How to Foster Relational Behavior in Construction Projects: Direct and Mediating Effects of Contractual Complexity and Regulatory Focus

Publication: Journal of Construction Engineering and Management
Volume 150, Issue 4

Abstract

Maintaining the interorganizational relationship is a vital goal in the construction industry, and how to promote relational behavior in the project has received widespread attention. A contract is one of the commonly used control mechanisms in project management. Due to the contradictory conclusions of existing research, there is a lack of explicit guidance and detailed elaboration on how a contract impacts relational behavior. According to regulatory focus theory, this paper examines how different dimensions of contractual complexity affect motivation for different relational behaviors. This research decomposes contractual complexity as control, coordination, and adaptation from a functional perspective, classes regulatory focus into prevention focus and promotion focus and differentiates relational behavior as flexibility, information exchange, and solidarity. By conducting a questionnaire survey, the results reveal that the paths of three contractual functions on relational behavior and the mediating roles of prevention and promotion focus differ. Specifically, contractual control directly affects three dimensions of relational behavior, contractual coordination increases information exchange by triggering a prevention focus, and contractual adaptation enhances flexibility, information exchange, and solidarity by evoking a promotion focus and also directly enhances solidarity. These findings explain the motivation of behaviors in interorganizational relationships from the perspective of social psychology and offer new insights into how to cultivate relational behavior and the linkage between contractual and relational governance in construction projects.

Practical Applications

This study is helpful for construction practitioners in developing a nuanced understanding of interorganizational cooperation from the view of ex ante contract design and social psychology. Project managers need to allocate their resources properly, focus on different aspects of contract design and shape different regulatory focuses to foster specific relational behavior. First, drawing up a detailed contract is costly, and construction practitioners can choose what to focus on when resources and efforts are limited. On the premise that the contract is adequate to reduce the possibility of opportunism, practitioners should spend time and effort infusing flexibility into a contract by affording guidance on uncertain matters. Second, when executing a construction project, if contractual complexity has been established, it is also possible to promote relational behavior by adjusting the regulatory focus of the parties. Project managers should pay attention to the psychological state of both parties in the construction project, since situational triggers can evoke changes in the psychological state of the parties, which in turn affects the motivation for behavior.

Get full access to this article

View all available purchase options and get full access to this article.

Data Availability Statement

Some or all data or models that support the findings of this study are available from the corresponding author upon reasonable request.

Acknowledgments

This work was supported by the National Natural Science Foundation of China (Grant Nos. 72301024, 72001067, and 72031008) and the Talent Fund of Beijing Jiaotong University (Grant No. 2023XKRCW003). The authors would like to thank all the respondents who participated in the survey.

