Sustainable Logistics Planning in Modular Integrated Construction Using Multimethod Simulation and Taguchi Approach

Publication: Journal of Construction Engineering and Management
Volume 148, Issue 6

Abstract

This study examined logistics planning in the modular integrated construction supply chain (MiC-SC). Existing models overlook two important characteristics of the MiC-SC—the dynamic behavior of its stakeholders, and the uncertain interactions between its activities and resources—making their applicability limited in real practice. The literature also lacks an understanding of which logistics and construction decisions significantly impact the MiC-SC key performance indicators (KPIs) (e.g., project duration, MiC-SC costs, and emissions). Moreover, optimizing logistics and construction decisions to achieve a trade-off between these KPIs is yet to be addressed. This study contributes to the MiC-SC knowledge by (1) developing a multimethod simulation model that captures the dynamic behavior of MiC-SC stakeholders through agent-based modeling and the uncertain interactions between their internal activities and resources using discrete-event simulation and considering more realistic features such as traffic condition, site layout, heterogeneous truck types, and uncertainty of activities duration; (2) integrating the developed model with the Taguchi approach (TA) to identify the significant logistics and construction decisions that impact five KPIs (project duration, construction costs, construction emissions, logistics costs, and logistics emissions); and (3) applying a simulation-optimization (SO) approach to find the near-optimum logistics and construction decisions that maximize the MiC-SC sustainability through minimizing the project duration, total costs, and carbon emissions. The model’s applicability was demonstrated using a case study of a high-rise MiC project. The TA analysis highlighted some interactions between logistics and construction decisions, calling for collaborative decision-making between stakeholders. The proposed SO approach could provide them with near-optimum decisions that minimize the project duration, MiC-SC costs, and emissions.

Get full access to this article

View all available purchase options and get full access to this article.

Data Availability Statement

Some or all data, models, or code that support this study’s findings are available from the corresponding author upon reasonable request.

