Estimation of Cost Contingency for Air Force Construction Projects

Publication: Journal of Construction Engineering and Management
Volume 136, Issue 11

Abstract

Risk and associated cost overruns are critical problems for construction projects, yet the most common practice for dealing with them is the assignment of an arbitrary flat percentage of the construction budget as a contingency fund. Therefore, our goal was to identify significant variables that may influence, or serve as indicators of, potential cost overruns. We analyzed data from 203 Air Force construction projects over a full range of project types and scopes using multiple linear regression to develop a model to predict the amount of required contingency funds. The proposed model uses only data that would be available prior to the award of a construction contract. The variables in the model were categorized as project characteristics, design performance metrics, and contract award process influences. Based on the performance metric used, the model captures 44% of actual cost overruns versus the 20% captured by the current practice. Furthermore, application of the model reduces the average contingency budgeting error from 11.2 to only 0.3%.

Get full access to this article

View all available purchase options and get full access to this article.

References

AACE International. (2007). “Cost engineering terminology.” Recommended practice 10S-90, Morgantown, W.Va.
Baccarini, D. (2004). “Accuracy in estimating project cost construction contingency—A statistical analysis.” Proc., Construction and Building Research Conf. of RICS, RICS, Leeds, U.K.
Burroughs, S. E., and Juntima, G. (2004). “Exploring techniques for contingency setting.” AACE Int. Trans., Proc., 44th AACE Int. Meeting, Washington, D.C., EST.3.1–EST.3.6.
Chen, D., and Hartman, F. T. (2000). “A neural network approach to risk assessment and contingency allocation.” AACE Int. Trans., Proc., 48th AACE Int. Meeting, Calgary, Canada, RI.7.1–RI.7.6.
Clark, D. E. (2001). “Monte Carlo analysis: Ten years of experience.” Coast. Eng., 43(6), 40–45.
Diekmann, J. E., Sewester, E. E., and Taher, K. (1988). “Risk management in capital projects.” Rep. No. 41, Construction Industry Institute, Univ. of Texas at Austin, Austin, Tex.
Federle, M. O., and Pigneri, S. C. (1993). “Predictive model of cost overruns.” AACE Int. Trans., Proc., 37th AACE Int. Meeting, Dearborn, Mich., L.7.1–L.7.9.
Flyvbjerg, B., Holm, M. K. S., and Buhl, S. L. (2004). “How common and how large are cost overruns in transport infrastructure projects?” Transport Rev., 23(1), 71–88.
Flyvbjerg, B., Holm, M. S., and Buhl, S. (2002). “Underestimating cost in public works projects: Error or lie?” J. Am. Plan. Assn., 68(3), 279–295.
Ford, D. N. (2002). “Achieving multiple project objectives through contingency management.” J. Constr. Eng. Manage., 128(1), 30–39.
Giegerich, D. B. (2002). “Early warning signs of troubled projects.” AACE Int. Trans., Proc., 46th AACE Int. Meeting, Portland, Ore., CDR.2.1–CDR.2.8.
Harbuck, R. H. (2004). “Competitive bidding for highway construction projects.” AACE Int. Trans., Proc., 48th AACE Int. Meeting, Washington, D.C., ES.9.1–ES.9.4.
Hollmann, J. K. (2007). “The Monte-Carlo challenge: A better approach.” AACE Int. Trans., Proc., 51st AACE Int. Meeting, Nashville, Tenn., RI.3.1–RI.3.7.
Jahren, C. T., and Ashe, A. M. (1990). “Predictors of cost-overrun rates.” J. Constr. Eng. Manage., 116(3), 548–552.
Kuprenas, J. A., and Nasr, E. B. (2003). “Controlling design-phase scope creep.” AACE Int. Trans., Proc., 47th AACE Int. Meeting, Orlando, Fla., CS.1.1–CS.1.5.
Mak, S., and Picken, D. (2000). “Using risk analysis to determine construction project contingencies.” J. Constr. Eng. Manage., 126(2), 130–136.
McClave, J., et al. (2005). Statistics for business and economics, 9th Ed., Pearson Prentice-Hall, Upper Saddle River, N.J.
Morris, M. R. (1990). “Improving the accuracy of early cost-estimates for federal construction projects.” Rep. Prepared for Building Research Board, National Research Council, Washington, D.C.
Patrascu, A. (1988). Construction cost engineering handbook, Marcel Dekker, New York.
Robbins, E. O. (2003). “FY03 MILCON dirtkicker award criteria.” Memorandum for all MAJCOM/CE., HQ USAF/ILE, Washington, D.C.
Smith, G. R., and Bohn, C. M. (1999). “Small to medium contractor contingency and assumption of risk.” J. Constr. Eng. Manage., 125(2), 101–108.
Sonmez, R., Ergin, A., and Birgonul, M. T. (2007). “Quantitative methodology for determination of cost contingency in international projects.” J. Manage. Eng., 23(1), 35–39.
Thompson, A., and Perry, J. G. (1992). Engineering construction risks: A guide to project risk analysis and risk management, Thomas Telford, London.
Touran, A. (2003). “Calculation of contingency in construction projects.” IEEE Trans. Eng. Manage., 50(2), 135–140.
Trost, S. M., and Oberlender, G. D. (2003). “Predicting accuracy of early cost estimates using factor analysis and multivariate regression.” J. Constr. Eng. Manage., 129(2), 198–204.
Zentner, R. (1996). “Accurate estimates start with clear pictures.” AACE Int. Trans., Proc., 40th AACE Int. Meeting, Vancouver, Canada, CS.10.1–CS.10.6.

