Automated Management of Time Extension Claims

Publication: Journal of Legal Affairs and Dispute Resolution in Engineering and Construction
Volume 16, Issue 2

Abstract

Disputes within the construction industry have caused parties to incur additional costs not accounted for. Ranking as one of the highest sources of disputes, there is a need to diminish reliance on the human factor in the extension of time (EOT) process and to bolster it with automation commodities. Six disadvantages were identified through the literature: poor record keeping, delayed event notification, an arduous process of EOT-related clauses within contracts, the lack of a superior delay analysis technique (DAT), no automation of a DAT, and finally a lack of standardized EOT submission reports. Research efforts have endeavored in tackling the drawbacks of the EOT process individually, no solution is provided to overcome all drawbacks at once to create one seamless process. This research aims to overcome the disadvantages present within the EOT submission process to provide a solution for the manual effort conducted in an EOT claim submission. Such was achieved though automated solutions that involve (1) live delay event notification and its proactive approvals; (2) natural language programming to extract EOT-related clauses; (3) a superior DAT; (4) the automation of the DAT; and (5) standardized claim document reporting system. The foregoing were then encompassed in a web-based system hereafter referred to as the automated management of time extension claims (AMTEC). AMTEC was then applied to a case study involving an EOT claim submission; it was initially applied manually and then using AMTEC. The level of effort, duration, and disputes within the entire process were compared in both scenarios. Results show that the duration for the processes decreased by 79% and the level of effort was decreased by 52%. Disputes within both scenarios were further analyzed and AMTEC was capable of overcoming the disputes faced within the manual process between parties.

Get full access to this article

View all available purchase options and get full access to this article.

Data Availability Statement

All data, models, or code that support the findings of this study are available from the corresponding author upon reasonable request.