References

AbouRizk, S. M., S. Hague, and R. Ekyalimpa. 2016. Construction simulation: An introduction using Simphony. Edmonton, AB: Canada Univ. Alberta.
AbouRizk, S. M., and D. W. Halpin. 1992. “Statistical properties of construction duration data.” J. Constr. Eng. Manage. 118 (3): 525–544. https://doi.org/10.1061/(ASCE)0733-9364(1992)118:3(525).
Ahn, S. J., S. U. Han, and M. Al-Hussein. 2020. “Improvement of transportation cost estimation for prefabricated construction using geo-fence-based large-scale GPS data feature extraction and support vector regression.” Adv. Eng. Inf. 43 (Jan): 101012. https://doi.org/10.1016/j.aei.2019.101012.
Al Hattab, M., E. Zankoul, and F. R. Hamzeh. 2017. “Near-real-time optimization of overlapping tower crane operations: A model and case study.” J. Comput. Civ. Eng. 31 (4): 05017001. https://doi.org/10.1061/(ASCE)CP.1943-5487.0000666.
Almashaqbeh, M., and K. El-Rayes. 2021. “Minimizing transportation cost of prefabricated modules in modular construction projects.” Eng. Constr. Archit. Manage. https://doi.org/10.1108/ECAM-11-2020-0969.
Bamana, F., N. Lehoux, and C. Cloutier. 2019. “Simulation of a construction project: Assessing impact of just-in-time and lean principles.” J. Constr. Eng. Manage. 145 (5): 05019005. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001654.
Bandinelli, R., M. Rapaccini, M. Tucci, and F. Visintin. 2006. “Using simulation for supply chain analysis: Reviewing and proposing distributed simulation frameworks.” Prod. Plann. Control 17 (2): 167–175. https://doi.org/10.1080/09537280500224051.
Barkokebas, B., S. Khalife, M. Al-Hussein, and F. Hamzeh. 2021. “A BIM-lean framework for digitalisation of premanufacturing phases in offsite construction.” Eng. Constr. Archit. Manage. 28 (8): 2155–2175. https://doi.org/10.1108/ECAM-11-2020-0986.
Borshchev, A. 2013. The big book of simulation modeling: Multimethod modeling with AnyLogic 6. Lisle, IL: AnyLogic North America.
Byrne, B. M. 2010. Structural equation modeling with AMOS: Basic concepts, applications, and programming. 3rd ed. New York: Taylor & Francis.
Chen, C., L. K. Tiong, and I.-M. Chen. 2019. “Using a genetic algorithm to schedule the space-constrained AGV-based prefabricated bathroom units manufacturing system.” Int. J. Prod. Res. 57 (10): 3003–3019. https://doi.org/10.1080/00207543.2018.1521532.
Chen, J.-H., S. Yan, H.-W. Tai, and C.-Y. Chang. 2017. “Optimizing profit and logistics for precast concrete production.” Can. J. Civ. Eng. 44 (6): 393–406. https://doi.org/10.1139/cjce-2016-0401.
CIC (Construction Industry Council). 2020. Reference material on logistics and transport for modular integrated construction projects. London: CIC.
CIC (Construction Industry Council). 2021. “Projects in Hong Kong.” Accessed March 3, 2022. http://mic.cic.hk/en/ProjectsInHongKong.
Dorrah, D. H., and M. Marzouk. 2021. “Integrated multi-objective optimization and agent-based building occupancy modeling for space layout planning.” J. Build. Eng. 34 (Feb): 101902. https://doi.org/10.1016/j.jobe.2020.101902.
Fang, Y., and S. T. Ng. 2019. “Genetic algorithm for determining the construction logistics of precast components.” Eng. Constr. Archit. Manage. 26 (Nov): 2289–2306. https://doi.org/10.1108/ECAM-09-2018-0386.
Ferdous, W., Y. Bai, T. D. Ngo, A. Manalo, and P. Mendis. 2019. “New advancements, challenges and opportunities of multi-storey modular buildings—A state-of-the-art review.” Eng. Struct. 183 (Mar): 883–893. https://doi.org/10.1016/j.engstruct.2019.01.061.
Goh, M., and Y. M. Goh. 2019. “Lean production theory-based simulation of modular construction processes.” Autom. Constr. 101 (May): 227–244. https://doi.org/10.1016/j.autcon.2018.12.017.
Gunawardena, T., T. Ngo, P. Mendis, L. Aye, and R. Crawford. 2014. “Time-efficient post-disaster housing reconstruction with prefabricated modular structures.” Open House Int. 39 (3): 59–69. https://doi.org/10.1108/OHI-03-2014-B0007.
Hair, J. F. 2009. Multivariate data analysis: A global perspective. 7th ed. Upper Saddle River, NJ: Prentice Hall.
Hammad, A. W., H. Grzybowska, M. Sutrisna, A. Akbarnezhad, and A. Haddad. 2020. “A novel mathematical optimisation model for the scheduling of activities in modular construction factories.” Construct. Manage. Econ. 38 (6): 534–551. https://doi.org/10.1080/01446193.2019.1682174.
Han, S., A. Bouferguene, M. Al-Hussein, and U. Hermann. 2017. “3D-based crane evaluation system for mobile crane operation selection on modular-based heavy construction sites.” J. Constr. Eng. Manage. 143 (9): 04017060. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001360.
Han, S. H., M. Al-Hussein, S. Al-Jibouri, and H. Yu. 2012. “Automated post-simulation visualization of modular building production assembly line.” Autom. Constr. 21 (Jan): 229–236. https://doi.org/10.1016/j.autcon.2011.06.007.