Information & Authors

Information

Published In

Go to Journal of Construction Engineering and Management
Journal of Construction Engineering and Management
Volume 136Issue 11November 2010
Pages: 1181 - 1188

History

Received: May 7, 2009
Accepted: Apr 22, 2010
Published online: Oct 15, 2010
Published in print: Nov 2010

Permissions

Request permissions for this article.

Authors

Affiliations

Alfred E. Thal Jr.
Assistant Professor, Dept. of Systems and Engineering Management, Air Force Institute of Technology, AFIT/ENV Bldg. 640, Wright-Patterson AFB, OH 45433-7765 (corresponding author).
Jason J. Cook
Chief, Environmental Branch, 721 MSG/CEV, 1 NORAD Rd., Suite 12104, Colorado Springs, CO 80914.
Edward D. White III
Associate Professor, Dept. of Mathematics and Statistics, Air Force Institute of Technology, AFIT/ENC Bldg. 641, Wright-Patterson AFB, OH 45433-7765.

Metrics & Citations

Metrics

Citations

Download citation

If you have the appropriate software installed, you can download article citation data to the citation manager of your choice. Simply select your manager software from the list below and click Download.

Cited by

View Options

Get Access

Access content

Please select your options to get access

Log in/Register Log in via your institution (Shibboleth)
ASCE Members: Please log in to see member pricing

Purchase

Save for later Information on ASCE Library Cards
ASCE Library Cards let you download journal articles, proceedings papers, and available book chapters across the entire ASCE Library platform. ASCE Library Cards remain active for 24 months or until all downloads are used. Note: This content will be debited as one download at time of checkout.

Terms of Use: ASCE Library Cards are for individual, personal use only. Reselling, republishing, or forwarding the materials to libraries or reading rooms is prohibited.
ASCE Library Card (5 downloads)
$105.00
Add to cart
ASCE Library Card (20 downloads)
$280.00
Add to cart
Buy Single Article
$35.00
Add to cart

Get Access

Access content

Please select your options to get access

Log in/Register Log in via your institution (Shibboleth)
ASCE Members: Please log in to see member pricing

Purchase

Save for later Information on ASCE Library Cards
ASCE Library Cards let you download journal articles, proceedings papers, and available book chapters across the entire ASCE Library platform. ASCE Library Cards remain active for 24 months or until all downloads are used. Note: This content will be debited as one download at time of checkout.

Terms of Use: ASCE Library Cards are for individual, personal use only. Reselling, republishing, or forwarding the materials to libraries or reading rooms is prohibited.
ASCE Library Card (5 downloads)
$105.00
Add to cart
ASCE Library Card (20 downloads)
$280.00
Add to cart
Buy Single Article
$35.00
Add to cart

Media

Figures

Other

Tables

Share

Share

Copy the content Link

Share with email

Email a colleague

Share