Time-Cost Optimization of Construction Projects with Generalized Activity Constraints
Publication: Journal of Construction Engineering and Management
Volume 131, Issue 10
Abstract
Time-cost analysis is an important element of project scheduling, especially for lengthy and costly construction projects, as it evaluates alternative schedules and establishes an optimum one considering any project completion deadline. Existing methods for time-cost analysis have not adequately considered typical activity and project characteristics, such as generalized precedence relationships between activities, external time constraints, activity planning constraints, and bonuses/penalties for early/delayed project completion that would provide a more realistic representation of actual construction projects. The present work aims to incorporate such characteristics in the analysis and has developed two solution methods, an exact and an approximate one. The exact method utilizes a linear/integer programming model to provide the optimal project time-cost curve and the minimum cost schedule considering all activity time-cost alternatives together. The approximate method performs a progressive project length reduction providing a near-optimal project time-cost curve but it is faster than the exact method as it examines only certain activities at each stage. In addition, it can be easily incorporated in project scheduling software. Evaluation results indicate that both methods can effectively simulate the structure of construction projects, and their application is expected to provide time and cost savings.
Get full access to this article
View all available purchase options and get full access to this article.
References
Bartusch, M., Möhring, R. H., and Radermacher, F. J. (1988). “Scheduling project networks with resource constraints and time windows.” Ann. Operat. Res., 16, 201–240.
Brucker, P., Drexl, A., Möhring, R., Neumann, K., and Pesch, E. (1999). “Resource-constrained project scheduling: Notation, classification, models, and methods.” Eur. J. Oper. Res., 112, 3–41.
Chassiakos, A. P., Samaras, C. I., and Theodorakopoulos, D. D. (2000). “An integer programming method for CPM time-cost analysis.” Comput. Model. Eng. Sci., 1(4), 9–18.
Coskunoglu, O. (1984). “Optimal probabilistic compression of PERT networks.” J. Constr. Eng. Manage., 110(4), 437–446.
De, P., Dunne, E. J., Ghosh, J. B., and Wells, C. E. (1995). “The discrete time-cost trade-off problem revisited.” Eur. J. Oper. Res., 81, 225–238.
Elmaghraby, S. E., and Kamburowski, J. (1992). “The analysis of activity networks under generalized precedence relations.” Manage. Sci., 38, 1245–1263.
Feng, C. W., Liu, L., and Burns, S. A. (1997). “Using genetic algorithms to solve construction time-cost trade-off problems.” J. Comput. Civ. Eng., 11(3), 184–189.
Feng, C. W., Liu, L., and Burns, S. A. (2000). “Stochastic construction time-cost trade-off analysis.” J. Comput. Civ. Eng., 14(2), 117–126.
Isidore, L. J., and Back, W. E. (2001). “Probabilistic optimal-cost scheduling.” J. Constr. Eng. Manage., 127(6), 431–437.
Laslo, Z. (2003). “Activity time-cost tradeoffs under time and cost chance constraints.” Comput. Ind. Eng., 44(3), 365–384.
Leu, S. S., and Yang, C. H. (1999). “GA-based multicriteria optimal model for construction scheduling.” J. Constr. Eng. Manage., 125(6), 420–427.
Li, H., Cao, J. N., and Love, P. E. D. (1999). “Using machine learning and GA to solve time-cost trade-off problems.” J. Constr. Eng. Manage., 125(5), 347–353.
Liu, L., Burns, S. A., and Feng, C. W. (1995). “Construction time-cost trade-off analysis using LP/IP hybrid method.” J. Constr. Eng. Manage., 121(4), 446–454.
Moussourakis, J., and Haksever, C. (2004). “Flexible model for time/cost tradeoff problem.” J. Constr. Eng. Manage., 130(3), 307–314.
Neumann, K., and Zhan, J. (1995). “Heuristics for the minimum project duration problem with minimal and maximal time lags under fixed resource constraints.” J. Intell. Manufact., 6, 145–154.
O’Brien, W. J., and Fischer, M. A. (2000). “Importance of capacity constraints to construction cost and schedule.” J. Constr. Eng. Manage., 126(5), 366–373.
Panagiotakopoulos, D. (1977). “Cost-time model for large CPM project networks.” J. Constr. Div., Am. Soc. Civ. Eng., 103(2), 201–211.
Perera, S. (1980). “Linear programming solution to network compression.” J. Constr. Div., Am. Soc. Civ. Eng., 106(3), 315–326.
Reda, R., and Carr, R. I. (1989). “Time-cost trade-off among related activities.” J. Constr. Eng. Manage., 115(3), 475–486.
Robinson, D. R. (1975). “A dynamic programming solution to cost-time trade-off for CPM.” Manage. Sci., 22(2), 158–166.
Schrage, L. E. (1997). Optimization modeling with Lindo, 5th Ed., Brooks and Cole, eds., Duxbury Press, Pacific Grove, Calif., 299–300.
Shtub, A., Bard, J., and Globerson, S. (1994). Project management: Engineering, technology and implementations, Prentice Hall International Eds., Prentice Hall, Englewood Cliffs, N.J., 382–392.
Zheng, D. X. M., Ng, S. T., and Kumaraswamy, M. M. (2004). “Applying a genetic algorithm-based multiobjective approach for time-cost optimization.” J. Constr. Eng. Manage., 130(2), 168–176.
Information & Authors
Information
Published In
Copyright
© 2005 ASCE.
History
Received: Aug 5, 2004
Accepted: Dec 9, 2004
Published online: Oct 1, 2005
Published in print: Oct 2005
Authors
Metrics & Citations
Metrics
Citations
Download citation
If you have the appropriate software installed, you can download article citation data to the citation manager of your choice. Simply select your manager software from the list below and click Download.