Han, S. H., S. Hasan, A. Bouferguène, M. Al-Hussein, and J. Kosa. 2015. “Utilization of 3D visualization of mobile crane operations for modular construction on-site assembly.” J. Manage. Eng. 31 (5): 04014080. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000317.
Hasan, S., A. Bouferguene, M. Al-Hussein, P. Gillis, and A. Telyas. 2013. “Productivity and CO2 emission analysis for tower crane utilization on high-rise building projects.” Autom. Constr. 31 (May): 255–264. https://doi.org/10.1016/j.autcon.2012.11.044.
Heravi, G., M. Rostami, and M. F. Kebria. 2020. “Energy consumption and carbon emissions assessment of integrated production and erection of buildings’ pre-fabricated steel frames using lean techniques.” J. Cleaner Prod. 253 (Apr): 120045. https://doi.org/10.1016/j.jclepro.2020.120045.
Hickman, J., D. Hassel, R. Joumard, Z. Samaras, and S. Sorenson. 1999. Methodology for calculating transport emissions and energy consumption. Rep. No. SE/491/98. Brussels, Belgium: European Commission.
Hong, T., J. Kim, and M. Lee. 2019. “A multi-objective optimization model for determining the building design and occupant behaviors based on energy, economic, and environmental performance.” Energy 174 (May): 823–834. https://doi.org/10.1016/j.energy.2019.02.035.
Hsu, P. Y., P. Angeloudis, and M. Aurisicchio. 2018. “Optimal logistics planning for modular construction using two-stage stochastic programming.” Autom. Constr. 94 (Oct): 47–61. https://doi.org/10.1016/j.autcon.2018.05.029.
Hsu, P. Y., M. Aurisicchio, and P. Angeloudis. 2019. “Risk-averse supply chain for modular construction projects.” Autom. Constr. 106 (Oct): 102898. https://doi.org/10.1016/j.autcon.2019.102898.
Hussein, M., A. E. E. Eltoukhy, A. Darko, and A. Eltawil. 2021a. “Simulation-optimization for the planning of off-site construction projects: A comparative study of recent swarm intelligence metaheuristics.” Sustain. https://doi.org/10.3390/su132413551.
Hussein, M., A. E. E. Eltoukhy, A. Karam, I. A. Shaban, and T. Zayed. 2021b. “Modelling in off-site construction supply chain management: A review and future directions for sustainable modular integrated construction.” J. Cleaner Prod. 310 (Aug): 127503. https://doi.org/10.1016/j.jclepro.2021.127503.
Hyun, H., I. Yoon, H.-S. Lee, M. Park, and J. Lee. 2021. “Multiobjective optimization for modular unit production lines focusing on crew allocation and production performance.” Autom. Constr. 125 (May): 103581. https://doi.org/10.1016/j.autcon.2021.103581.
Jaśkowski, P., A. Sobotka, and A. Czarnigowska. 2018. “Decision model for planning material supply channels in construction.” Autom. Constr. 90 (Jun): 235–242. https://doi.org/10.1016/j.autcon.2018.02.026.
Jeong, J., T. Hong, C. Ji, J. Kim, M. Lee, K. Jeong, and S. Lee. 2017. “An integrated evaluation of productivity, cost and CO2 emission between prefabricated and conventional columns.” J. Cleaner Prod. 142 (Jan): 2393–2406. https://doi.org/10.1016/j.jclepro.2016.11.035.
Juan, A. A., J. Faulin, S. E. Grasman, M. Rabe, and G. Figueira. 2015. “A review of simheuristics: Extending metaheuristics to deal with stochastic combinatorial optimization problems.” Oper. Res. Perspect. 2 (Dec): 62–72. https://doi.org/10.1016/j.orp.2015.03.001.
Kamali, M., and K. Hewage. 2016. “Life cycle performance of modular buildings: A critical review.” Renewable Sustainable Energy Rev. 62 (Sep): 1171–1183. https://doi.org/10.1016/j.rser.2016.05.031.
Kong, L., H. Li, H. Luo, L. Ding, and X. Zhang. 2018. “Sustainable performance of just-in-time (JIT) management in time-dependent batch delivery scheduling of precast construction.” J. Cleaner Prod. 193 (Aug): 684–701. https://doi.org/10.1016/j.jclepro.2018.05.037.
Lee, Y., J. I. Kim, F. Flager, and M. Fischer. 2021. “Generation of stacking plans for prefabricated exterior wall panels shipped vertically with A-frames.” Autom. Constr. 122 (Feb): 103507. https://doi.org/10.1016/j.autcon.2020.103507.
Li, J.-Q., Y.-Q. Han, P.-Y. Duan, Y.-Y. Han, B. Niu, C.-D. Li, Z.-X. Zheng, and Y.-P. Liu. 2020. “Meta-heuristic algorithm for solving vehicle routing problems with time windows and synchronized visit constraints in prefabricated systems.” J. Cleaner Prod. 250 (Mar): 119464. https://doi.org/10.1016/j.jclepro.2019.119464.
Liu, D., X. Li, J. Chen, and R. Jin. 2020a. “Real-time optimization of precast concrete component transportation and storage.” Adv. Civ. Eng. 2020: 5714910. https://doi.org/10.1155/2020/5714910.
Liu, G., H. Yang, Y. Fu, C. Mao, P. Xu, J. Hong, and R. Li. 2020b. “Cyber-physical system-based real-time monitoring and visualization of greenhouse gas emissions of prefabricated construction.” J. Cleaner Prod. 246 (Feb): 119059. https://doi.org/10.1016/j.jclepro.2019.119059.
