. “Weather-delay simulation model based on vertical weather profile for high-rise building construction.” J. Constr. Eng. Manage. 142 (6): 04016007. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001109.
Khamooshi, H., and A. Abdi. 2017. “Project duration forecasting using earned duration management with exponential smoothing techniques.” J. Manage. Eng. 33 (1): 04016032. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000475.
Kim, K., and J. M. de la Garza. 2005. “Critical path method with multiple calendars.” J. Constr. Eng. Manage. 131 (3): 330–342. https://doi.org/10.1061/(ASCE)0733-9364(2005)131:3(330).
Kim, K. J., W. G. Yun, and I. K. Kim. 2016. “Estimating approximate construction duration of CFRD in the planning stage.” KSCE J. Civ. Eng. 20 (7): 2604–2613. https://doi.org/10.1007/s12205-016-0810-0.
Kim, Y., K. Kim, and D. Shin. 2005. “Delay analysis method using delay section.” J. Constr. Eng. Manage. 131 (11): 1155–1164. https://doi.org/10.1061/(ASCE)0733-9364(2005)131:11(1155).
Koehn, E., and G. Brown. 1985. “Climatic effects on construction.” J. Constr. Eng. Manage. 111 (2): 129–137. https://doi.org/10.1061/(ASCE)0733-9364(1985)111:2(129).
Larsson, R., and M. Rudberg. 2019. “Impact of weather conditions on in situ concrete wall operations using a simulation-based approach.” J. Constr. Eng. Manage. 145 (7): 05019009. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001662.
Lee, D.-H., I.-S. Jung, J.-W. Park, and K.-H. Kim. 2018. Development of key performance index (KPI) and business model for construction projects (1/2). Goyang-si, South Korea: Korea Institute of Construction Technology.
Lee, H.-S., H.-G. Ryu, J.-H. Yu, and J.-J. Kim. 2005. “Method for calculating schedule delay considering lost productivity.” J. Constr. Eng. Manage. 131 (11): 1147–1154. https://doi.org/10.1061/(ASCE)0733-9364(2005)131:11(1147).
Lee, H.-S., J.-W. Shin, M. Park, and H.-G. Ryu. 2009. “Probabilistic duration estimation model for high-rise structural work.” J. Constr. Eng. Manage. 135 (12): 1289–1298. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000105.
LHI (Land & Housing Institute). 2015. A study on the method of estimating the construction duration for apartment to assure quality. Jinju-si, South Korea: Korea Land & Housing Corporation.
LHI (Land & Housing Institute). 2017. A study on the estimated standard for construction duration of school facility. Jinju-si, South Korea: Korea Land & Housing Corporation.
Li, Y., K. Lu, and Y. Lu. 2017. “Project schedule forecasting for skyscrapers.” J. Manage. Eng. 33 (3): 05016023. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000498.
Lim, J. H., D. Y. Kim, D. Kim, S.-C. Jeong, D.-K. Seol, and Y.-K. Huh. 2018. “Developing a construction duration estimation model to ensure the safety in apartment housing construction sites.” KSCE J. Civ. Eng. 22 (7): 2195–2205. https://doi.org/10.1007/s12205-017-0605-y.
Lucko, G., and E. M. Rojas. 2010. “Research validation: Challenges and opportunities in the construction domain.” J. Constr. Eng. Manage. 136 (1): 127–135. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000025.
Marzouk, M., and A. Hamdy. 2013. “Quantifying weather impact on formwork shuttering and removal operation using system dynamics.” KSCE J. Civ. Eng. 17 (4): 620–626. https://doi.org/10.1007/s12205-013-0301-5.
MassDOT (Massachusetts DOT). 2014. “Highway project controls toolkit, controls guidelines attachment A: Important work restrictions.” Accessed September 20, 2021. https://www.mass.gov/lists/massdot-highway-project-controls-toolkit.
MOLIT (Ministry of Land, Infrastructure, and Transport). 2019. Project duration calculation criteria for public construction projects. Sejong City, Republic of Korea: MOLIT.
Moselhi, O., and K. El-Rayes. 2002. “Analyzing weather-related construction claims.” Cost Eng. 44 (8): 12.
Nandakumar, V., and H. N. Ahuja. 1985. “Simulation model to forecast project completion time.” J. Constr. Eng. Manage. 111 (4): 325–342. https://doi.org/10.1061/(ASCE)0733-9364(1985)111:4(325).
NECA (National Electrical Contractors Association). 2004. The effect of temperature on productivity. Bethesda, MD: NECA.
Nguyen, L. D., J. Kneppers, B. García de Soto, and W. Ibbs. 2010. “Analysis of adverse weather for excusable delays.” J. Constr. Eng. Manage. 136 (12): 1258–1267. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000242.
Nguyen, L. D., D. H. Phan, and L. C. M. Tang. 2013. “Simulating construction duration for multistory buildings with controlling activities.” J. Constr. Eng. Manage. 139 (8): 951–959. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000677.
RS Means. 2012. RSMeans construction cost data. Norwell, MA: Construction Publishers & Consultants.
Shan, Y., and P. M. Goodrum. 2014. “Integration of building information modeling and critical path method schedules to simulate the impact of temperature and humidity at the project level.” Buildings 4 (3): 295–319. https://doi.org/10.3390/buildings4030295.
Thomas, H. R., D. R. Riley, and V. E. Sanvido. 1999. “Loss of labor productivity due to delivery methods and weather.” J. Constr. Eng. Manage. 125 (1): 39–46. https://doi.org/10.1061/(ASCE)0733-9364(1999)125:1(39).
Thomas, H. R., and A. S. Sakarcan. 1994. “Forecasting labor productivity using factor model.” J. Constr. Eng. Manage. 120 (1): 228–239. https://doi.org/10.1061/(ASCE)0733-9364(1994)120:1(228).
Thomas, H. R., and I. Yiakoumis. 1987. “Factor model of construction productivity.” J. Constr. Eng. Manage. 113 (4): 623–639. https://doi.org/10.1061/(ASCE)0733-9364(1987)113:4(623).
Thorpe, D., and E. P. Karan. 2008. “Method for calculating schedule delay considering weather conditions.” In Proc., 24th Annual Conf. of the Association of Researchers in Construction Management (ARCOM 2008), 809–818. Cardiff, Wales: Association of Researchers in Construction Management.
Woldesenbet, A., D. H. S. Jeong, and G. D. Oberlender. 2012. “Daily work reports–based production rate estimation for highway projects.” J. Constr. Eng. Manage. 138 (4): 481–490. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000442.
Yang, Y.-C., C.-J. Park, J.-H. Kim, and J.-J. Kim. 2007. “Management of daily progress in a construction project of multiple apartment buildings.” J. Constr. Eng. Manage. 133 (3): 242–253. https://doi.org/10.1061/(ASCE)0733-9364(2007)133:3(242).
Yi, W., and A. P. C. Chan. 2015. “Optimal work pattern for construction workers in hot weather: A case study in Hong Kong.” J. Comput. Civ. Eng. 29 (5): 05014009. https://doi.org/10.1061/(ASCE)CP.1943-5487.0000419.
Yoon, J., and I. Yu. 2017. “A study on estimating normal project duration of apartment remodeling project.” Korean J. Constr. Eng. Manage. 18 (2): 12–20. https://doi.org/10.6106/KJCEM.2017.18.2.012.
Yoon, J., and I. Yu. 2019. “Estimating normal duration of renovation for multistory apartment building considering extension-type renovation projects.” J. Civ. Eng. Manage. 25 (2): 156–167. https://doi.org/10.3846/jcem.2019.8024.
Zhao, T., and J. M. Dungan. 2019. “Loss of productivity analysis using project-specific curves.” J. Leg. Aff. Dispute Resolut. Eng. Constr. 11 (4): 04519027. https://doi.org/10.1061/(ASCE)LA.1943-4170.0000324.
Zou, X., Q. Zhang, and L. Zhang. 2018. “Modeling and solving the deadline satisfaction problem in line-of-balance scheduling.” J. Manage. Eng. 34 (1): 04017044. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000565.