References

Works Cited

Abd El-Razek, M. E., H. A. Bassioni, and A. M. Mobarak. 2008. “Causes of delay in building construction projects in Egypt.” J. Constr. Eng. Manage. 134 (11): 831–841. https://doi.org/10.1061/(ASCE)0733-9364(2008)134:11(831).
Abdul-Malak, M.-A., and S. Khalife. 2017. “Models for the administration of structured construction contract notices.” J. Leg. Aff. Dispute Resolut. Eng. Constr. 9 (3): 04517017. https://doi.org/10.1061/(ASCE)LA.1943-4170.0000228.
Abdul-Malak, M.-A. U., and T. A. Abdulhai. 2017. “Conceptualization of the contractor’s project management group dynamics in claims initiation and documentation evolution.” J. Leg. Aff. Dispute Resolut. Eng. Constr. 9 (3): 04517014. https://doi.org/10.1061/(ASCE)LA.1943-4170.0000229.
Agrawal, A. K., M. Jagannathan, and V. S. K. Delhi. 2020. “Control focus in standard forms: An assessment through text mining and NLP.” J. Leg. Aff. Dispute Resolut. Eng. Constr. 13 (1): 04520040. https://doi.org/10.1061/(ASCE)LA.1943-4170.0000441.
Ahmad, H. S., I. M. Bazlamit, and M. D. Ayoush. 2017. “Investigation of document management systems in small size construction companies in Jordan.” Procedia Eng. 182 (Jun): 3–9. https://doi.org/10.1016/j.proeng.2017.03.101.
Aibinu, A. A. 2009. “Contractual approach for facilitating the resolution of dispute over a contractor’s failure to comply with time limit for notice of delays.” J. Leg. Aff. Dispute Resolut. Eng. Constr. 1 (3): 137–146. https://doi.org/10.1061/(ASCE)1943-4162(2009)1:3(137).
Al-Gahtani, K. S., I. A. Al-Sulaihi, and A. Iqupal. 2016. “Total float management: Computerized technique for construction delay analysis.” Can. J. Civ. Eng. 43 (5): 391–401. https://doi.org/10.1139/cjce-2015-0434.
Al Qady, M., and A. Kandil. 2009. “Concept relation extraction from construction documents using natural language processing.” J. Constr. Eng. Manage. 136 (3): 294–302. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000131.
Al Qady, M., and A. Kandil. 2013. “Document management in construction: Practices and opinions.” J. Constr. Eng. Manage. 139 (10): 06013002. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000741.
Arai, K., R. Bhatia, and S. Kapoor. 2020. “Proceedings of the future technologies conference (FTC) 2019: Volume 2.” In Vol. 1070 of Advances in intelligent systems and computing. Cham, Switzerland: Springer. https://doi.org/10.1007/978-3-030-32523-7.
Arcadis. 2020. “Global construction disputes report.” Accessed February 12, 2023. https://www.cmaanet.org/elearning/2020-global-construction-disputes-report.
Arditi, D., G. T. Akan, and S. Gurdamar. 1985. “Reasons for delays in public projects in Turkey.” Construct. Manage. Econ. 3 (2): 171–181. https://doi.org/10.1080/01446198500000013.
Assaf, S. A., and S. Al-Hejji. 2006. “Causes of delay in large construction projects.” Int. J. Project Manage. 24 (4): 349–357. https://doi.org/10.1016/j.ijproman.2005.11.010.
Björk, B.-C. 2003. “Electronic document management in construction–research issues and results.” ITcon 8 (Jan): 105–117.
Candaş, A. B., and O. B. Tokdemir. 2022. “Automating coordination efforts for reviewing construction contracts with multilabel text classification.” J. Constr. Eng. Manage. 148 (6): 04022027. https://doi.org/10.1061/(ASCE)CO.1943-7862.0002275.
Çevikbaş, M., and Z. Işık. 2021. “An overarching review on delay analyses in construction projects.” Buildings 11 (3): 109. https://doi.org/10.3390/buildings11030109.
Chen, G., M. Liu, Y. Zhang, Z. Wang, S. M. Hsiang, and C. He. 2023. “Using images to detect, plan, analyze, and coordinate a smart contract in construction.” J. Manage. Eng. 39 (2): 04023002. https://doi.org/10.1061/JMENEA.MEENG-5121.
Chowdhary, K. R. 2020. Fundamentals of artificial intelligence. New Delhi, India: Springer. https://doi.org/10.1007/978-81-322-3972-7.
Cinko, E. G., S. Demirkesen, E. Sadikoglu, and C. Zhang. 2023. “Investigating the critical success factors of claims management in construction contracts.” J. Leg. Aff. Dispute Resolut. Eng. Constr. 15 (2): 04522066. https://doi.org/10.1061/JLADAH.LADR-921.
Ding, Y., J. Ma, and X. Luo. 2022. “Applications of natural language processing in construction.” Autom. Constr. 136 (Apr): 104169. https://doi.org/10.1016/j.autcon.2022.104169.
Douglas, L. E. 2002. “Schedule analyzer pro - an aid in the analysis of delay time impact analysis–proquest.” Cost Eng. 44 (8): 30–36.
Elazhary, M. 2021. “Tracking delay analysis.” J. Leg. Aff. Dispute Resolut. Eng. Constr. 13 (3): 04521020. https://doi.org/10.1061/(ASCE)LA.1943-4170.0000485.
El Nemr, W., and H. Mohamed. 2019. CDR-3250 Legal and practical challenges to the implementation of the time impact analysis method. Morgantown, WV: Association for the Advancement of Cost Engineering.
Enshassi, A., J. Al-Najjar, and M. Kumaraswamy. 2009. “Delays and cost overruns in the construction projects in the Gaza strip.” J. Financ. Manage. Prop. Constr. 14 (2): 126–151. https://doi.org/10.1108/13664380910977592.
Faridi, A. S., and S. M. El-Sayegh. 2006. “Significant factors causing delay in the UAE construction industry.” Construct. Manage. Econ. 24 (11): 1167–1176. https://doi.org/10.1080/01446190600827033.