References

Argyres, N., and K. J. Mayer. 2007. “Contract design as a firm capability: An integration of learning and transaction cost perspectives.” Acad. Manage. Rev. 32 (4): 1060–1077. https://doi.org/10.5465/amr.2007.26585739.
Bai, X., S. Sheng, and J. J. Li. 2016. “Contract governance and buyer–supplier conflict: The moderating role of institutions.” J. Oper. Manage. 41 (1): 12–24. https://doi.org/10.1016/j.jom.2015.10.003.
Baker, R., J. M. Brick, N. A. Bates, M. Battaglia, M. P. Couper, J. A. Dever, K. J. Gile, and R. Tourangeau. 2013. “Summary report of the AAPOR task force on non-probability sampling.” J. Surv. Stat. Methodol. 1 (2): 90–143. https://doi.org/10.1093/jssam/smt008.
Barclay, D., R. Thompson, and C. Higgins. 1995. “The partial least squares (PLS) approach to causal modeling: Personal computer use as an illustration.” Technol. Stud. 2 (2): 285–309.
Beersma, B., A. Homan, G. van Kleef, and C. De Dreu. 2013. “Outcome interdependence shapes the effects of prevention focus, on team processes and performance.” Organ. Behav. Hum. Dec. Processes 121 (2): 194–203. https://doi.org/10.1016/j.obhdp.2013.02.003.
Carson, S. J., A. Madhok, and T. Wu. 2006. “Uncertainty, opportunism, and governance: The effects of volatility and ambiguity on formal and relational contracting.” Acad. Manage. J. 49 (5): 1058–1077. https://doi.org/10.5465/amj.2006.22798187.
Celly, K. S., and G. L. Frazier. 1996. “Outcome-based and behavior-based coordination efforts in channel relationships.” J. Market. Res. 33 (2): 200–210. https://doi.org/10.1177/002224379603300207.
Das, T. K., and R. Kumar. 2011. “Regulatory focus and opportunism in the alliance development process.” J. Manage. 37 (3): 682–708. https://doi.org/10.1177/0149206309356325.
Das, T. K., and B.-S. Teng. 2001. “Trust, control, and risk in strategic alliances: An integrated framework.” Organ. Stud. 22 (2): 251–283. https://doi.org/10.1177/0170840601222004.
Denicol, J., A. Davies, and I. Krystallis. 2020. “What are the causes and cures of poor megaproject performance? A systematic literature review and research agenda.” Project Manage. J. 51 (3): 328–345. https://doi.org/10.1177/8756972819896113.
Faems, D., M. Janssens, A. Madhok, and B. V. Looy. 2008. “Toward an integrative perspective on alliance governance: Connecting contract design, trust dynamics, and contract application.” Acad. Manage. J. 51 (6): 1053–1078. https://doi.org/10.5465/amj.2008.35732527.
Fehr, E., O. Hart, and C. Zehnder. 2011. “Contracts as reference points-experimental evidence.” Am. Econ. Rev. 101 (2): 493–525. https://doi.org/10.1257/aer.101.2.493.
Florack, A., J. Keller, and J. Palcu. 2013. “Regulatory focus in economic contexts.” J. Econ. Psychol. 38 (Aug): 127–137. https://doi.org/10.1016/j.joep.2013.06.001.
Gao, N., Y. Chen, W. Wang, and Y. Wang. 2018. “Addressing project complexity: The role of contractual functions.” J. Manage. Eng. 34 (3): 04018011. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000613.
Gardner, H. K., F. Gino, and B. R. Staats. 2012. “Dynamically integrating knowledge in teams: Transforming resources into performance.” Acad. Manage. J. 55 (4): 998–1022. https://doi.org/10.5465/amj.2010.0604.
Gross, J. J., and O. P. John. 2003. “Individual differences in two emotion regulation processes: Implications for affect, relationships, and well-being.” J. Personality Social Psychol. 85 (2): 348–362. https://doi.org/10.1037/0022-3514.85.2.348.
Guo, W., W. Lu, L. Hao, and X. Gao. 2023. “Interdependence and information exchange between conflicting parties: The role of interorganizational trust.” IEEE Trans. Eng. Manage. 70 (1): 156–172. https://doi.org/10.1109/TEM.2020.3047499.
Hair, J. F., J. J. Risher, M. Sarstedt, and C. M. Ringle. 2019. “When to use and how to report the results of PLS-SEM.” Eur. Bus. Rev. 31 (1): 2–24. https://doi.org/10.1108/EBR-11-2018-0203.
Hair, J. F., M. Sarstedt, C. M. Ringle, and J. A. Mena. 2011. “An assessment of the use of partial least squares structural equation modeling in marketing research.” J. Acad. Mark. Sci. 40 (3): 414–433. https://doi.org/10.1007/s11747-011-0261-6.
Haq, S. U., D. Gu, C. Liang, and I. Abdullah. 2019. “Project governance mechanisms and the performance of software development projects: Moderating role of requirements risk.” Int. J. Project Manage. 37 (4): 533–548. https://doi.org/10.1016/j.ijproman.2019.02.008.
Harmon, D. J., P. H. Kim, and K. J. Mayer. 2015. “Breaking the letter vs. spirit of the law: How the interpretation of contract violations affects trust and the management of relationships.” Strategic Manage. J. 36 (4): 497–517. https://doi.org/10.1002/smj.2231.