Liu, J., M. Soleimanifar, and M. Lu. 2017. “Resource-loaded piping spool fabrication scheduling: Material-supply-driven optimization.” Visual Eng. 5 (1): 1–14. https://doi.org/10.1186/s40327-017-0044-3.
Liu, S., A. Mansoor, B. Kugyelka, A. Bouferguene, and M. Al-Hussein. 2019. “On-site assembly of modular building using discrete event simulation.” In Proc., Winter Simulation Conf., 3008–3018. New York: IEEE. https://doi.org/10.1109/WSC40007.2019.9004896.
Luo, H., J. Liu, C. Li, K. Chen, and M. Zhang. 2020. “Ultra-rapid delivery of specialty field hospitals to combat COVID-19: Lessons learned from the Leishenshan Hospital project in Wuhan.” Autom. Constr. 119 (Nov): 103345. https://doi.org/10.1016/j.autcon.2020.103345.
Mahdavi, A. 2020. The art of process-centric modeling with AnyLogic. New York: AnyLogic Company.
Marler, R. T., and J. S. Arora. 2005. “Function-transformation methods for multi-objective optimization.” Eng. Optim. 37 (6): 551–570. https://doi.org/10.1080/03052150500114289.
Marzouk, M., H. Said, and M. El-Said. 2009. “Framework for multiobjective optimization of launching girder bridges.” J. Constr. Eng. Manag. 135 (1): 791–800. https://doi.org/10.1061/(ASCE)0733-9364(2009)135:8(791).
McCabe, B. 2003. “Construction engineering and project management III: Monte carlo simulation for schedule risks.” In Proc., 35th Conf. on Winter Simulation: Driving Innovation, 1561–1565. New York: IEEE.
Miller, J. H. 1998. “Active nonlinear tests (ANTs) of complex simulation models.” Manage. Sci. 44 (6): 820–830. https://doi.org/10.1287/mnsc.44.6.820.
Moghadam, M., M. Al-Hussein, S. Al-Jibouri, and A. Telyas. 2012. “Post simulation visualization model for effective scheduling of modular building construction.” Can. J. Civ. Eng. 39 (9): 1053–1061. https://doi.org/10.1139/l2012-077.
North, M. J., and C. M. Macal. 2007. Managing business complexity: Discovering strategic solutions with agent-based modeling and simulation. Oxford, UK: Oxford University Press.
Olearczyk, J., M. Al-Hussein, and A. Bouferguène. 2014. “Evolution of the crane selection and on-site utilization process for modular construction multilifts.” Autom. Constr. 43 (Jul): 59–72. https://doi.org/10.1016/j.autcon.2014.03.015.
OptTek. 2022. “OptQuest, The world’s leading optimization engine.” Accessed March 3, 2022. https://www.opttek.com/products/optquest/.
Pan, N.-H., M.-L. Lee, and S.-Q. Chen. 2011. “Construction material supply chain process analysis and optimization.” J. Civ. Eng. Manage. 17 (3): 357–370. https://doi.org/10.3846/13923730.2011.594221.
Pan, N.-H., Y.-Y. Lin, and N.-F. Pan. 2010. “Enhancing construction project supply chains and performance evaluation methods: A case study of a bridge construction project.” Can. J. Civ. Eng. 37 (8): 1094–1106. https://doi.org/10.1139/L10-047.
Pan, W., and C. K. Hon. 2020. “Briefing: Modular integrated construction for high-rise buildings.” In Proc., Institution of Civil Engineers–Municipal Engineer, 64–68. London: Thomas Telford.
Rand, W., and R. T. Rust. 2011. “Agent-based modeling in marketing: Guidelines for rigor.” Int. J. Res. Marketing 28 (3): 181–193. https://doi.org/10.1016/j.ijresmar.2011.04.002.
Rashid, K., J. Louis, and C. Swanson. 2020. “Optimizing labor allocation in modular construction factory using discrete event simulation and genetic algorithm.” In Proc., 2020 Winter Simulation Conf. (WSC), 2569–2576. New York: IEEE. https://doi.org/10.1109/WSC48552.2020.9383867.
Rossetti, M. D. 2015. Simulation modeling and Arena. New York: Wiley.
Roy, R. K. 2001. Design of experiments using the taguchi approach: 16 steps to product and process improvement. New York: Wiley. https://doi.org/10.1198/004017002320256440.
RS Means. 2001. Heavy construction cost data. London: RS Means.
Salama, T., A. Salah, and O. Moselhi. 2021. “Integrating critical chain project management with last planner system for linear scheduling of modular construction.” Constr. Innovation 21 (4): 525–554. https://doi.org/10.1108/CI-05-2018-0046.
Salama, T., A. Salah, O. Moselhi, and M. Al-Hussein. 2017. “Near optimum selection of module configuration for efficient modular construction.” Autom. Constr. 83 (Nov): 316–329. https://doi.org/10.1016/j.autcon.2017.03.008.
Sandanayake, M., G. Zhang, S. Setunge, C.-Q. Li, and J. Fang. 2016. “Models and method for estimation and comparison of direct emissions in building construction in Australia and a case study.” Energy Build. 126 (Aug): 128–138. https://doi.org/10.1016/j.enbuild.2016.05.007.
Sargent, R. G. 2013. “Verification and validation of simulation models.” J. Simul. 7 (1): 12–24. https://doi.org/10.1057/jos.2012.20.
Shao, G., S. J. Shin, and S. Jain. 2015. “Data analytics using simulation for smart manufacturing.” In Proc., Winter Simul. Conf., 2192–2203. New York: IEEE. https://doi.org/10.1109/WSC.2014.7020063.
