Abstract

Construction project delays can stem from a myriad of factors and pose significant challenges for owners and contractors. While numerous methods for analyzing delays exist, the majority are designed for network scheduling, lack contemporaneous tracking (i.e., do not allow for identifying and tracking delays as they occur), and struggle with attributing delays to specific stakeholders. Therefore, this paper introduces a novel graphical approach to monitor delays by comparing as-planned and as-built schedules at the activity level. Distinguished by its contemporaneous nature, the new method allows real-time tracking and quantification of delays. This facilitates identifying their origin and potential causes. Rules for constructing the graphs of various delay scenarios are demonstrated for typical activity combinations. The effectiveness of the proposed method is validated via a case study that showcases its practical application. Implementing it is straightforward, and while the method could be applied to network schedules, its relevance lies in linear and repetitive schedules. The cyclic nature of tasks in such schedules underscores the importance of contemporaneous delay tracking to facilitate swift remedial actions and pinpoint liability.

Practical Applications

In this study, the authors present a new way to track delay using graphs by comparing starts, productivities, and finishes of as-planned and as-built schedules at the activity level. Because it is contemporaneous, the new approach tracks and measures delays in real time, currently manually, but easily implemented as computer code. This method makes it easier to find the source and possible causes of activity and project delays. Detailed rules are derived for common activity scenarios and interactions on how to create the respective graphs. A real-world study demonstrates how the proposed method can be used to substantiate its potential value to practitioners in industry. The proposed approach is practical, and while it could be used for network schedules, it is especially useful for linear and repetitive schedules.

Get full access to this article

View all available purchase options and get full access to this article.

Data Availability Statement

All data generated or analyzed during the study are included in the published paper.