Heide, J. B., and G. John. 1992. “Do norms matter in marketing relationships?” J. Market. 56 (2): 32–44. https://doi.org/10.1177/002224299205600203.
Heide, J. B., K. H. Wathne, and A. I. Rokkan. 2007. “Interfirm monitoring, social contracts, and relationship outcomes.” J. Market. Res. 44 (3): 425–433. https://doi.org/10.1509/jmkr.44.3.425.
Higgins, E. T. 1998. “Promotion and prevention: Regulatory focus as a motivational principle.” In Vol. 30 of Advances in experimental social psychology, edited by M. P. Zanna, 1–46. Cambridge, MA: Academic Press. https://doi.org/10.1016/S0065-2601(08)60381-0.
Higgins, E. T., C. J. R. Roney, E. Crowe, and C. Hymes. 1994. “Ideal versus ought predilections for approach and avoidance distinct self-regulatory systems.” J. Personality Social Psychol. 66 (2): 276–286. https://doi.org/10.1037/0022-3514.66.2.276.
Ito, J. K., and R. B. Peterson. 1986. “Effects of task difficulty and interunit interdependence on information processing systems.” Acad. Manage. J. 29 (1): 139–149. https://doi.org/10.2307/255865.
Jap, S. D., and S. Ganesan. 2000. “Control mechanisms and the relationship life cycle: Implications for safeguarding specific investments and developing commitment.” J. Market. Res. 37 (2): 227–245. https://doi.org/10.1509/jmkr.37.2.227.18735.
Johnson, P. D., M. B. Smith, J. C. Wallace, A. D. Hill, and R. A. Baron. 2015. “A review of multilevel regulatory focus in organizations.” J. Manage. 41 (5): 1501–1529. https://doi.org/10.1177/0149206315575552.
Koolwijk, J., C. van Oel, and M. Bel. 2022. “The interplay between financial rules, trust and power in strategic partnerships in the construction industry.” Eng. Constr. Archit. Manage. 29 (3): 1089–1108. https://doi.org/10.1108/ECAM-09-2020-0713.
Lanaj, K., C.-H. Chang, and R. Johnson. 2012. “Regulatory focus and work-related outcomes: A review and meta-analysis.” Psychol. Bull. 138 (5): 998–1034. https://doi.org/10.1037/a0027723.
Lavelle, J. J., D. E. Rupp, and J. Brockner. 2007. “Taking a multifoci approach to the study of justice, social exchange, and citizenship behavior: The target similarity model.” J. Manage. 33 (6): 841–866. https://doi.org/10.1177/0149206307307635.
Lee, C.-Y., and H.-Y. Chong. 2021. “Influence of prior ties on trust and contract functions for BIM-enabled EPC megaproject performance.” J. Constr. Eng. Manage. 147 (7): 04021057. https://doi.org/10.1061/(ASCE)CO.1943-7862.0002076.
Li, B., A. Akintoye, P. J. Edwards, and C. Hardcastle. 2005. “Critical success factors for PPP/PFI projects in the UK construction industry.” Constr. Manage. Econ. 23 (5): 459–471. https://doi.org/10.1080/01446190500041537.
Ling-yee, L. 2010. “Encouraging extra-role behavior in a channel context: The role of economic-, social-, and justice-based sharedness mechanisms.” Ind. Mark. Manage. 39 (2): 195–201. https://doi.org/10.1016/j.indmarman.2008.12.011.
Lu, P., S. Guo, L. Qian, P. He, and X. Xu. 2015. “The effectiveness of contractual and relational governances in construction projects in China.” Int. J. Project Manage. 33 (1): 212–222. https://doi.org/10.1016/j.ijproman.2014.03.004.
Lu, W., and W. Guo. 2019. “The effect of task conflict on relationship quality: The mediating role of relational behavior.” Negotiation Conflict Manage. Res. 12 (4): 297–321. https://doi.org/10.1111/ncmr.12150.
Lu, W., W. Guo, and Q. Zhu. 2020. “Effect of justice on contractor’s relational behavior: Moderating role of owner’s asset specificity.” J. Constr. Eng. Manage. 146 (4): 04020020. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001795.
Lumineau, F., and J. E. Henderson. 2012. “The influence of relational experience and contractual governance on the negotiation strategy in buyer-supplier disputes.” J. Oper. Manage. 30 (5): 382–395. https://doi.org/10.1016/j.jom.2012.03.005.
Lumineau, F., and D. Malhotra. 2011. “Shadow of the contract: How contract structure shapes interfirm dispute resolution.” Strategic Manage. J. 32 (5): 532–555. https://doi.org/10.1002/smj.890.
Lusch, R. F., and J. R. Brown. 1996. “Interdependency, contracting, and relational behavior in marketing channels.” J. Mark. 60 (4): 19–38. https://doi.org/10.1177/002224299606000404.
Ma, L., and H. Fu. 2022. “A governance framework for the sustainable delivery of megaprojects: The interaction of megaproject citizenship behavior and contracts.” J. Constr. Eng. Manage. 148 (4): 04022004. https://doi.org/10.1061/(ASCE)CO.1943-7862.0002251.
Malhotra, D., and F. Lumineau. 2011. “Trust and collaboration in the aftermath of conflict: The effects of contract structure.” Acad. Manage. J. 54 (5): 981–998. https://doi.org/10.5465/amj.2009.0683.
