Repetitive Scheduling Method: Requirements, Modeling, and Implementation
Publication: Journal of Construction Engineering and Management
Volume 142, Issue 5
Abstract
Projects with repeating activities, such as multistory buildings and highways, present unique scheduling challenges. This paper presents the necessary requirements that scheduling systems should address to meet the needs and complexities of repetitive projects in practice. The repetitive scheduling method (RSM) provides a unified scheduling framework that applies to all types of repetitive projects. In RSM, projects are classified as discrete (vertical) or continuous (horizontal or linear) and then as uniform and nonuniform, depending on whether progress is measured using a counting scale or a dominant-attribute scale. RSM modeling elements include three types of activities (line, block, and bar) and 10 types of relationships (links) between activities. , a computer program developed by the authors to validate the proposed scheduling approach, is used to develop the production diagrams and tabular reports of the target schedule for a complex of four-story apartment buildings for a low-income housing project. Sufficient detail is provided so that the project and its target schedule can be used to validate future research and to verify other systems.
Get full access to this article
View all available purchase options and get full access to this article.
Acknowledgments
The various plans and schedules for the construction of the four-story apartment building complex presented in this paper were developed in cooperation with Mr. Luis Riquezes, the project manager for the work, whose contributions are gratefully acknowledged.
References
Adeli, H., and Karim, A. (1997). “Scheduling/cost optimization and neural dynamics model for construction.” J. Constr. Eng. Manage., 450–458.
Arditi, D., and Albulak, M. Z. (1986). “Line-of-balance scheduling in pavement construction.” J. Constr. Eng. Manage., 411–424.
Ballard, G., and Tommelein, I. D. (1999). “Aiming for continuous flow.” Lean Construction Institute, Arlington, VA.
Barrie, D. S., and Paulson, B. C. (1984). Professional construction management, McGraw-Hill, New York.
Birrell, G. S. (1980). “Construction planning—Beyond critical path.” J. Constr. Div., 106(3), 389–407.
Carr, R. I., and Meyer, W. L. (1974). “Planning construction of repetitive building units.” J. Constr. Div., 100(3), 403–412.
Chrzanowski, E. N., and Johnston, D. W. (1986). “Application of linear scheduling.” J. Constr. Eng. Manage., 476–491.
Clough, R. H., Sears, G. A., and Sears, S. K. (2000). Construction project management, 4th Ed. Wiley, New York.
Dressler, J. (1980). “Construction management in West Germany.” J. Constr. Div., 106(4), 477–487.
Gorman, J. E. (1972). “How to get visual impact on planning diagram.” Roads Streets, 115(8), 74–75.
Harris, R. B. (1978). Precedence and arrow networking techniques for construction, Wiley, New York.
Harris, R. B., and Ioannou, P. G. (1998a). “Scheduling projects with repeating activities.” J. Constr. Eng. Manage., 269–278.
Harris, R. B., and Ioannou, P. G. (1998b). “Scheduling projects with repetitive activities.”, Dept. of Civil and Environmental Engineering, Univ. of Michigan, Ann Arbor, MI.
Ioannou, P. G., and Harris, R. B. (2003). “Discussion of ‘Algorithm for determining controlling path considering resource continuity’ by Mohammed A. Ammar and Emad Elbeltagi.” J. Comput. Civ. Eng., 17, 68–70.
Ioannou, P. G., and Srisuwanrat, C. (2006). “Sequence step algorithm for continuous resource utilization in probabilistic repetitive projects.” Proc., Winter Simulation Conf., IEEE, Piscataway, NJ, 1731–1740.
Ioannou, P. G., and Srisuwanrat, C. (2007a). “Optimal scheduling of probabilistic repetitive projects using completed unit and genetic algorithms.” Proc., Winter Simulation Conf., IEEE, Piscataway, NJ, 2151–2158.
Ioannou, P. G., and Srisuwanrat, C. (2007b). “Probabilistic scheduling for repetitive projects.” Proc., 15th Conf. of the Int. Group for Lean Construction, Lansing, MI.