Information & Authors

Information

Published In

Go to Journal of Management in Engineering
Journal of Management in Engineering
Volume 38Issue 4July 2022

History

Received: Sep 30, 2021
Accepted: Feb 16, 2022
Published online: Mar 25, 2022
Published in print: Jul 1, 2022
Discussion open until: Aug 25, 2022

Permissions

Request permissions for this article.

Authors

Affiliations

Senior Researcher, Technical Policy Research Team, Construction Engineer Policy Institute of Korea, Seoul 06098, South Korea. ORCID: https://orcid.org/0000-0001-5496-7661. Email: [email protected]
Professor, Dept. of Architectural Engineering, Ajou Univ., Gyeonggi-do 16499, South Korea. ORCID: https://orcid.org/0000-0002-5681-0411. Email: [email protected]
Assistant Professor, Dept. of Architectural Engineering, Ajou Univ., Gyeonggi-do 16499, South Korea (corresponding author). ORCID: https://orcid.org/0000-0002-3904-4305. Email: [email protected]

Metrics & Citations

Metrics

Citations

Download citation

If you have the appropriate software installed, you can download article citation data to the citation manager of your choice. Simply select your manager software from the list below and click Download.

Cited by

  • Space–Time–Workforce Visualization and Conditional Capacity Synthesis in Uncertainty, Journal of Management in Engineering, 10.1061/JMENEA.MEENG-4991, 39, 2, (2023).

View Options

Get Access

Access content

Please select your options to get access

Log in/Register Log in via your institution (Shibboleth)
ASCE Members: Please log in to see member pricing

Purchase

Save for later Information on ASCE Library Cards
ASCE Library Cards let you download journal articles, proceedings papers, and available book chapters across the entire ASCE Library platform. ASCE Library Cards remain active for 24 months or until all downloads are used. Note: This content will be debited as one download at time of checkout.

Terms of Use: ASCE Library Cards are for individual, personal use only. Reselling, republishing, or forwarding the materials to libraries or reading rooms is prohibited.
ASCE Library Card (5 downloads)
$105.00
Add to cart
ASCE Library Card (20 downloads)
$280.00
Add to cart
Buy Single Article
$35.00
Add to cart

Get Access

Access content

Please select your options to get access

Log in/Register Log in via your institution (Shibboleth)
ASCE Members: Please log in to see member pricing

Purchase

Save for later Information on ASCE Library Cards
ASCE Library Cards let you download journal articles, proceedings papers, and available book chapters across the entire ASCE Library platform. ASCE Library Cards remain active for 24 months or until all downloads are used. Note: This content will be debited as one download at time of checkout.

Terms of Use: ASCE Library Cards are for individual, personal use only. Reselling, republishing, or forwarding the materials to libraries or reading rooms is prohibited.
ASCE Library Card (5 downloads)
$105.00
Add to cart
ASCE Library Card (20 downloads)
$280.00
Add to cart
Buy Single Article
$35.00
Add to cart

Media

Figures

Other

Tables

Share

Share

Copy the content Link

Share with email

Email a colleague

Share