Mayer, K. J., and N. S. Argyres. 2004. “Learning to contract: Evidence from the personal computer industry.” Organ. Sci. 15 (4): 394–410. https://doi.org/10.1287/orsc.1040.0074.
Mayer, K. J., Z. Xing, and P. Mondal. 2022. “Contracting for innovation: Designing contracts that account for exchange hazards and the need for innovation.” Strategic Manage. J. 43 (11): 2253–2278. https://doi.org/10.1002/smj.3409.
Mellewigt, T., C. Decker, and B. Eckhard. 2012. “What drives contract design in alliances? Taking stock and how to proceed.” Zeitschrift für Betriebswirtschaft 82 (7–8): 839–864. https://doi.org/10.1007/s11573-012-0591-y.
Mellewigt, T., A. Madhok, and A. Weibel. 2007. “Trust and formal contracts in interorganizational relationships—Substitutes and complements.” Managerial Decis. Econ. 28 (8): 833–847. https://doi.org/10.1002/mde.1321.
Molden, D., A. Lee, and E. Higgins. 2008. “Motivations for promotion and prevention.” In Handbook of motivation science, edited by J. Y. Shah and W. L. Gardner, 169–187. New York: Guilford Press.
Mooi, E. A., and M. Ghosh. 2010. “Contract specificity and its performance implications.” J. Mark. 74 (2): 105–120. https://doi.org/10.1509/jm.74.2.105.
Neubert, M. J., K. M. Kacmar, D. S. Carlson, L. B. Chonko, and J. A. Roberts. 2008. “Regulatory focus as a mediator of the influence of initiating structure and servant leadership on employee behavior.” J. Appl. Psychol. 93 (6): 1220–1233. https://doi.org/10.1037/a0012695.
Ning, Y., and F. Y. Y. Ling. 2013. “Reducing hindrances to adoption of relational behaviors in public construction projects.” J. Constr. Eng. Manage. 139 (11): 04013017. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000745.
Ning, Y., and F. Y. Y. Ling. 2015. “The effects of project characteristics on adopting relational transaction strategies.” Int. J. Project Manage. 33 (5): 998–1007. https://doi.org/10.1016/j.ijproman.2014.12.006.
Owens, B. P., and D. R. Hekman. 2016. “How does leader humility influence team performance? Exploring the mechanisms of contagion and collective promotion focus.” Acad. Manage. J. 59 (3): 1088–1111. https://doi.org/10.5465/amj.2013.0660.
Podsakoff, P. M., S. B. MacKenzie, J. Y. Lee, and N. P. Podsakoff. 2003. “Common method biases in behavioral research: A critical review of the literature and recommended remedies.” J. Appl. Psychol. 88 (5): 879–903. https://doi.org/10.1037/0021-9010.88.5.879.
Qian, Q., and L. Zhang. 2018. “Impact of regulatory focus on choice of project-governance modes: Role of tolerance of opportunistic behavior.” J. Constr. Eng. Manage. 144 (8): 04018070. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001526.
Quanji, Z., S. Zhang, and Y. Wang. 2017. “Contractual governance effects on cooperation in construction projects: Multifunctional approach.” J. Prof. Issues Eng. Educ. Pract. 143 (3): 04016025. https://doi.org/10.1061/(ASCE)EI.1943-5541.0000320.
Reuer, J. J., and A. Ariño. 2007. “Strategic alliance contracts: Dimensions and determinants of contractual complexity.” Strategic Manage. J. 28 (3): 313–330. https://doi.org/10.1002/smj.581.
Rietzschel, E. 2011. “Collective regulatory focus predicts specific aspects of team innovation.” Group Processes Intergroup Relat. 14 (3): 337–345. https://doi.org/10.1177/1368430210392396.
Sacramento, C., D. Fay, and M. West. 2013. “Workplace duties or opportunities? Challenge stressors, regulatory focus, and creativity.” Organ. Behav. Hum. Dec. Processes 121 (2): 141–157. https://doi.org/10.1016/j.obhdp.2013.01.008.
Schepker, D. J., W.-Y. Oh, A. Martynov, and L. Poppo. 2014. “The many futures of contracts: Moving beyond structure and safeguarding to coordination and adaptation.” J. Manage. 40 (1): 193–225. https://doi.org/10.1177/0149206313491289.
Schilke, O., and F. Lumineau. 2016. “The double-edged effect of contracts on alliance performance.” J. Manage. 44 (7): 2827–2858. https://doi.org/10.1177/0149206316655872.
Shin, Y., M. Kim, J. N. Choi, and S.-H. Lee. 2016. “Does team culture matter? Roles of team culture and collective regulatory focus in team task and creative performance.” Group Organ. Manage. 41 (2): 232–265. https://doi.org/10.1177/1059601115584998.
Stouthuysen, K., H. Slabbinck, and F. Roodhooft. 2012. “Controls, service type and perceived supplier performance in interfirm service exchanges.” J. Oper. Manage. 30 (5): 423–435. https://doi.org/10.1016/j.jom.2012.01.002.
Tangpong, C., K.-T. Hung, and Y. K. Ro. 2010. “The interaction effect of relational norms and agent cooperativeness on opportunism in buyer–supplier relationships.” J. Oper. Manage. 28 (5): 398–414. https://doi.org/10.1016/j.jom.2009.12.001.