References

Alkass, S., M. Mazerolle, and F. Harris. 1996. “Construction delay analysis techniques.” Construct. Manage. Econ. 14 (5): 375–394. https://doi.org/10.1080/014461996373250.
Allen, J. F. 1983. “Maintaining knowledge about temporal intervals.” Commun. ACM 26 (11): 832–843. https://doi.org/10.1145/182.358434.
Al-Momani, A. H. 2000. “Construction delay: A quantitative analysis.” Int. J. Project Manage. 18 (1): 51–59. https://doi.org/10.1016/S0263-7863(98)00060-X.
Arditi, D., and T. Pattanakitchamroon. 2006. “Selecting a delay analysis method in resolving construction claims.” Int. J. Project Manage. 24 (2): 145–155. https://doi.org/10.1016/j.ijproman.2005.08.005.
Arditi, D., O. B. Tokdemir, and K. Suh. 2002. “Challenges in line-of-balance scheduling.” J. Constr. Eng. Manage. 128 (6): 545–556. https://doi.org/10.1061/(ASCE)0733-9364(2002)128:6(545).
Assaf, S. A., and S. Al-Hejji. 2006. “Causes of delay in large construction projects.” Int. J. Project Manage. 24 (4): 349–357. https://doi.org/10.1016/j.ijproman.2005.11.010.
Ballesteros-Pérez, P. 2017. “Modelling the boundaries of project fast-tracking.” Autom Constr. 84 (Sep): 231–241. https://doi.org/10.1016/j.autcon.2017.09.006.
Ballesteros-Pérez, P., M. C. González-Cruz, and A. Cañavate-Grimal. 2012a. “Mathematical relationships between scoring parameters in capped tendering.” Int. J. Project Manage. 30 (7): 850–862. https://doi.org/10.1016/j.ijproman.2012.01.008.
Ballesteros-Pérez, P., M. C. González-Cruz, M. Fernández-Diego, and E. Pellicer. 2014. “Estimating future bidding performance of competitor bidders in capped tenders.” J. Civ. Eng. Manage. 20 (5): 702–713. https://doi.org/10.3846/13923730.2014.914096.
Ballesteros-Pérez, P., M. C. González-Cruz, and J. P. Pastor-Ferrando. 2010. “Analysis of construction projects by means of value curves.” Int. J. Project Manage. 28 (7): 719–731. https://doi.org/10.1016/j.ijproman.2009.11.003.
Ballesteros-Pérez, P., M. C. González-Cruz, J. P. Pastor-Ferrando, and M. Fernández-Diego. 2012b. “The iso-score curve graph. A new tool for competitive bidding.” Autom. Constr. 22 (Apr): 481–490. https://doi.org/10.1016/j.autcon.2011.11.007.
Ballesteros-Pérez, P., E. Sanz-Ablanedo, R. Soetanto, M. C. González-Cruz, G. D. Larsen, and A. Cerezo-Narváez. 2020. “Duration and cost variability of construction activities: An empirical study.” J. Constr. Eng. Manage. 146 (1): 04019093. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001739.
Bataglin, F. S., D. D. Viana, R. V. Coelho, I. D. Tommelein, and C. T. Formoso. 2021. “Buffer types and methods of deployment in construction.” In Proc., 29th Annual Conf. of the Int. Group for Lean Construction, edited by L. F. Alarcon, and V. A. González, 849–858. Lima, Peru: International Group of Lean Construction. https://doi.org/10.24928/2021/0171.
Bubshait, A. A., and M. J. Cunningham. 1998. “Comparison of delay analysis methodologies.” J. Constr. Eng. Manage. 124 (4): 315–322. https://doi.org/10.1061/(ASCE)0733-9364(1998)124:4(315).
Chan, A. P. C., D. Scott, and A. P. L. Chan. 2004. “Factors affecting the success of a construction project.” J. Constr. Eng. Manage. 130 (1): 153–155. https://doi.org/10.1061/(ASCE)0733-9364(2004)130:1(153).
Finke, M. R. 1999. “Window analyses of compensable delays.” J. Constr. Eng. Manage. 125 (2): 96–100. https://doi.org/10.1061/(ASCE)0733-9364(1999)125:2(96).
Garcia, M. V. A. T. 2019. “A comparative analysis and evaluation of existing construction delay analysis methods based on critical path network.” Master’s thesis, Dept. of Civil and Environmental Engineering, Catholic Univ. of America.
González, V. A., L. F. Alarcón, and P. Gazmuri. 2006. “Design of work in process buffers in repetitive building projects: A case study.” In Proc., 14th Int. Conf. for Lean Construction. Santiago, Chile: International Group for Lean Construction.
Greenwood, D., K. Hogg, and S. Kan. 2005. “Subcontractors’ liability for project delay.” J. Finan. Manage. Prop. Constr. 10 (2): 107–114. https://doi.org/10.1108/13664380580001068.
Harris, R. B., and P. G. Ioannou. 1998. “Scheduling projects with repeating activities.” J. Constr. Eng. Manage. 124 (4): 269–278. https://doi.org/10.1061/(ASCE)0733-9364(1998)124:4(269).
Hegazy, T., K. Mostafa, and S. Ojulari. 2021. “Tetris-inspired approach for generating tightly-packed repetitive schedules.” Autom. Constr. 124 (Apr): 103601. https://doi.org/10.1016/j.autcon.2021.103601.
Johnston, D. W. 1981. “Linear scheduling method for highway construction.” J. Constr. Div. 107 (2): 247–261. https://doi.org/10.1061/JCCEAZ.0000960.
Kao, C.-K., and J.-B. Yang. 2009. “Comparison of windows-based delay analysis methods.” Int. J. Project Manage. 27 (4): 408–418. https://doi.org/10.1016/j.ijproman.2008.05.016.
Kikwasi, G. J. 2023. “Claims in construction projects: How causes are linked to effects?” J. Eng. Des. Tech. 21 (6): 1710–1724. https://doi.org/10.1108/JEDT-06-2021-0312.
Kim, Y., K. Kim, and D. Shin. 2005. “Delay analysis method using delay section.” J. Constr. Eng. Manage. 131 (11): 1155–1164. https://doi.org/10.1061/(ASCE)0733-9364(2005)131:11(1155).
Kraiem, Z. M., and J. E. Diekmann. 1987. “Concurrent delays in construction projects.” J. Constr. Eng. Manage. 113 (4): 591–602. https://doi.org/10.1061/(ASCE)0733-9364(1987)113:4(591).
Love, P. E. D., and H. Li. 2000. “Quantifying the causes and costs of rework in construction.” Construct. Manage. Econ. 18 (4): 479–490. https://doi.org/10.1080/01446190050024897.
Lucko, G. 2007. “Mathematical analysis of linear schedules.” In Proc., Construction Research Congress, edited by P. S. Chinowsky, A. D. Songer, P. M. Carrillo, and Freeport, Commonwealth of the Bahamas, 1387–1395. Reston, VA: ASCE.
Lucko, G. 2009. “Productivity scheduling method: Linear schedule analysis with singularity functions.” J. Constr. Eng. Manage.135 (4): 246–253. https://doi.org/10.1061/(ASCE)0733-9364(2009)135:4(246).
Lucko, G., and G. Gattei. 2016. “Line-of-balance against linear scheduling: Critical comparison.” Proc. Inst. Civ. Eng. Manage. Procurement Law 169 (1): 26–44. https://doi.org/10.1680/jmapl.15.00016.
Lucko, G., and A. A. Peña Orozco. 2009. “Float types in linear schedule analysis with singularity functions.” J. Constr. Eng. Manage. 135 (5): 368–377. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000007.
Majid, M. Z. A., and R. McCaffer. 1998. “Factors of non-excusable delays that influence contractors’ performance.” J. Manage. Eng. 14 (3): 42–49. https://doi.org/10.1061/(ASCE)0742-597X(1998)14:3(42).
Mostafa, K., S. Ojulari, and T. Hegazy. 2023. “Enhanced repetitive scheduling formulation for meeting deadlines and resource constraints in linear and scattered projects.” Can. J. Civ. Eng. 50 (3): 172–183. https://doi.org/10.1139/cjce-2022-0029.
Odeh, A. M., and H. T. Battaineh. 2001. “Causes of construction delay: Traditional contracts.” Int. J. Project Manage. 20 (1): 67–73. https://doi.org/10.1016/S0263-7863(00)00037-5.
Sanni-Anibire, M. O., R. Mohamad Zin, and S. O. Olatunji. 2022. “Causes of delay in the global construction industry: A meta analytical review.” Int. J. Constr. Manage. 22 (8): 1395–1407. https://doi.org/10.1080/15623599.2020.1716132.
Trauner, T. J., W. A. Manginelli, J. S. Lowe, M. F. Nagata, and B. J. Furniss. 2009. Construction delays: Understanding them clearly, analyzing them correctly. 2nd ed. Cambridge, MA: Butterworth-Heinemann/Elsevier.
Wickwire, J. M., T. J. Driscoll, S. B. Hurlbut, and M. J. Groff. 2009. Construction scheduling: Preparation, liability, and claims. 3rd ed. New York: Wolters Kluwer Law and Business.
Zika-Viktorsson, A., P. Sundström, and M. Engwall. 2006. “Project overload: An exploratory study of work and management in multi-project settings.” Int. J. Project Manage. 24 (5): 385–394. https://doi.org/10.1016/j.ijproman.2006.02.010.

