Free access
Back Matter
Dec 14, 2022

Index for Geotechnical Baseline Reports

Publication: Geotechnical Baseline Reports: Suggested Guidelines

Abstract

This is the index for the publication

Formats available

You can view the full content in the following formats:

Note: Page numbers followed by f and t indicate figures and tables.
baseline
21
conservative
48
DSC clause
24
goals
21–23
ground characterization table with
36t–37t
items to be addressed in
22–23
linking with other contract documents
28–29
occurrence of boulders
24
parameters for engineering class
39f
payment quantities
79
project challenges
21
quantitative
47
setting
27–28
setting data ranges as
77
shaft excavation
24
for smaller projects
58–59
statements
23, 25, 76
by tunnel reach
42–43
uncertainty
25–27
verifiable
23–25
Better Contracting for Underground Construction
1
case histories
81t–84t
Changed Conditions clause
Differing Site Condition clause
Code of Federal Regulations (CFR)
18
construction manager (CM)
54, 74responsibilities of parties
Construction Manager at Risk (CMAR)
54delivery alternatives
Construction manager general contractor (CMGC)
54delivery alternatives
Contingency Fund
8
contractor, the
73responsibilities of parties
contractual and legal considerations
65
baselines in GBR
67–68
DSC entitlement
68
entitlement standard
66
GBR standing within contract
65–66
material difference and compensable claim
69
Methods Statement
69
relationship to other contract documents
66–67
reliance and causation
68–69
unforseeability
67
delivery alternatives
49
additional
54–55
Construction Manager at Risk
54
Construction manager general contractor
54
design-bid-build delivery
50
design-build delivery
50–51
Early Contractor Involvement
54
GBR development approach options
49
General contractor construction manager
54
progressive design-build delivery
53–54
Public–Private Partnership
55
success factors
49Geotechnical Baseline Report development
design-bid-build (DBB)
5
delivery
50delivery alternatives
design-build (DB)
5
delivery
50–51, 78delivery alternatives
Differing Site Condition clause (DSC clause)
17, 24, 77
bidding practices
77–78
“Entitlement Standard”
20
Federal clause
17
function of
19
historical development
17–18
modifications to standard clause
19–20
standard clause
18
Differing Site Conditions (DSC)
3
dispute adjudicator, the
74responsibilities of parties
Disputes Review Board (DRB)
3, 75
Early Contractor Involvement (ECI)
54delivery alternatives
Engineering News Record (ENR)
78
Engineer of Record (EOR)
14, 49
“Entitlement Standard”
20Differing Site Condition clause
Environmental Data Report
14
Escrow Bid Documents (EBDs)
3, 58
Federal clause
17Differing Site Condition clause
GBR for bidding (GBR-B)
51
GBR for Contracting (GBR-C)
52
General contractor construction manager (GCCM)
54delivery alternatives
Geotechnical Baseline Report (GBR)
1, 3, 4
bargain
5–8
baseline statements in
25
benefits of guidelines
10
Better Contracting for Underground Construction
1
bidding practices
77–78
Contingency Fund
8
contracts for underground construction projects
3
contractual understanding
5
DBB project delivery
5
development process
5
evolution of need for
1–2
Geotechnical Site Investigations for Underground Projects
2
ground reference conditions
4
guideline document scope
10–11
guideline publications
3–4
improved contracting practices
2–3
known unknowns
6
May 2022 workshop
80
November 2021 workshop
80
Port of Miami Tunnel Project
8
preparation of
6
purpose of
4, 8–9
quality of GBRs
75
recent practices and lessons learned
75–80
reduced levels of site investigation
78–79
risk analyses and funding buckets
7f
risk assessment
6
shortcomings of previous practice
9
stages of project development
6
Task Committee on
4
Geotechnical Baseline Report applications
57
baseline parameters for consideration
62–63
baselines for smaller projects
58–59
effects on subcontractors and impact amplification
57
escrow bid documents
58
identification of risk factors
59–62
items to consider when developing baselines
60t–62t
Geotechnical Baseline Report development
49
engineer of record
49
GBR-B/C interactive option 1
51–52
GBR-B interactive option 2
52–53delivery alternatives
Geotechnical Baseline Report preparation
31
baseline parameters for engineering class
39f
baselines by tunnel reach
42–43
baseline statements examples
44t–45t
benefit of ground reference model
38–40
conservative baselines
48
consistency and compatibility
46–47
DBB delivery
40, 41
design-related parameters
41
formulating contents of GBRs
41
GBR outline and checklist
32t–34t
Geotechnical Baseline Report Authorship
42t
Geotechnical Design Summary Report
40
ground characterization table with baselines
36t–37t
link with Risk Registers
42
one piece of paper approach
35–38
organization and content
31
owner involvement
48
project type
38
quantitative baselines
47
selection of design parameters
40, 41
suggested outline
31–35
time and budget for preparation
47–48
wording suggestions
43–46
writing without ambiguity
43, 46
Geotechnical Data Report (GDR)
13
contractual hierarchy
15
Environmental Data Report
14
geotechnical baseline report
15
Geotechnical Interpretive Report
15
geotechnical memoranda for design
14–15
information in
13
Geotechnical Design Summary Report (GDSR)
3
Geotechnical Interpretive Report
15
Geotechnical Site Investigations for Underground Projects
2
ground reference model
38–40Geotechnical Baseline Report preparation
guaranteed maximum price (GMP)
54
Implied Warranty
78
International Federation of Consulting Engineers (FIDIC)
66
New Engineering Contract (NEC)
66
one piece of paper approach
35–38Geotechnical Baseline Report preparation
one-sided contracts
78
owner, the
71–72
owner's engineer
72–73responsibilities of parties
Port of Miami Tunnel Project
8
progressive design-build (PDB)
53–54delivery alternatives
Public–Private Partnership (P3)
55delivery alternatives
responsibilities of parties
71
construction manager, the
74
contractor, the
73
dispute adjudicator, the
74
owner's engineer
72–73
owner, the
71–72
Risk Registers
42Geotechnical Baseline Report preparation
standard clause
18Differing Site Condition clause
Standard Penetration Test (SPT)
24
Task Committee on Geotechnical Baseline Reports
4Geotechnical Baseline Report
tunnel boring machine (TBM)
22
unconfined compressive strength (UCS)
46
Underground Technology Research Council (UTRC)
2
US National Committee on Tunneling Technology (USNCTT)
1

Information & Authors

Information

Published In

Go to Geotechnical Baseline Reports
Geotechnical Baseline Reports: Suggested Guidelines
Pages: 87 - 90
Editor: Randall J. Essex
ISBN (Print): 978-0-7844-1608-2
ISBN (Online): 978-0-7844-8450-0

History

Published online: Dec 14, 2022
Published in print: Dec 22, 2022

Permissions

Request permissions for this article.

Authors

Metrics & Citations

Metrics

Citations

Download citation

If you have the appropriate software installed, you can download article citation data to the citation manager of your choice. Simply select your manager software from the list below and click Download.

View Options

Media

Figures

Other

Tables

Share

Share

Copy the content Link

Share with email

Email a colleague

Share