Valerio, M. A., N. Rodriguez, P. Winkler, J. Lopez, M. Dennison, Y. Liang, and B. J. Turner. 2016. “Comparing two sampling methods to engage hard-to-reach communities in research priority setting.” BMC Med. Res. Method. 16 (1): 1–11. https://doi.org/10.1186/s12874-016-0242-z.
Wallace, J. C., P. D. Johnson, and M. L. Frazier. 2009. “An examination of the factorial, construct, and predictive validity and utility of the regulatory focus at work scale.” J. Organ. Behav.: Int. J. Ind. Occup. Organ. Psychol. Behav. 30 (6): 805–831. https://doi.org/10.1002/job.572.
Wang, D., Y. Wang, and Y. Lu. 2020. “Impact of regulatory focus on uncertainty in megaprojects: Mediating role of trust and control.” J. Constr. Eng. Manage. 146 (12): 04020142. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001951.
Wang, W., Y. Chen, S. Zhang, and Y. Wang. 2018. “Contractual complexity in construction projects: Conceptualization, operationalization, and validation.” Project Manage. J. 49 (3): 46–61. https://doi.org/10.1177/8756972818770589.
Weber, L., and C. W. Bauman. 2019. “The cognitive and behavioral impact of promotion and prevention contracts on trust in repeated exchanges.” Acad. Manage. J. 62 (2): 361–382. https://doi.org/10.5465/amj.2016.1230.
Weber, L., and K. J. Mayer. 2011. “Designing effective contracts: Exploring the influence of framing and expectations.” Acad. Manage. Rev. 36 (1): 53–75. https://doi.org/10.5465/amr.2008.0270.
Weber, L., K. J. Mayer, and J. T. Macher. 2011. “An analysis of extendibility and early termination provisions: The importance of framing duration safeguards.” Acad. Manage. J. 54 (1): 182–202. https://doi.org/10.5465/amj.2011.59215083.
Wu, A., Z. Wang, and S. Chen. 2017. “Impact of specific investments, governance mechanisms and behaviors on the performance of cooperative innovation projects.” Int. J. Project Manage. 35 (3): 504–515. https://doi.org/10.1016/j.ijproman.2016.12.005.
Yan, L., and L. Zhang. 2020. “Interplay of contractual governance and trust in improving construction project performance: Dynamic perspective.” J. Manage. Eng. 36 (4): 04020029. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000791.
Yang, F., X. Huang, and L. Wu. 2019. “Experiencing meaningfulness climate in teams: How spiritual leadership enhances team effectiveness when facing uncertain tasks.” Hum. Resour. Manage. 58 (2): 155–168. https://doi.org/10.1002/hrm.21943.
You, J., Y. Chen, Y. Hua, and W. Wang. 2019. “The efficacy of contractual governance on task and relationship conflict in inter-organisational transactions.” Int. J. Conflict Manage. 30 (1): 65–86. https://doi.org/10.1108/IJCMA-05-2018-0061.
You, J., Y. Chen, W. Wang, and C. Shi. 2018. “Uncertainty, opportunistic behavior, and governance in construction projects: The efficacy of contracts.” Int. J. Project Manage. 36 (5): 795–807. https://doi.org/10.1016/j.ijproman.2018.03.002.
Zhang, Q., K. Z. Zhou, Y. Wang, and H. Wei. 2017. “Untangling the safeguarding and coordinating functions of contracts: Direct and contingent value in China.” J. Bus. Res. 78 (Feb): 184–192. https://doi.org/10.1016/j.jbusres.2016.12.014.
Zhang, S., Y. Fu, and F. Kang. 2018. “How to foster contractors’ cooperative behavior in the Chinese construction industry: Direct and interaction effects of power and contract.” Int. J. Project Manage. 36 (7): 940–953. https://doi.org/10.1016/j.ijproman.2018.05.004.
Zhang, S. B., Y. F. Fu, Y. Gao, and X. D. Zheng. 2016. “Influence of trust and contract on dispute negotiation behavioral strategy in construction subcontracting.” J. Manage. Eng. 32 (4): 04016001. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000427.
Zhang, X., and X. Wang. 2020. “Team learning in interdisciplinary research teams: Antecedents and consequences.” J. Knowl. Manage. 25 (6): 1429–1455. https://doi.org/10.1108/JKM-07-2019-0372.
Zheng, X., J. Chen, Y. Han, L. Ren, and Q. Shi. 2021. “Unveiling complex relational behavior in megaprojects: A qualitative-quantitative network approach.” Int. J. Project Manage. 39 (7): 738–749. https://doi.org/10.1016/j.ijproman.2021.07.001.
Zheng, X., Y. Lu, and R. Chang. 2019. “Governing behavioral relationships in megaprojects: Examining effect of three governance mechanisms under project uncertainties.” J. Manage. Eng. 35 (5): 04019016. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000701.
Zheng, X., Y. Lu, Y. Le, Y. Li, and J. Fang. 2018. “Formation of interorganizational relational behavior in megaprojects: Perspective of the extended theory of planned behavior.” J. Manage. Eng. 34 (1): 04017052. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000560.