Information & Authors

Information

Published In

Go to Journal of Construction Engineering and Management
Journal of Construction Engineering and Management
Volume 150Issue 8August 2024

History

Received: Dec 27, 2023
Accepted: Mar 8, 2024
Published online: Jun 4, 2024
Published in print: Aug 1, 2024
Discussion open until: Nov 4, 2024

Permissions

Request permissions for this article.

Authors

Affiliations

Karol Viviana Triana-Granados, A.M.ASCE https://orcid.org/0009-0000-0027-6769 [email protected]
Project Engineer, Bozzuto Construction, 6460 Ivy Lane, Suite 700, Greenbelt, MD 20770. ORCID: https://orcid.org/0009-0000-0027-6769. Email: [email protected]
Isabella Rose Bernard [email protected]
Undergraduate Dual-Degree Student, Dept. of Civil and Environmental Engineering, Catholic Univ. of America, Washington, DC 20064. Email: [email protected]
Alizée Merlin [email protected]
Construction Works Engineer, Ingénieur des Travaux de la Construction; formerly, International Exchange Student, Dept. of Civil and Environmental Engineering, Catholic Univ. of America, Washington, DC 20064. Email: [email protected]
Professor and Director, Construction Engineering and Management Program, Dept. of Civil and Environmental Engineering, Catholic Univ. of America, Washington, DC 20064. ORCID: https://orcid.org/0000-0002-7355-3365. Email: [email protected]
Professor, Dept. of Engineering Projects, Universitat Politècnica de València, València 46022, Spain (corresponding author). ORCID: https://orcid.org/0000-0002-4629-9664. Email: [email protected]

Metrics & Citations

Metrics

Citations

Download citation

If you have the appropriate software installed, you can download article citation data to the citation manager of your choice. Simply select your manager software from the list below and click Download.

View Options

Get Access

Access content

Please select your options to get access

Log in/Register Log in via your institution (Shibboleth)
ASCE Members: Please log in to see member pricing

Purchase

Save for later Information on ASCE Library Cards
ASCE Library Cards let you download journal articles, proceedings papers, and available book chapters across the entire ASCE Library platform. ASCE Library Cards remain active for 24 months or until all downloads are used. Note: This content will be debited as one download at time of checkout.

Terms of Use: ASCE Library Cards are for individual, personal use only. Reselling, republishing, or forwarding the materials to libraries or reading rooms is prohibited.
ASCE Library Card (5 downloads)
$105.00
Add to cart
ASCE Library Card (20 downloads)
$280.00
Add to cart
Buy Single Article
$35.00
Add to cart

Get Access

Access content

Please select your options to get access

Log in/Register Log in via your institution (Shibboleth)
ASCE Members: Please log in to see member pricing

Purchase

Save for later Information on ASCE Library Cards
ASCE Library Cards let you download journal articles, proceedings papers, and available book chapters across the entire ASCE Library platform. ASCE Library Cards remain active for 24 months or until all downloads are used. Note: This content will be debited as one download at time of checkout.

Terms of Use: ASCE Library Cards are for individual, personal use only. Reselling, republishing, or forwarding the materials to libraries or reading rooms is prohibited.
ASCE Library Card (5 downloads)
$105.00
Add to cart
ASCE Library Card (20 downloads)
$280.00
Add to cart
Buy Single Article
$35.00
Add to cart

Media

Figures

Other

Tables

Share

Share

Copy the content Link

Share with email

Email a colleague

Share