Siebers, P. O., C. M. Macal, J. Garnett, D. Buxton, and M. Pidd. 2010. “Discrete-event simulation is dead, long live agent-based simulation!” J. Simul. 4 (3) 204–210. https://doi.org/10.1057/jos.2010.14.
Taghaddos, H., U. Hermann, S. Abourizk, and Y. Mohamed. 2014. “Simulation-based multiagent approach for scheduling modular construction.” J. Comput. Civ. Eng. 28 (2): 263–274. https://doi.org/10.1061/(ASCE)CP.1943-5487.0000262.
Tommelein, I. D., and M. Weissenberger. 1999. “More just-in-time: Location of buffers in structural steel supply and construction processes.” In Proc., IGLC 109–120. Berkeley, CA: Univ. of California.
Wang, T., M. Abdallah, C. Clevenger, and S. Monghasemi. 2019. “Time–cost–quality trade-off analysis for planning construction projects.” Eng. Constr. Archit. Manage. 28 (1): 82–100. https://doi.org/10.1108/ECAM-12-2017-0271.
Wang, Z., and H. Hu. 2017. “Improved precast production–scheduling model considering the whole supply chain.” J. Comput. Civ. Eng. 31 (4): 04017013. https://doi.org/10.1061/(ASCE)CP.1943-5487.0000667.
Wang, Z., H. Hu, and J. Gong. 2018a. “Framework for modeling operational uncertainty to optimize offsite production scheduling of precast components.” Autom. Constr. 86 (Feb): 69–80. https://doi.org/10.1016/j.autcon.2017.10.026.
Wang, Z., H. Hu, and J. Gong. 2018b. “Simulation based multiple disturbances evaluation in the precast supply chain for improved disturbance prevention.” J. Cleaner Prod. 177 (Mar): 232–244. https://doi.org/10.1016/j.jclepro.2017.12.188.
Yang, H., J. K. H. Chung, Y. Chen, Y. Pan, Z. Mei, and X. Sun. 2018. “Ordering strategy analysis of prefabricated component manufacturer in construction supply chain.” Mathematical Problems Eng. 2018: 1–16. https://doi.org/10.1155/2018/4062871.
Yi, W., S. Wang, and A. Zhang. 2020. “Optimal transportation planning for prefabricated products in construction.” Comput. Civ. Infrastruct. Eng. 35 (4): 342–353. https://doi.org/10.1111/mice.12504.
Younes, A., and M. Marzouk. 2018. “Tower cranes layout planning using agent-based simulation considering activity conflicts.” Autom. Constr. 93 (Sep): 348–360. https://doi.org/10.1016/j.autcon.2018.05.030.
Yusuf, M. M., A. Karam, and A. B. Eltawil. 2019a. “A simulation based optimization study for optimum sequencing of precast components considering supply chain risks.” In Proc., 8th Conf. on Operations Research and Enterprise Systems, 330–337. Setúbal, Portugal: Science and Technology Publications. https://doi.org/10.5220/0007373303300337.
Yusuf, M. M., A. Karam, and A. B. Eltawil. 2019b. “A stochastic optimization approach of flow shop sequencing problem for on-time delivery of precast components.” In Proc., 8th Int. Conf. on Operations Research and Enterprise Systems, 245–252. Setúbal, Portugal: Science and Technology Publications. https://doi.org/10.5220/0007309602450252.
Zaiontz, C. 2015. “Statistics using excel succinctly.” Accessed March 3, 2022. https://www.syncfusion.com/succinctly-free-ebooks/statistics.
Zankoul, E., and H. Khoury. 2016. “Modeling, animating, and optimizing on-shore wind farm construction operations.” J. Comput. Civ. Eng. 30 (6): 5016001. https://doi.org/10.1061/(ASCE)CP.1943-5487.0000567.
Zhai, Y., T.-M. Choi, S. Shao, S. X. Xu, and G. Q. Huang. 2020. “Spatial-temporal hedging coordination in prefabricated housing production.” Int. J. Prod. Econ. 229 (Nov): 107792. https://doi.org/10.1016/j.ijpe.2020.107792.
Zhai, Y., Y. Fu, G. Xu, and G. Huang. 2019. “Multi-period hedging and coordination in a prefabricated construction supply chain.” Int. J. Prod. Res. 57 (7): 1949–1971. https://doi.org/10.1080/00207543.2018.1512765.
Zhai, Y., R. Y. Zhong, and G. Q. Huang. 2018. “Buffer space hedging and coordination in prefabricated construction supply chain management.” Int. J. Prod. Econ. 200 (Jun): 192–206. https://doi.org/10.1016/j.ijpe.2018.03.014.
Zhang, H., and L. Yu. 2020. “Dynamic transportation planning for prefabricated component supply chain.” Eng. Constr. Archit. Manage. 27 (Apr): 2553–2576. https://doi.org/10.1108/ECAM-12-2019-0674.
Zhang, H., and L. Yu. 2021. “Resilience-cost tradeoff supply chain planning for the prefabricated construction project.” J. Civ. Eng. Manage. 27 (1): 45–59. https://doi.org/10.3846/jcem.2021.14114.
Zhang, Y., Z. Lei, S. Han, A. Bouferguene, and M. Al-Hussein. 2020. “Process-oriented framework to improve modular and offsite construction manufacturing performance.” J. Constr. Eng. Manage. 146 (9): 04020116. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001909.
Zhu, M., J. Dai, R. Liu, J. Xu, and A. Alwisy. 2021. “Two-period based carbon-economy equilibrium strategy for modular construction supply planning.” J. Cleaner Prod. 290 (Mar): 125674. https://doi.org/10.1016/j.jclepro.2020.125674.