Information & Authors

Information

Published In

Go to Journal of Construction Engineering and Management
Journal of Construction Engineering and Management
Volume 150Issue 4April 2024

History

Received: Apr 19, 2023
Accepted: Nov 2, 2023
Published online: Jan 19, 2024
Published in print: Apr 1, 2024
Discussion open until: Jun 19, 2024

Permissions

Request permissions for this article.

ASCE Technical Topics:

Authors

Affiliations

Lecturer, School of Economics and Management, Beijing Jiaotong Univ., Beijing 100044, PR China. ORCID: https://orcid.org/0000-0002-8983-8920. Email: [email protected]
Professor, Dept. of Construction Management, College of Management and Economics, Tianjin Univ., Tianjin 300072, PR China. ORCID: https://orcid.org/0000-0003-2921-1189. Email: [email protected]
Associate Professor, School of Urban Economics and Management, Beijing Univ. of Civil Engineering and Architecture, Beijing 100044, PR China. ORCID: https://orcid.org/0000-0002-5129-2002. Email: [email protected]
Lecturer, School of Economics and Management, Hebei Univ. of Technology, Tianjin 300401, PR China (corresponding author). ORCID: https://orcid.org/0000-0002-8092-2632. Email: [email protected]

Metrics & Citations

Metrics

Citations

Download citation

If you have the appropriate software installed, you can download article citation data to the citation manager of your choice. Simply select your manager software from the list below and click Download.

View Options

Get Access

Access content

Please select your options to get access

Log in/Register Log in via your institution (Shibboleth)
ASCE Members: Please log in to see member pricing

Purchase

Save for later Information on ASCE Library Cards
ASCE Library Cards let you download journal articles, proceedings papers, and available book chapters across the entire ASCE Library platform. ASCE Library Cards remain active for 24 months or until all downloads are used. Note: This content will be debited as one download at time of checkout.

Terms of Use: ASCE Library Cards are for individual, personal use only. Reselling, republishing, or forwarding the materials to libraries or reading rooms is prohibited.
ASCE Library Card (5 downloads)
$105.00
Add to cart
ASCE Library Card (20 downloads)
$280.00
Add to cart
Buy Single Article
$35.00
Add to cart

Get Access

Access content

Please select your options to get access

Log in/Register Log in via your institution (Shibboleth)
ASCE Members: Please log in to see member pricing

Purchase

Save for later Information on ASCE Library Cards
ASCE Library Cards let you download journal articles, proceedings papers, and available book chapters across the entire ASCE Library platform. ASCE Library Cards remain active for 24 months or until all downloads are used. Note: This content will be debited as one download at time of checkout.

Terms of Use: ASCE Library Cards are for individual, personal use only. Reselling, republishing, or forwarding the materials to libraries or reading rooms is prohibited.
ASCE Library Card (5 downloads)
$105.00
Add to cart
ASCE Library Card (20 downloads)
$280.00
Add to cart
Buy Single Article
$35.00
Add to cart

Media

Figures

Other

Tables

Share

Share

Copy the content Link

Share with email

Email a colleague

Share