Fellows, R. F., D. Langford, R. Newcombe, and S. Urry. 2009. Construction management in practice. New York: Wiley.
Fernando, H., T. Hewavitharana, and A. Perera. 2019. “Evaluation of electronic document management (EDM) Systems for construction organizations.” In Proc., Moratuwa Engineering Research Conf. (MERCon), 273–278. New York: IEEE. https://doi.org/10.1109/MERCon.2019.8818768.
Finch, E. F., R. Flanagan, and L. E. Marsh. 1996. “Electronic document management in construction using auto-ID.” Autom. Constr. 5 (4): 313–321. https://doi.org/10.1016/S0926-5805(96)00156-2.
Forcada, N., M. Casals, X. Roca, and M. Gangolells. 2007. “Adoption of web databases for document management in SMEs of the construction sector in Spain.” Autom. Constr. 16 (4): 411–424. https://doi.org/10.1016/j.autcon.2006.07.011.
Gharaibeh, H. 2014. “Evaluating project management software packages using a scoring model—A comparison between MS project and Primavera.” J. Software Eng. Appl. 7 (7): 541. https://doi.org/10.4236/jsea.2014.77050.
González, P., V. González, K. Molenaar, and F. Orozco. 2013. “Analysis of causes of delay and time performance in construction projects.” J. Constr. Eng. Manage. 140 (1): 04013027. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000721.
Hajjar, D., and S. M. AbouRizk. 2000. “Integrating document management with project and company data.” J. Comput. Civ. Eng. 14 (1): 70–77. https://doi.org/10.1061/(ASCE)0887-3801(2000)14:1(70).
Hamzah, N., M. A. Khoiry, I. Arshad, N. M. Tawil, and A. I. Che Ani. 2011. “Cause of construction delay - theoretical framework.” Procedia Eng. 20 (Jun): 490–495. https://doi.org/10.1016/j.proeng.2011.11.192.
Hassan, F. U., and T. Le. 2020. “Automated requirements identification from construction contract documents using natural language processing.” J. Leg. Aff. Dispute Resolut. Eng. Constr. 12 (2): 04520009. https://doi.org/10.1061/(ASCE)LA.1943-4170.0000379.
Hjelt, M., and B.-C. Björk. 2006. “Experiences of EDM usage in construction projects.” ITcon 11 (Feb): 113–125.
Hoshino, K. P., J. C. Livengood, and C. W. Carson. 2011. “Forensic schedule analysis.” In Proc., AACE: Int. Recommended Practice, 135. Fairmont, WV: Association for the Advancement of Cost Engineering.
Jergeas, G. F., and F. T. Hartman. 1994. “Contractors’ construction-claims avoidance.” J. Constr. Eng. Manage. 120 (3): 553–560. https://doi.org/10.1061/(ASCE)0733-9364(1994)120:3(553).
Kaliba, C., M. Muya, and K. Mumba. 2009. “Cost escalation and schedule delays in road construction projects in Zambia.” Int. J. Project Manage. 27 (5): 522–531. https://doi.org/10.1016/j.ijproman.2008.07.003.
Kalyanathaya, K. P., D. Akila, and P. Rajesh. 2019. “Advances in natural language processing–A survey of current research trends, development tools and industry applications.” Int. J. Recent Technol. Eng. 7 (5): 199–202.
Kartam, S. 1999. “Generic methodology for analyzing delay claims.” J. Constr. Eng. Manage. 125 (6): 409–419. https://doi.org/10.1061/(ASCE)0733-9364(1999)125:6(409).
Keane, P. J., and A. F. Caletka. 2015. Delay analysis in construction contracts. 2nd ed. Hoboken, NJ: Blackwell.
Khalife, S., and M.-A. Abdul-Malak. 2018. “Investigating site-related notices in construction contracts.” Proc. Int. Struct. Eng. Constr. 5 (1). https://doi.org/10.14455/ISEC.res.2018.35.
Khoshgoftar, M., A. H. A. Bakar, and O. Osman. 2010. “Causes of delays in Iranian construction projects.” Int. J. Constr. Manage. 10 (2): 53–69. https://doi.org/10.1080/15623599.2010.10773144.
Kiziltas, S., B. Akinci, E. Ergen, P. Tang, and C. Gordon. 2008. “Technological assessment and process implications of field data capture technologies for construction and facility/infrastructure management.” J. Inf. Technol. Construct. (ITcon) 13 (10): 134–154.
Kumaraswamy, M. M., and K. Yogeswaran. 2003. “Substantiation and assessment of claims for extensions of time.” Int. J. Project Manage. 21 (1): 27–38. https://doi.org/10.1016/S0263-7863(01)00052-7.
Lee, J. H., J.-S. Yi, and J. W. Son. 2019. “Development of automatic-extraction model of poisonous clauses in international construction contracts using rule-based NLP.” J. Comput. Civil Eng. 33 (3): 04019003. https://doi.org/10.1061/(ASCE)CP.1943-5487.0000807.
Lehtiranta, L. 2014. “Risk perceptions and approaches in multi-organizations: A research review 2000–2012.” Int. J. Project Manage. 32 (4): 640–653. https://doi.org/10.1016/j.ijproman.2013.09.002.
Lo, T. Y., I. W. Fung, and K. C. Tung. 2006. “Construction delays in Hong Kong civil engineering projects.” J. Constr. Eng. Manage. 132 (6): 636–649. https://doi.org/10.1061/(ASCE)0733-9364(2006)132:6(636).
Mezher, T. M., and W. Tawil. 1998. “Causes of delays in the construction industry in Lebanon.” Eng. Constr. Archit. Manage. 5 (3): 252–260. https://doi.org/10.1108/eb021079.
Nehme, F., and K. Feldman. 2021. “Evolving role and future directions of natural language processing in gastroenterology.” Digestive Dis. Sci. 66 (1): 29–40. https://doi.org/10.1007/s10620-020-06156-y.