Information & Authors

Information

Published In

Go to Journal of Construction Engineering and Management
Journal of Construction Engineering and Management
Volume 148Issue 6June 2022

History

Received: Jul 2, 2021
Accepted: Jan 14, 2022
Published online: Mar 16, 2022
Published in print: Jun 1, 2022
Discussion open until: Aug 16, 2022

Permissions

Request permissions for this article.

Authors

Affiliations

Ph.D. Student, Dept. of Building and Real Estate, Hong Kong Polytechnic Univ., Kowloon, Hong Kong SAR (corresponding author). ORCID: https://orcid.org/0000-0002-7153-9308. Email: [email protected]
Assistant Professor, Dept. of Building and Real Estate, Hong Kong Polytechnic Univ., Kowloon, Hong Kong SAR. ORCID: https://orcid.org/0000-0002-7978-6039. Email: [email protected]
Abdelrahman E. E. Eltoukhy [email protected]
Research Assistant Professor, Dept. of Industrial and Systems Engineering, Hong Kong Polytechnic Univ., Kowloon, Hong Kong SAR. Email: [email protected]
Tarek Zayed, F.ASCE [email protected]
Professor, Dept. of Building and Real Estate, Hong Kong Polytechnic Univ., Kowloon, Hong Kong SAR. Email: [email protected]

Metrics & Citations

Metrics

Citations

Download citation

If you have the appropriate software installed, you can download article citation data to the citation manager of your choice. Simply select your manager software from the list below and click Download.

