Subcontractor Schedule Performance: Finance-Inspired Schedule Beta Indices
Publication: Construction Research Congress 2020: Project Management and Controls, Materials, and Contracts
ABSTRACT
Construction projects continue to be faced with chronic delay issues, which are not yet quantifiable to become controllable. In construction projects, subcontractors play an important role and directly contribute to the production progress. Evaluating their schedule performance can become a valuable strategy for general contractors as part of their risk mitigation. It also allows subcontractors to substantiate their reputation with an objective value. In the future, this can be added to prequalification akin to setting safety expectations and allow bonding agencies to refine subcontractor ratings. One should therefore develop a meaningful mathematical quantification of schedule performance by subcontractors. Previous research has adapted the so-called beta, a financial index that tracks stock price performance within their market. But the new schedule beta functions like a correlation coefficient, i.e., by definition it cannot distinguish fast subcontractor activities in a fast project from slow activities in a slow project. This research therefore refines schedule beta by breaking it into its downside and upside constituent parts of schedule performance, again inspired by finance. An exemplar is reanalyzed to demonstrate its functioning and explain different types of subcontractor performance. Results confirm the feasibility of extracting the downside and upside schedule beta, which can support the goal of keeping projects on time.
Get full access to this article
View all available purchase options and get full access to this chapter.
ACKNOWLEDGEMENT
The support of National Science Foundation (CMMI-1536005) and Charles Pankow Foundation (#07-16) for portions of the work presented here is gratefully acknowledged. Opinions, findings, and conclusions or recommendations expressed in this material are the authors’ and not necessarily represent the views of NSF and CPF.
REFERENCES
Adam, A., Josephson, P., Lindahl, G. (2017). “Aggregation of factors causing cost overruns and time delays in large public construction projects: Trends and implications.” Eng. Constr. Arch. Mgmt., 24(3), 393-406.
Al-Gahtani, K. S. (2006). A comprehensive construction delay analysis technique – enhanced with a float ownership concept. Dissertation, SUNY: 388pp.
Austin, R. B. Pishdad-Bozorgi, P., de la Garza, J. M. (2015). “Identifying and Prioritizing Best Practices to Achieve Flash Track Projects.” JCEM, 142(2): 04015077(12).
Black, F., Jensen, M. C., Scholes, M. (1972). The Capital Asset Pricing Model: Some Empirical Tests. Ed. Jensen, M., Studies in the Theory of Capital Markets. Praeger, New York, NY.
Braimah, N., Ndekugri, I. (2009). “Consultants’ Perceptions on Construction Delay Analysis Methodologies.” JCEM, 135(12): 1279-1288.
Chong, J. T., Halcoussis, D., Phillips, G. M. (2012). “Misleading Betas: An Educational Example.” Am. J. Bus. Educ., 5(5): 617-622.
Chong, J. T., Jin, Y., Phillips, G. M. (2014). “The Entrepreneur’s Cost of Capital: Incorporating Downside Risk.” Bus. Valuation Rev., 33(3): 81-91.
Esmaeili, B., Hallowell, M. R., Rajagopalan, B. (2015). “Attribute-Based Safety Risk Assessment. II: Predicting Safety Outcomes Using Generalized Linear Models.” JCEM, 141(8): 04015022(11).
Everett, J. G., Thompson, W. S. (1995). “Experience Modification Rating for Workers’ Compensation Insurance.” JCEM, 121(1): 66-79.
Garcia, M. V. A. T. (2019). A Comparative Analysis and Evaluation of Existing Construction Delay Analysis Methods Based on Critical Path Network. Thesis, Catholic University of America, Washington, DC: 122pp.
Gosling, J., Naim, M., Towill, D. (2013). “Identifying and Categorizing the Sources of Uncertainty in Construction Supply Chains.” JCEM, 139(1): 102-110.
Huynh, H. T., Su, Y., Lucko, G., Thompson, R. C. (2018). “Beta Index and Complexity in Schedule Performance Measurement.” Proc. Constr. Res. Congr., ASCE, Reston, VA: 471-480.
Kadry, M., Osman, H., Georgy, M. (2016). “Causes of Construction Delays in Countries with High Geopolitical Risks.” JCEM, 143(2): 04016095(11).
Larsen, J. K., Shen, G. Q., Lindhard, S. M., Brunoe, T. D. (2016). “Factors Affecting Schedule Delay, Cost Overrun, and Quality Level in Public Construction Projects.” JME, 32(1): 04015032(10).
Mao, J. C. T. (1970). “Survey of Capital Budgeting: Theory and Practice.” J. Fin., 25(2): 349-60.
NRC (2009). Advancing the Competitiveness and Efficiency of the U.S. Construction Industry. National Research Council, Washington, DC: 114pp.
Guy, A. (2015). “Upside and downside beta portfolio construction: A different approach to risk measurement and portfolio construction.” Risk Governance and Control: Financial Markets and Institutions, 5(4): 243-251.
Thompson, R. C., Lucko, G. (2013). “Modeling Measures of Risk Correlation for Quantitative Float Management of Construction Projects.” Proc. 5thInt. Conf. Constr. Eng. Proj. Mgmt., UNC, Charlotte, NC: 8pp.
Thompson, R. C., Lucko, G., Su, Y. (2016). “Reconsidering an Appropriate Probability Distribution Function for Construction Simulation.” Proc. Constr. Res. Congr., ASCE, Reston, VA: 2522-2531.
Thompson, R. C., Su, Y., Lucko, G. (2017). “Measuring Project Performance Inspired by Stock Index.” Procedia Eng., 196: 706-713
Information & Authors
Information
Published In
Construction Research Congress 2020: Project Management and Controls, Materials, and Contracts
Pages: 525 - 534
Editors: David Grau, Ph.D., Arizona State University, Pingbo Tang, Ph.D., Arizona State University, and Mounir El Asmar, Ph.D., Arizona State University
ISBN (Online): 978-0-7844-8288-9
Copyright
© 2020 American Society of Civil Engineers.
History
Published online: Nov 9, 2020
Published in print: Nov 9, 2020
Authors
Metrics & Citations
Metrics
Citations
Download citation
If you have the appropriate software installed, you can download article citation data to the citation manager of your choice. Simply select your manager software from the list below and click Download.