Nitithamyong, P., and M. J. Skibniewski. 2004. “Web-based construction project management systems: How to make them successful?” Autom. Constr. 13 (4): 491–506. https://doi.org/10.1016/j.autcon.2004.02.003.
Okpala, D. C., and A. N. Aniekwu. 1988. “Causes of high costs of construction in Nigeria.” J. Constr. Eng. Manage. 114 (2): 233–244. https://doi.org/10.1061/(ASCE)0733-9364(1988)114:2(233).
Oracle. 2009. P6 project management reference manual. Austin, TX: Oracle.
Prieto, S. A., E. T. Mengiste, and B. García de Soto. 2023. “Investigating the use of ChatGPT for the scheduling of construction projects.” Buildings 13 (4): 857. https://doi.org/10.3390/buildings13040857.
Rachid, Z., B. Toufik, and B. Mohammed. 2019. “Causes of schedule delays in construction projects in Algeria.” Int. J. Construct. Manage. 19 (5): 371–381. https://doi.org/10.1080/15623599.2018.1435234.
Ron Winter Consulting Corporation. 2010. “Schedule analyzer software.” Accessed February 1, 2023. http://scheduleanalyzer.com/index.htm.
Salunkhe, A., and R. S. Patil. 2014. “Effect of construction delays on project time overrun: Indian scenario.” Int. J. Res. Eng. Technol. 03 (01): 543–547. https://doi.org/10.15623/ijret.2014.0301091.
Samuelson, O., and B.-C. Björk. 2014. “Adoption processes for EDM, EDI and BIM technologies in the construction industry.” Supplement, J. Civ. Eng. Manage. 19 (S1): S172–S187. https://doi.org/10.3846/13923730.2013.801888.
Sanni-Anibire, M. O., R. M. Zin, and S. O. Olatunji. 2022. “Causes of delay in the global construction industry: A meta analytical review.” Int. J. Constr. Manage. 22 (8): 1395–1407. https://doi.org/10.1080/15623599.2020.1716132.
Semple, C., F. T. Hartman, and G. Jergeas. 1994. “Construction claims and disputes: Causes and cost/time overruns.” J. Constr. Eng. Manage. 120 (4): 785–795. https://doi.org/10.1061/(ASCE)0733-9364(1994)120:4(785).
Senaratne, S., and J. Mayuran. 2015. “Documentation management based on ISO for construction industries in developing countries.” J. Constr. Dev. Countries 20 (2): 81–95.
Seneviratne, K., and G. V. Michael. 2020. “Disputes in time bar provisions for contractors’ claims in standard form of contracts.” Int. J. Construct. Manage. 20 (4): 335–346. https://doi.org/10.1080/15623599.2018.1484854.
Seo, W., Y. H. Kwak, and Y. Kang. 2021. “Relationship between consistency and performance in the claim management process for construction projects.” J. Manage. Eng. 37 (6): 04021068. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000973.
Singh, R. 2010. “Delays and cost overruns in infrastructure projects: Extent, causes and remedies.” Econ. Polit. Wkly 45 (21): 43–54.
Srdić, A., and A. J. Šelih. 2015. “Delays in construction projects: Causes and mitigation.” Organ. Technol. Manage. Constr. Int. 7 (3): 1383–1389. https://doi.org/doi:10.5592/otmcj.2015.3.5.
Sui, L. 2020. “Profiling of valid available grounds to claim extension of time in construction industry.” M.Sc. thesis, Built Environment and Surveying, Universiti Teknologi Malaysia.
Surabhi, M. C. 2013. “Natural Language processing future.” In Proc., Int. Conf. on Optical Imaging Sensor and Security (ICOSS), 1–3. New York: IEEE. https://doi.org/10.1109/ICOISS.2013.6678407.
Sweis, G., R. Sweis, A. Abu Hammad, and A. Shboul. 2008. “Delays in construction projects: The case of Jordan.” Int. J. Project Manage. 26 (6): 665–674. https://doi.org/10.1016/j.ijproman.2007.09.009.
Toor, S. U. R., and S. Ogunlana. 2008. “Problems causing delays in major construction projects in Thailand.” Construct. Manage. Econ. 26 (4): 395–408. https://doi.org/10.1080/01446190801905406.
Tsai, M.-K., J.-B. Yang, and N.-J. Yau. 2013. “Developing computer-based schedule delay analysis methods based on information flow analysis: A case study.” J. Civ. Eng. Manage. 19 (6): 823–835. https://doi.org/10.3846/13923730.2013.801901.
Wang, J., S. Zhang, P. Fenn, X. Luo, Y. Liu, and L. Zhao. 2022. “Adopting BIM to facilitate dispute management in the construction industry: A conceptual framework development.” J. Constr. Eng. Manage. 149 (1): 03122010. https://doi.org/10.1061/(ASCE)CO.1943-7862.0002419.
Xu, X., and H. Cai. 2021. “Ontology and rule-based natural language processing approach for interpreting textual regulations on underground utility infrastructure.” Adv. Eng. Inf. 48 (Apr): 101288. https://doi.org/10.1016/j.aei.2021.101288.
Yang, J.-B., and C.-K. Kao. 2009. “Review of delay analysis methods: A process-based comparison.” Open Constr. Build. Technol. J. 3 (1): 81–89. https://doi.org/10.2174/1874836800903010081.
Yang, J.-B., and M.-K. Tsai. 2010. “Computerizing ICBF method for schedule delay analysis.” J. Constr. Eng. Manage. 137 (8): 583–591. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000338.
Yang, J.-B., and P.-C. Yin. 2009. “Isolated collapsed but-for delay analysis methodology.” J. Constr. Eng. Manage. 135 (7): 570–578. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000016.
Yusuwan, N. M., and H. Adnan. 2013. “Issues associated with extension of time (EoT) claim in Malaysian construction industry.” Procedia Technol. 9 (Dec): 740–749. https://doi.org/10.1016/j.protcy.2013.12.082.

