Isolated Collapsed But-For Delay Analysis Methodology
Publication: Journal of Construction Engineering and Management
Volume 135, Issue 7
Abstract
Schedule delays are common in construction projects. Although many methods have been developed for analyzing and measuring schedule delays for construction projects, each method has functional limitations and use prerequisites. No one method is acceptable for all project participants under all circumstances. This study presents the isolated collapsed but-for (ICBF) method, an innovative delay analysis method for construction projects. During analysis, the ICBF method requires as-planned and as-built schedules as well as identified liability documents with key delay events to perform its analysis approach. Based on its application to an illustrative case and comparisons with other methods, the ICBF method is effective for delay analysis. Results provided by the proposed method can be easily traced to the actual case in an as-built schedule.
Get full access to this article
View all available purchase options and get full access to this article.
Acknowledgments
The writers would like to thank the National Science Council, Taiwan, ROC, for financially supporting this research under Contract Nos. NSC95-2221-E-216-048 and NSC96-2221-E-216-027-MY2. The writers are also thankful to the reviewers for their valuable suggestions and comments.
References
Alkass, S., Mazerolle, M., Tribaldos, E., and Harris, F. (1995). “Computer aided construction delay analysis and claims preparation.” Constr. Manage. Econom., 13(4), 335–352.
Alkass, S., Mazerolle, M., Tribaldos, E., and Harris, F. (1996). “Construction delay analysis techniques.” Constr. Manage. Econom., 14(5), 375–394.
Arditi, D., and Pattanakitchamroon, T. (2006). “Selecting a delay analysis method in resolving construction claims.” Int. J. Proj. Manage., 24(2), 145–155.
Bordoli, D. W., and Baldwin, A. N. (1998). “A methodology for assessing construction project delays.” Constr. Manage. Econom., 16(3), 327–337.
Bubshait, A. A., and Cunningham, M. J. (1998). “Comparison of delay analysis methodologies.” J. Constr. Eng. Manage., 124(4), 315–322.
Elnagar, H., and Yates, J. K. (1997). “Construction documentation used as indicators of delays.” Cost Eng., 39(8), 31–37.
Gothand, K. D. (2003). “Schedule delay analysis: modified windows approach.” Cost Eng., 45(9), 18–23.
Hegazy, T. M., and Zhang, K. (2005). “Daily windows delay analysis.” J. Constr. Eng. Manage., 131(5), 505–512.
Kraiem, Z., and Diekmann, J. (1987). “Concurrent delays in construction projects.” J. Constr. Eng. Manage., 113(4), 591–602.
Mbabazi, A., Hegazy, T., and Saccomanno, F. (2005). “Modified but-for method for delay analysis.” J. Constr. Eng. Manage., 131(10), 1142–1144.
Mohan, S. B., and Al-Gahtani, K. S. (2006). “Current delay analysis techniques and improvement.” Cost Eng., 48(9), 12–21.
Ng, S. T., Skitmore, M., Deng, M. Z. M., and Nadeem, A. (2004). “Improving existing delay analysis techniques for the establishment of delay liabilities.” Constr. Innovation, 4(1), 3–17.
Sgarlata, M. A., and Brasco, C. J. (2004). “Successful claims resolution through an understanding of the law governing allocation of risk for delay and disruption.” CM ejournal, CMAA, ⟨http://cmaanet.org/ejournal.php⟩ (Dec. 12, 2007).
Yang, J. B. (2005). “Comparison of delay analysis software for construction projects.” Proc., 33rd Annual Canadian Society for Civil Engineering (CSCE) Conf., Toronto, Canada, CT-115-1–9.
Yang, J. B., and Kao, C. K. (2007). “A knowledge map for delay analysis development.” Proc., Fourth International Conference on Construction in the 21st Century, Gold Coast, Australia.
Yang, J. B., and Kao, C. K. (2009). “Review of delay analysis methodologies: A process-based comparison.” The Open Construction & Building Technology Journal (under review).
Yang, J. B., Kao, C. K., and Lee, Y. Y. (2006). “System requirement analysis of a construction delay analysis system.” Proc., 23rd International Symp. on Automation and Robotics in Construction, Tokyo, 102–106.
Zack, J. G. (2001). “But-for schedules—Analysis and defense.” Cost Eng., 43(8), 13–17.
Information & Authors
Information
Published In
Copyright
© 2009 ASCE.
History
Received: Feb 6, 2008
Accepted: Oct 15, 2008
Published online: Mar 27, 2009
Published in print: Jul 2009
Authors
Metrics & Citations
Metrics
Citations
Download citation
If you have the appropriate software installed, you can download article citation data to the citation manager of your choice. Simply select your manager software from the list below and click Download.