Probabilistic Monitoring of Project Performance Using SS-Curves

Publication: Journal of Construction Engineering and Management
Volume 126, Issue 2

Abstract

The purpose of this study was to develop a new concept of project control. This new concept uses stochastic S-curves (SS-Curves) as an alternative to using the deterministic S-curve technique commonly employed in professional practice. SS-curves are developed by determining the activity level variability in cost and duration. Simulation is the recommended approach for obtaining SS-curves, similar to the way that stochastic schedules are currently developed. SS-curves provide probability distributions for expected cost and duration for a given percentage of work completed. Monitoring project performance is performed by comparing the most likely budget and duration values, obtained from respective probability distributions for actual progress, with the project's actual data and cumulative cost. By using this method, an evaluation of actual project performance can be developed that appropriately considers the natural variability of construction costs and duration, rather than utilizing only one possible deterministic outcome. Given the probabilistic characteristics of SS-curves, additional benefits are presented that enable a more comprehensive project control methodology.

Get full access to this article

View all available purchase options and get full access to this article.

References

1.
Bent, J., and Humphreys, K. (1996). Effective project management through applied cost and schedule control. Marcel Dekker, New York.
2.
Crandall, K. C. (1976). “Probabilistic time scheduling.”J. Constr. Div., ASCE, 102(3), 415–423.
3.
Crandall, K. C. (1977). “Analysis of schedule simulations.”J. Constr. Div., ASCE, 103(3), 387–394.
4.
Crandall, K. C., and Woolery, J. C. (1982). “Schedule development under stochastic scheduling.”J. Constr. Div., ASCE, 108(2), 321–329.
5.
Diekmann, J. E. (1983). “Probabilistic estimating: mathematics and applications.”J. Constr. Engrg. and Mgmt., ASCE, 109(3), 297–308.
6.
Monte Carlo;ot Version 2.0. (1993). Primavera Systems, Inc., Bala Cynwyd, Pa.
7.
Neil, J. N. (1986). “Project control for engineering.” Publication No. 6-1, Construction Industry Institute, Austin, Tex.
8.
Neil, J. N. (1987). “Project control for construction.” Publication No. 6-5, Construction Industry Institute, Austin, Tex.
9.
Oberlander, G. D. (1993). Project management for engineering and construction. McGraw-Hill, New York.
10.
Pritsker, A. A. B., and Sigal, C. E. (1983). Management decision making: a network simulation approach. Prentice-Hall, Englewood Cliffs, N.J.
11.
Pultar, M. (1990). “Progress-based construction scheduling.”J. Constr. Engrg. and Mgmt., ASCE, 116(4), 670–688.
12.
Rao, G. N., and Grobler, F. (1995). “Integrated analysis of cost risk and schedule risk.” Proc., Comp. in Civ. Engrg., ASCE, New York, 1404–1411.
13.
@RISK for Project;ot. (1993). Palisade, Inc., Newfield, N.Y.
14.
Senior, B. A. (1995). “Simulation and critical path method software connectivity.” Proc., Comp. in Civ. Engrg., ASCE, New York, 1412–1419.
15.
Sha′ath, K. K., and Singh, G. (1994). “A PC-based stochastic project scheduling and costing module.” Proc., Comp. in Civ. Engrg., ASCE, New York, 9–16.
16.
Singh, A. (1991). “Developing and implementing C-SCSC.”J. Profl. Issues in Engrg. Educ. and Pract., ASCE, 117(3), 295–308.
17.
Stevens, W. M. (1983). “Cost control: integrated cost/schedule performance.” Proc., Improving Productivity, ASCE, New York, 16–27.
18.
Touran, A. (1993). “Probabilistic cost estimation with subjective correlations.”J. Constr. Engrg. and Mgmt., ASCE, 119(1), 58–71.
19.
Touran, A. (1994). “Probabilistic modeling of scheduling uncertainty: methods and tools.” Proc., Comp. in Civ. Engrg., ASCE, New York, 380–383.
20.
Ward, S. A., and Lithfield, T. (1980). Cost control in design and construction. McGraw-Hill, New York.

Information & Authors

Information

Published In

Go to Journal of Construction Engineering and Management
Journal of Construction Engineering and Management
Volume 126Issue 2March 2000
Pages: 142 - 148

History

Received: Dec 4, 1998
Published online: Mar 1, 2000
Published in print: Mar 2000

Permissions

Request permissions for this article.

Authors

Affiliations

Member, ASCE
Associate Member, ASCE
Assoc. Prof., Dept. of Industrial Engrg., Tecnológico de Monterrey, Monterrey, N.L. 64849, México.
Asst. Prof., Dept. of Civ. Engrg., Clemson Univ., Clemson, SC 29630.
Prof., Mgmt. Grad. School, Tecnológico de Monterrey, Monterrey, NL 64849, México.

Metrics & Citations

Metrics

Citations

Download citation

If you have the appropriate software installed, you can download article citation data to the citation manager of your choice. Simply select your manager software from the list below and click Download.

Cited by

View Options

Get Access

Access content

Please select your options to get access

Log in/Register Log in via your institution (Shibboleth)
ASCE Members: Please log in to see member pricing

Purchase

Save for later Information on ASCE Library Cards
ASCE Library Cards let you download journal articles, proceedings papers, and available book chapters across the entire ASCE Library platform. ASCE Library Cards remain active for 24 months or until all downloads are used. Note: This content will be debited as one download at time of checkout.

Terms of Use: ASCE Library Cards are for individual, personal use only. Reselling, republishing, or forwarding the materials to libraries or reading rooms is prohibited.
ASCE Library Card (5 downloads)
$105.00
Add to cart
ASCE Library Card (20 downloads)
$280.00
Add to cart
Buy Single Article
$35.00
Add to cart

Get Access

Access content

Please select your options to get access

Log in/Register Log in via your institution (Shibboleth)
ASCE Members: Please log in to see member pricing

Purchase

Save for later Information on ASCE Library Cards
ASCE Library Cards let you download journal articles, proceedings papers, and available book chapters across the entire ASCE Library platform. ASCE Library Cards remain active for 24 months or until all downloads are used. Note: This content will be debited as one download at time of checkout.

Terms of Use: ASCE Library Cards are for individual, personal use only. Reselling, republishing, or forwarding the materials to libraries or reading rooms is prohibited.
ASCE Library Card (5 downloads)
$105.00
Add to cart
ASCE Library Card (20 downloads)
$280.00
Add to cart
Buy Single Article
$35.00
Add to cart

Media

Figures

Other

Tables

Share

Share

Copy the content Link

Share with email

Email a colleague

Share