Cited by

  • A Comprehensive Evaluation Model with TOPSIS Method for Construction Site Layout of Building Projects and Its Applications, Journal of Urban Planning and Development, 10.1061/JUPDDM.UPENG-4640, 150, 3, (2024).
  • Mixed Reality-Based Approach for Minimizing Time Uncertainty in Prefabrication, Journal of Construction Engineering and Management, 10.1061/JCEMD4.COENG-14846, 150, 11, (2024).
  • Critical Review of Virtual Reality Applications in Offsite Construction Research, Journal of Construction Engineering and Management, 10.1061/JCEMD4.COENG-14837, 150, 11, (2024).
  • Transportation-Induced Impact on a Prefinished Volumetric Modular House Using Trailer Bogie: Case Study, Journal of Construction Engineering and Management, 10.1061/JCEMD4.COENG-14567, 150, 7, (2024).
  • Offsite Construction Supply Chain Challenges: An Integrated Overview, Journal of Construction Engineering and Management, 10.1061/JCEMD4.COENG-14444, 150, 7, (2024).
  • Corporate Climate Pledges of High-Revenue Design Firms and Contractors, Journal of Construction Engineering and Management, 10.1061/JCEMD4.COENG-13719, 150, 2, (2024).
  • Sensor-Integrated Hybrid Blockchain System for Supply Chain Coordination in Volumetric Modular Construction, Journal of Construction Engineering and Management, 10.1061/(ASCE)CO.1943-7862.0002427, 149, 1, (2023).
  • Optimized multimodal logistics planning of modular integrated construction using hybrid multi-agent and metamodeling, Automation in Construction, 10.1016/j.autcon.2022.104637, 145, (104637), (2023).
  • SÜRDÜRÜLEBİLİR LOJİSTİK ALT BİLEŞENLERİNİN TESPİTİ VE SÜRDÜRÜLEBİLİR LOJİSTİK BİLEŞENLERİNİN ETKİ DÜZEYLERİNİN DEMATEL YÖNTEMİ İLE BELİRLENMESİ, Toros Üniversitesi İİSBF Sosyal Bilimler Dergisi, 10.54709/iisbf.1166388, (2022).
  • Optimisation of the Logistics System in an Electric Motor Assembly Flowshop by Integrating the Taguchi Approach and Discrete Event Simulation, Sustainability, 10.3390/su142416770, 14, 24, (16770), (2022).
  • See more

View Options

Get Access

Access content

Please select your options to get access

Log in/Register Log in via your institution (Shibboleth)
ASCE Members: Please log in to see member pricing

Purchase

Save for later Information on ASCE Library Cards
ASCE Library Cards let you download journal articles, proceedings papers, and available book chapters across the entire ASCE Library platform. ASCE Library Cards remain active for 24 months or until all downloads are used. Note: This content will be debited as one download at time of checkout.

Terms of Use: ASCE Library Cards are for individual, personal use only. Reselling, republishing, or forwarding the materials to libraries or reading rooms is prohibited.
ASCE Library Card (5 downloads)
$105.00
Add to cart
ASCE Library Card (20 downloads)
$280.00
Add to cart
Buy Single Article
$35.00
Add to cart

Get Access

Access content

Please select your options to get access

Log in/Register Log in via your institution (Shibboleth)
ASCE Members: Please log in to see member pricing

Purchase

Save for later Information on ASCE Library Cards
ASCE Library Cards let you download journal articles, proceedings papers, and available book chapters across the entire ASCE Library platform. ASCE Library Cards remain active for 24 months or until all downloads are used. Note: This content will be debited as one download at time of checkout.

Terms of Use: ASCE Library Cards are for individual, personal use only. Reselling, republishing, or forwarding the materials to libraries or reading rooms is prohibited.
ASCE Library Card (5 downloads)
$105.00
Add to cart
ASCE Library Card (20 downloads)
$280.00
Add to cart
Buy Single Article
$35.00
Add to cart

Media

Figures

Other

Tables

Share

Share

Copy the content Link

Share with email

Email a colleague

Share