Accuracy of Highway Contractor’s Schedules

Publication: Journal of Construction Engineering and Management
Volume 130, Issue 5

Abstract

Contractors are required by the Michigan Department of Transportation (MDOT) to submit a progress schedule identifying the controlling path of activities for a construction project. During the 2000 construction season, MDOT allowed contractors to submit a progress schedule with overlapping or concurrent controlling operations. Prior to this, only one activity at a time could be controlling on the progress schedule. This paper reports on the results of a research project where the focus was to examine the accuracy of the progress schedules, which only list controlling items. Eight construction projects were studied and a determination of progress schedule accuracy was made. This was done to determine if there was an increase in accuracy of the schedules when concurrent controlling operations were used. Included in the eight projects were four without concurrent controlling activities and four with concurrent controlling activities. A comparison based upon similar projects with and without concurrent activities was made. Additionally, 22 projects were analyzed, all without concurrent controlling activities, to determine the accuracy of progress schedules for two types of projects. The comparison revealed that, in three of the four cases, the accuracy of progress schedules increased with the allowance of concurrent controlling activities. The 22 projects revealed that the accuracy of progress schedules varied considerably. It was also determined that contractors overestimated the duration of activities included in progress schedules.

Get full access to this article

View all available purchase options and get full access to this article.

References

1.
Arditi, D., and Robinson, M. A. (1995). “Concurrent delays in construction litigation.” Cost Eng., 37(7), 20–30.
2.
Bartholomew, S.H. ( 1998). Construction contracting: Business and legal principles, Prentice–Hall, Englewood Cliffs, N.J.
3.
Dobie, Gerald., MDOT Engineer of Construction Retired. Interview Letter to the Author. 10 October 2001.
4.
Federal Highway Administration (FHWA). (1996). “Standard specification for road and bridge construction on federal highway projects.” FP-96, U.S. Department of Transportation, Washington, D.C.
5.
Goldratt, E.M. ( 1997). Critical chain, North River Press, Great Barrington, Mass.
6.
Kallo, G. G. (1996). “The reliability of critical path method (CPM) techniques in the analysis and evaluation of delay claims.” Cost Eng., 38(5), 35–37.
7.
Knoke, J. R., and Jentzen, G. H. (1994). “Facilitate delay analysis technique.” Trans. Am. Assn. Cost. Eng..
8.
Kraiem, Z. I., and Diekmann, J. E. (1987). “Concurrent delays in construction projects.” J. Constr. Eng. Manage., 113(4), 591–602.
9.
MDOT/MRBA/AUC/progress schedule summit. (1999). C&T Training Center, Michigan Dept. of Transportation, Lansing, Mich.
10.
Michigan Department of Transportation 1996 standard specification for construction. (1996). Michigan Dept. of Transportation, Lansing, Mich.
11.
Michigan Dept. of Transportation. (1999). “Special provision for progress schedule.” FUSP102 (G), Lansing, Mich.
12.
Michigan Dept. of Transportation. (2001). “Special Provision of proposal submission, award, and execution of contract.” FUSP102 (I), Lansing, Mich.
13.
Nunnally, S.W. ( 1998). Construction methods and management, 4th Ed., Prentice-Hall, Englewood Cliffs, N.J.
14.
Shi, J. J., Cheung, S. O., and Arditi, D. (2001). “Construction delay computation method.” J. Constr. Eng. Manage. 127(1), 60–65.
15.
Trauner, T.J. ( 1990). Construction delays, R. S. Means, Kingston, Mass.
16.
Yates, J. K. (1993). “Construction decision support system for delay analysis.” J. Constr. Eng. Manage., 119(2), 226–244.

Information & Authors

Information

Published In

Go to Journal of Construction Engineering and Management
Journal of Construction Engineering and Management
Volume 130Issue 5October 2004
Pages: 647 - 655

History

Published online: Oct 1, 2004
Published in print: Oct 2004

Permissions

Request permissions for this article.

Authors

Affiliations

Kris G. Mattila, P.E., A.M.ASCE
Associate Professor, Dept. of Civil and Environmental Engineering, Michigan Technological Univ., Houghton, MI 49931. E-mail: [email protected]
Michael R. Bowman
Project Engineer, The Christman Company, Petoskey, MI 49770. E-mail: [email protected]

Metrics & Citations

Metrics

Citations

Download citation

If you have the appropriate software installed, you can download article citation data to the citation manager of your choice. Simply select your manager software from the list below and click Download.

Cited by

View Options

Get Access

Access content

Please select your options to get access

Log in/Register Log in via your institution (Shibboleth)
ASCE Members: Please log in to see member pricing

Purchase

Save for later Information on ASCE Library Cards
ASCE Library Cards let you download journal articles, proceedings papers, and available book chapters across the entire ASCE Library platform. ASCE Library Cards remain active for 24 months or until all downloads are used. Note: This content will be debited as one download at time of checkout.

Terms of Use: ASCE Library Cards are for individual, personal use only. Reselling, republishing, or forwarding the materials to libraries or reading rooms is prohibited.
ASCE Library Card (5 downloads)
$105.00
Add to cart
ASCE Library Card (20 downloads)
$280.00
Add to cart
Buy Single Article
$35.00
Add to cart

Get Access

Access content

Please select your options to get access

Log in/Register Log in via your institution (Shibboleth)
ASCE Members: Please log in to see member pricing

Purchase

Save for later Information on ASCE Library Cards
ASCE Library Cards let you download journal articles, proceedings papers, and available book chapters across the entire ASCE Library platform. ASCE Library Cards remain active for 24 months or until all downloads are used. Note: This content will be debited as one download at time of checkout.

Terms of Use: ASCE Library Cards are for individual, personal use only. Reselling, republishing, or forwarding the materials to libraries or reading rooms is prohibited.
ASCE Library Card (5 downloads)
$105.00
Add to cart
ASCE Library Card (20 downloads)
$280.00
Add to cart
Buy Single Article
$35.00
Add to cart

Media

Figures

Other

Tables

Share

Share

Copy the content Link

Share with email

Email a colleague

Share