Ioannou, P. G., and Yang, I. T. (2003). “Discussion of ‘Algorithm for determining controlling path considering resource continuity’ by Mohammed A. Ammar and Emad Elbeltagi.” J. Comput. Civ. Eng., 17, 68–70.
Ioannou, P. G., and Yang, I. T. (2004). “Discussion of ‘Comparison of linear scheduling model and repetitive scheduling method’ by Kris G. Mattila and Amy Park.” J. Constr. Eng. Manage., 461–463.
Johnston, D. W. (1981). “Linear scheduling method for highway construction.” J. Constr. Div., 107(2), 247–261.
Kenley, R., and Seppänen, O. (2009). “Location-based management of construction projects: Part of a new typology for project scheduling methodologies.” Proc., Winter Simulation Conf., IEEE, Piscataway, NJ, 2563–2570.
Lumsden, P. (1968). The line-of-balance method, Pergamon Press, London.
Lutz, J. D. (1990). “Planning of linear construction projects using simulation and line of balance.” Ph.D. dissertation, Dept. of Civil Engineering, Purdue Univ., West Lafayette, IN.
Mattila, K. G., and Abraham, D. M. (1998). “Resource leveling of linear schedules using integer linear programming.” J. Constr. Eng. Manage., 232–244.
O’Brien, J. J. (1975). “VPM scheduling for high-rise buildings.” J. Constr. Div., 101(4), 895–905.
Peer, S. (1974). “Network analysis and construction planning.” J. Constr. Div., 100(3), 203–210.
Perera, S. (1980). “Planning of housing construction using control charts.” Hous. Sci., 4(5), 447–458.
Riley, D., and Savindo, V. (1997). “Space planning for mechanical, electrical, plumbing, and fire protection trades in multi-story buildings construction.” Proc., Construction Congress, ASCE, New York, 102–109.
Rowings, J. E., and Rahbar, F. F. (1992). Use of linear scheduling in transportation projects, National Research Council, Washington, DC.
Russell, A. D., and Wong, W. C. M. (1993). “New generation of planning structures.” J. Constr. Eng. Manage., 196–214.
Sarraj, Z. M. (1990). “Formal development of line-of-balance technique.” J. Constr. Eng. Manage., 689–704.
Serpell, A., Venturi, A., and Contreras, J. (1995). “Characterization of waste in building construction projects.” Proc., 3rd Annual Conf. of the Int. Group for Lean Construction, IGLC III, Albuquerque, NM.
Stradal, O., and Cacha, J. (1982). “Time space scheduling method.” J. Constr. Div., 108(3), 445–457.
Suhail, S. A., and Neale, R. H. (1994). “CPM/LOB: New methodology to integrate CPM and line of balance.” J. Constr. Eng. Manage., 667–684.
Thabet, W. Y., and Beliveau, Y. J. (1994). “HVLS: Horizontal and vertical logic scheduling for multistory projects.” J. Constr. Eng. Manage., 875–892.
Tommelein, I. D. (1998). “Pull-driven scheduling for pipe-spool installation: Simulation of lean construction technique.” J. Constr. Eng. Manage., 279–288.
Vorster, M. C., Beliveau, Y. J., and Bafna, T. (1992). “Linear scheduling and visualization.” Transp. Res. Rec., 1351, 32–39.
Whiteman, W. E., and Irwig, H. G. (1988). “Disturbance scheduling technique for managing renovation work.” J. Constr. Eng. Manage., 191–213.
Information & Authors
Information
Published In
Copyright
© 2016 American Society of Civil Engineers.
History
Received: Jun 22, 2015
Accepted: Oct 14, 2015
Published online: Jan 5, 2016
Published in print: May 1, 2016
Discussion open until: Jun 5, 2016
Authors
Metrics & Citations
Metrics
Citations
Download citation
If you have the appropriate software installed, you can download article citation data to the citation manager of your choice. Simply select your manager software from the list below and click Download.