Information & Authors

Information

Published In

Go to Journal of Legal Affairs and Dispute Resolution in Engineering and Construction
Journal of Legal Affairs and Dispute Resolution in Engineering and Construction
Volume 16Issue 2May 2024

History

Received: Jun 2, 2023
Accepted: Sep 29, 2023
Published online: Dec 20, 2023
Published in print: May 1, 2024
Discussion open until: May 20, 2024

Permissions

Request permissions for this article.

ASCE Technical Topics:

Authors

Affiliations

Dept. of Construction Engineering, American Univ. in Cairo, Parcel 8, 74 S El-Teseen St., New Cairo, Cairo 11835, Egypt (corresponding author). ORCID: https://orcid.org/0009-0003-2497-5830. Email: [email protected]
Ossama Hosny, Ph.D. [email protected]
Professor, Dept. of Construction Engineering, American Univ. in Cairo, Parcel 8, 74 S El-Teseen St., New Cairo, Cairo 11835, Egypt. Email: [email protected]

Metrics & Citations

Metrics

Citations

Download citation

If you have the appropriate software installed, you can download article citation data to the citation manager of your choice. Simply select your manager software from the list below and click Download.

View Options

Get Access

Access content

Please select your options to get access

Log in/Register Log in via your institution (Shibboleth)
ASCE Members: Please log in to see member pricing

Purchase

Save for later Information on ASCE Library Cards
ASCE Library Cards let you download journal articles, proceedings papers, and available book chapters across the entire ASCE Library platform. ASCE Library Cards remain active for 24 months or until all downloads are used. Note: This content will be debited as one download at time of checkout.

Terms of Use: ASCE Library Cards are for individual, personal use only. Reselling, republishing, or forwarding the materials to libraries or reading rooms is prohibited.
ASCE Library Card (5 downloads)
$105.00
Add to cart
ASCE Library Card (20 downloads)
$280.00
Add to cart
Buy Single Article
$35.00
Add to cart

Get Access

Access content

Please select your options to get access

Log in/Register Log in via your institution (Shibboleth)
ASCE Members: Please log in to see member pricing

Purchase

Save for later Information on ASCE Library Cards
ASCE Library Cards let you download journal articles, proceedings papers, and available book chapters across the entire ASCE Library platform. ASCE Library Cards remain active for 24 months or until all downloads are used. Note: This content will be debited as one download at time of checkout.

Terms of Use: ASCE Library Cards are for individual, personal use only. Reselling, republishing, or forwarding the materials to libraries or reading rooms is prohibited.
ASCE Library Card (5 downloads)
$105.00
Add to cart
ASCE Library Card (20 downloads)
$280.00
Add to cart
Buy Single Article
$35.00
Add to cart

Media

Figures

Other

Tables

Share

Share

Copy the content Link

Share with email

Email a colleague

Share