EVMS Maturity and Its Impact on Project Cost and Schedule Performance of Large and Complex Projects: A Preliminary Analysis
Publication: Construction Research Congress 2022
ABSTRACT
An Earned Value Management System (EVMS) is an organization’s system for project/program management that integrates a defined set of associated work scopes, schedules, and budgets, allowing for effective planning, performance, and management control. Using a mature EVMS is critical to overall project success of large complex government projects. The government customer’s expectation of a mature EVMS is to provide current and accurate data to control the project and support informed decision-making, including cost and schedule predictions. However, a comprehensive literature review reveals that there is a need for a consistent rating to measure the maturity of an EVMS. The primary objective of this paper is developing a new EVMS maturity rating, validating it on real projects, and testing its impact on project performance in terms of cost and schedule growth. The authors developed the rating based on a literature review of more than 300 references, a survey of more than 250 respondents, and workshops with more than 50 expert practitioners. The paper identifies 56 maturity attributes that are responsible for EVMS maturity and tests the new maturity framework on real projects to measure its impact on project performance. The preliminary results of data collected from 11 real-life projects, totaling $12.5 billion in project costs, show significant differences in cost and schedule performance between the projects with lower EVMS maturity scores and those with higher maturity scores.
Get full access to this article
View all available purchase options and get full access to this chapter.
REFERENCES
Aramali, V., Gibson, G. E., Jr., El Asmar, M., and Cho, N. (2021). “Earned Value Management System (EVMS) State of Practice: Identifying Critical Processes, Challenges and Factors of a High-Performing EVMS.” J. Manage. Eng. ASCE. In Press.
Cho, N., El Asmar, M., Gibson, G. E., Jr., and Aramali, V. (2020). “Earned Value Management System (EVMS) Reliability: A Review of Existing EVMS Literature.” Construction Research Congress 2020. Reston, VA: American Society of Civil Engineers.
Christensen, D. S., and Heise, S. R. (1993). “Cost performance index stability.” National Contract Management Journal, 25(1), 7–15.
Christensen, D. S., and Templin, C. (2002). “EAC evaluation methods: do they still work.” Acquisition Review Quarterly, 9(1), 105–116.
Christensen, D., and Payne, K. (1992). “Cost performance index stability: fact or fiction?.” Journal of Parametrics, 12(1), 27–40.
DOE (Department of Energy). (2018). Office of Project Management EVMS Compliance Review Standard Operating Procedure (ECRSOP). Washington, DC.
DOE (Department of Energy). (2019). DOE EVMS gold card. Washington, DC.
Djali, S., Janssens, S., Van Yper, S., and Van Parijs, J. (2010). “How a data-driven quality management system can manage compliance risk in clinical trials.” Drug Information Journal, 44(4), 359–373.
Driessnack, J. D. (2017). “The History of Earned Value Management, The 60’s.” College of Performance Management, The Measurable News, (2), 29–34.
Fleming, Q., and Koppelman, J. M. (2009). “The two most useful earned value metrics: the CPI and the TCPI.” Cost Engineering, 51(3), 16–18.
GAO (Government Accountability Office). (2015). Schedule Assessment Guide: Best Practices for Project Schedules. Washington, DC.
Humphreys, G. C. (2016). “EVMS – After the Evolution: The Long Slow Road.” College of Performance Management, The Measurable News, (1), 19–22.
ISO (International Standard Organization). (2018). Earned value management in project and programme management. Geneva: ISO.
Kester, D., Cottrell, D., and Carney, K. (2015). “Data Driven EVMS Compliance: An Analytical Approach That Will Transform the Way We Think About Managing.” College of Performance Management, The Measurable News, (2), 7–13.
McGregor, J. S. (2019). Department of Defense Earned Value Management Implementation Guide (EVMIG). Arlington, VA: Department of Defense.
NASA (National Aeronautics and Space Administration). (2018). Earned value management (EVM) implementation handbook. Washington, DC.
NDIA (National Defense Industrial Association). (2018a). Earned Value Management Systems Application Guide. Arlington, VA: Integrated Program Management Division.
NDIA (National Defense Industrial Association). (2018b). Earned Value Management Systems EIA-748-D Intent Guide. Arlington, VA: Integrated Program Management Division.
NDIA (National Defense Industrial Association). (2020). Earned Value Management System Guideline Scalability Guide. Arlington, VA: Integrated Program Management Division.
Petter, J. L., Ritschel, J. D., and White, E. D. (2014). “SPI(T) STABILITY: ANALYZING DOD CONTRACTS.” College of Performance Management, The Measurable News, (2), 24–28.
PMI (Project Management Institute). (2019). The Standard for Earned Value Management. Newtown Square, PA: Project Management Institute.
Stratton, R. W. (2006). The earned value management maturity model. San Francisco: Berrett-Koehler Publishers.
Yussef, A., Gibson, G. E., Jr., El Asmar, M., and Ramsey, D. (2019). “Quantifying FEED maturity and its impact on project performance in large industrial projects.” J. Manage. Eng. 35(5): 04019021.
Yussef, A., Gibson, G. E., Jr., El Asmar, M., and Ramsey, D. (2020). Industry Survey for Determining the State of Practice of Front End Engineering Design for Industrial Construction. Practice Periodical on Structural Design and Construction, 25(4), 04020025.
Information & Authors
Information
Published In
History
Published online: Mar 7, 2022
Authors
Metrics & Citations
Metrics
Citations
Download citation
If you have the appropriate software installed, you can download article citation data to the citation manager of your choice. Simply select your manager software from the list below and click Download.