Timing and Severity of Cumulative Impact of Changes on Labor Productivity
Publication: Journal of Legal Affairs and Dispute Resolution in Engineering and Construction
Volume 15, Issue 1
Abstract
Cumulative impact of changes can be a factor impacting labor productivity. It is considered as the ripple effect of multiple changes. Because individual change orders for scope changes normally cover their direct effects, it is difficult to accurately predict the cumulative impacts and adequately capture them in the forward priced change orders. Though certain research on the timing of changes was done through statistical analyses, the timing of changes and the severity of their cumulative impact have not been rigorously defined mathematically. This paper presents a rigorous mathematical model defining the timing of changes and the severity of their cumulative impact, which is applied to the published data. Due to limited size of the published data, the numerical research remains conceptual. Through numerical analysis, this paper investigates how changes affected the labor productivity for the base scope work before, during, and after the performance of changed work, under the premise that cumulative impact of changes negatively impacted labor productivity. For various sections of a specific project, productivity losses due to cumulative impact of changes need to be assessed on a case-by-case basis in the light of the timing of changes.
Get full access to this article
View all available purchase options and get full access to this article.
Data Availability Statement
References
List of Cases
Acme Missiles & Construction Corp., 68–1 BCA ¶ 6873.
Bechtel National, Inc. NASA BCA No. 1186-7, 90-1 BCA ¶ 22,549
Centex Bateson Construction Co., VABCA Nos. 4613, 5162–5265, 99–1 BCA ¶ 30,153, 149,261.
Coastal Dry Dock & Repair Corp., ASBCA No. 36754, 91-1 BCA ¶ 23,324.
David J. Tierney, Jr., Inc., GSBCA Nos. 7107, 6198, 88-2 BCA ¶ 20,806.
Haas & Haynie Corp., GSBCA Nos. 5530, 6224, 6638, 6919–20, 84–2 BCA ¶ 17,446, 86,897.
Montgomery-Ross-Fisher, Inc., PSBCA Nos. 1033, 1096, 84-2 BCA ¶ 17,492.
Southwest Marine, Inc., DOTCAB No. 1663, 94-3 BCA ¶ 127,102.
Triple “A” South, ASBCA No. 46886, 94-3 BCA ¶ 27,194.
Works Cited
Hanna, A. S., and K. A. Iskandar. 2017. “Quantifying and modeling the cumulative impact of change orders.” J. Constr. Eng. Manage. 143 (10): 04017076. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001385.
Hanna, A. S., J. Russell, T. W. Gotzion, and E. V. Nordheim. 1999a. “Impact of change orders on labor efficiency for mechanical construction.” J. Constr. Eng. Manage. 125 (3): 176–184. https://doi.org/10.1061/(ASCE)0733-9364(1999)125:3(176).
Hanna, A. S., J. Russell, E. V. Nordheim, and M. Bruggink. 1999b. “Impact of change orders on labor efficiency for electrical construction.” J. Constr. Eng. Manage. 125 (4): 224–232. https://doi.org/10.1061/(ASCE)0733-9364(1999)125:4(224).
Ibbs, C. W. 1997. “Quantitative impacts of project change: Size issues.” J. Constr. Eng. Manage. 123 (3): 308–311. https://doi.org/10.1061/(ASCE)0733-9364(1997)123:3(308).
Ibbs, C. W. 2005. “Impact of change’s timing on labor productivity.” J. Constr. Eng. Manage. 131 (11): 1219–1223. https://doi.org/10.1061/(ASCE)0733-9364(2005)131:11(1219).
Ibbs, C. W. 2012. “Construction change: Likelihood, severity and impact on productivity.” J. Leg. Aff. Dispute Resolut. Eng. Constr. 4 (3): 67–73. https://doi.org/10.1061/(ASCE)LA.1943-4170.0000089.
Ibbs, C. W. 2021. “Update on quantitative analysis of change and loss of productivity.” J. Leg. Aff. Dispute Resolut. Eng. Constr. 13 (1): 02520002 https://doi.org/10.1061/(ASCE)LA.1943-4170.0000447.
Ibbs, C. W., and W. E. Allen. 1995. Quantitative impacts of project change. CII SD108. Austin, TX: CII.
Jones, R. M. 2001. “Lost productivity: Claims for cumulative impact of multiple change orders.” Public Contract Law J. 31 (1): 1–46.
Leonard, C. A. 1988. “The effects of change orders on productivity.” M.S. thesis, Dept. of Civil Engineering, Concordia Univ.
MCAA (Mechanical Contractors Association of America). 2016. Change orders, productivity, overtime: A primer for the construction industry. Rockville, MD: MCAA.
Zhao, T. 2021. “Modeling with functions for cumulative impact of changes.” J. Leg. Aff. Dispute Resolut. Eng. Constr. 13 (4): 04521029. https://doi.org/10.1061/(ASCE)LA.1943-4170.0000492.
Zhao, T., and J. M. Dungan. 2021. “Pilot investigation of underestimates: Likelihood, severity, and impact on productivity.” J. Leg. Aff. Dispute Resolut. Eng. Constr. 13 (4): 04521021. https://doi.org/10.1061/(ASCE)LA.1943-4170.0000488.
Information & Authors
Information
Published In
Copyright
© 2022 American Society of Civil Engineers.
History
Received: Jan 14, 2022
Accepted: Aug 12, 2022
Published online: Oct 22, 2022
Published in print: Feb 1, 2023
Discussion open until: Mar 22, 2023
ASCE Technical Topics:
- Analysis (by type)
- Business management
- Change management
- Change orders
- Construction engineering
- Construction management
- Employment
- Engineering fundamentals
- Labor
- Mathematics
- Numerical analysis
- Personnel management
- Practice and Profession
- Productivity
- Project management
- Regression analysis
- Statistical analysis (by type)
Authors
Metrics & Citations
Metrics
Citations
Download citation
If you have the appropriate software installed, you can download article citation data to the citation manager of your choice. Simply select your manager software from the list below and click Download.