Chapter
Sep 20, 2022
Electrical Transmission and Substation Structures 2022

Keeping It Close: A Composite Solution to Rebuilding a 69 kV Line

Publication: Electrical Transmission and Substation Structures 2022: Innovating for Critical Global Infrastructure

ABSTRACT

There are several critical customers located in Southern Maryland Electric Cooperative, SMECO territory. Until recently, one customer had been served by Potomac Electric Power Company, PEPCO, up until 2012 when the feed to the facility was purchased from PEPCO by SMECO. The feed to this customer is a radial, 69-kilovolt line dating back to the mid 1940s. When SMECO purchased the line, it was in need of extensive repair. A significant section of the line needed to be rebuilt entirely. The line rebuild presented numerous challenges that had to be addressed, including: The only back up source for the line is onsite generation that cannot support the entire facility at once. Extended outages were not an option and were limited to weekends in late fall and early spring. The line would have to be rebuilt while the existing line remained energized. The railroad, parallel to the line, had been converted to a hiker/biker trail with significant pedestrian traffic. The line traverses part of the Mattawoman Creek watershed, which is recognized to be a critical area by the EPA. Given the critical nature of the line and surrounding limitations, SMECO realized that standard construction practices would not be practical within the project’s parameters. In conjunction with the project engineer, Booth & Associates, SMECO evaluated several options for rebuilding the line and determined the most practical option was to rebuild the line using composite poles on an offset centerline 10 feet from the existing centerline. Composite poles have a life expectancy comparable to steel poles, and the lightweight nature of composite material allowed the contractor to use lighter construction equipment resulting in no significant damage to the bike path. The base sections were set first, and the pole tops were set using only the material handler on the contractor’s bucket trucks. Only two outages under two days each spread over two weekends were required to complete the line cutover and retire the old line.

Get full access to this article

View all available purchase options and get full access to this chapter.

References

Maryland Department of Natural Resources Environmental Resources and Land Information Network https://dnr.maryland.gov/Pages/Merlin.aspx(February 22, 2021)
AUI Powerhttps://auipower.com/(February 22, 2021)

Information & Authors

Information

Published In

Go to Electrical Transmission and Substation Structures 2022
Electrical Transmission and Substation Structures 2022: Innovating for Critical Global Infrastructure
Pages: 279 - 290
Editor: Tim Cashman
ISBN (Online): 978-0-7844-8446-3

History

Published online: Sep 20, 2022
Published in print: Sep 20, 2022

Permissions

Request permissions for this article.

Authors

Affiliations

Hugh Voehl III [email protected]
Southern Maryland Electric Cooperative, Hughesville, MD. E-mail: [email protected]
Ryan Schlotterbeck [email protected]
P.E.
Southern Maryland Electric Cooperative, Hughesville, MD. E-mail: [email protected]
John Williams [email protected]
P.E.
Booth & Associates, LLC, Owings Mills, MD. E-mail: [email protected]

Metrics & Citations

Metrics

Citations

Download citation

If you have the appropriate software installed, you can download article citation data to the citation manager of your choice. Simply select your manager software from the list below and click Download.

View Options

Get Access

Access content

Please select your options to get access

Log in/Register Log in via your institution (Shibboleth)
ASCE Members: Please log in to see member pricing

Purchase

Save for later Information on ASCE Library Cards
ASCE Library Cards let you download journal articles, proceedings papers, and available book chapters across the entire ASCE Library platform. ASCE Library Cards remain active for 24 months or until all downloads are used. Note: This content will be debited as one download at time of checkout.

Terms of Use: ASCE Library Cards are for individual, personal use only. Reselling, republishing, or forwarding the materials to libraries or reading rooms is prohibited.
ASCE Library Card (5 downloads)
$105.00
Add to cart
ASCE Library Card (20 downloads)
$280.00
Add to cart
Buy Single Paper
$35.00
Add to cart
Buy E-book
$98.00
Add to cart

Get Access

Access content

Please select your options to get access

Log in/Register Log in via your institution (Shibboleth)
ASCE Members: Please log in to see member pricing

Purchase

Save for later Information on ASCE Library Cards
ASCE Library Cards let you download journal articles, proceedings papers, and available book chapters across the entire ASCE Library platform. ASCE Library Cards remain active for 24 months or until all downloads are used. Note: This content will be debited as one download at time of checkout.

Terms of Use: ASCE Library Cards are for individual, personal use only. Reselling, republishing, or forwarding the materials to libraries or reading rooms is prohibited.
ASCE Library Card (5 downloads)
$105.00
Add to cart
ASCE Library Card (20 downloads)
$280.00
Add to cart
Buy Single Paper
$35.00
Add to cart
Buy E-book
$98.00
Add to cart

Media

Figures

Other

Tables

Share

Share

Copy the content Link

Share with email

Email a colleague

Share