Exploring Unit Cost Performance for Water Infrastructure Delivery
Publication: Practice Periodical on Structural Design and Construction
Volume 28, Issue 1
Abstract
Various delivery methods are used in the water industry for delivering treatment plant projects, which include the traditional design-bid-build (DBB) method as well as alternative project delivery methods (APDM), such as construction manager at risk (CMAR) and design-build (DB). Research has shown that APDM may improve water infrastructure project delivery performance when compared to DBB. However, utilizing an APDM does not guarantee a project’s successful delivery; other project variables also influence project delivery performance. The objective of this study is to develop exploratory mathematical models to investigate the impact of project-specific delivery factors and attributes on a water project’s success. The authors assess unit cost performance, which is a measure of a water treatment plant’s capacity in million gallons per day, over a project’s total cost. This study consisted of holding an industry expert workshop to review and develop a data collection questionnaire. Information on a total of 15 water treatment plant projects delivered in the US was collected and used to develop multiple linear regression models that explored project-specific key factors and attributes that impact unit cost performance. Results of the regression models revealed four critical variables: (1) use of GMP; (2) project team experience; (3) level of design completed before constructor engagement; and (4) project complexity, to have a statistically significant impact on the unit cost performance of water projects. The findings and contributions of this study can aid water stakeholders in understanding the unit cost performance impact of key project variables on their projects and support them in their project delivery method decisions.
Get full access to this article
View all available purchase options and get full access to this article.
Data Availability Statement
All data, models, and code generated or used during the study appear in the published article.
Acknowledgments
This work builds on a project funded by the Water Research Foundation (WRF) under Project No. 4685 “Project Delivery Performance Evaluation and Decision Support Tool for Water and Wastewater Capital Projects.” The authors would also like to thank all industry collaborators who have contributed to this research effort.
References
Abi Shdid, C., E. Andary, A. Chowdhury, and I. Ahmad. 2018. “Project performance rating model for water and wastewater treatment plant public projects.” J. Manage. Eng. 35 (2): 04018064. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000678.
Allen, L. N. 2001. “Comparison of design-build to design-bid-build as a project delivery method.” Master’s thesis, Naval Postgraduate School, US Navy.
ASCE. 2017. 2017 infrastructure report card. Reston, VA: ASCE.
AWWA (American Water Works Association). 2019. “2019 state of the water industry report.” Accessed January 8, 2020. https://www.awwa.org/Portals/0/AWWA/ETS/Resources/2019_STATE%20OF%20THE%20WATER%20INDUSTRY_post.pdf.
Bogus, S. M., J. S. Shane, and K. R. Molenaar. 2010. “Comparison of water/wastewater project performance by project delivery system and payment provision.” In Construction research congress 2010, 859–868. Reston, VA: ASCE. https://doi.org/10.1061/41109(373)86.
Chan, W. M. 1998. “Modeling construction durations for public housing projects in Hong Kong.” Ph.D. thesis, Dept. of Civil and Structural Engineering, Univ. of Hong Kong.
Creedy, G., M. Skitmore, and J. Wong. 2010. “Evaluation of risk factors leading to cost overrun in delivery of highway construction projects.” J. Constr. Eng. Manage. 136 (5): 528–537. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000160.
El Asmar, M., A. Hanna, and W. Loh. 2016. “Evaluating integrated project delivery using the project quarterback rating.” J. Constr. Eng. Manage. 142 (1): 04015046. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001015.
EPA (Environmental Protection Agency). 2018. “Drinking water infrastructure needs survey and assessment: Sixth report to congress.” Accessed January 8, 2020. https://www.epa.gov/sites/production/files/2018-10/documents/corrected_sixth_drinking_water_infrastructure_needs_survey_and_assessment.pdf.
Feghaly, J., M. El Asmar, and S. Ariaratnam. 2019. “Selecting project delivery methods for water treatment plants.” Eng. Constr. Archit. Manage. 27 (4): 936–951. https://doi.org/10.1108/ECAM-06-2019-0308.
Feghaly, J., M. El Asmar, and S. Ariaratnam. 2020a. “A comparison of project delivery method performance for water infrastructure capital projects.” Can. J. Civ. Eng. 48 (6): 691–701. https://doi.org/10.1139/cjce-2019-0508.
Feghaly, J., M. El Asmar, and S. Ariaratnam. 2020b. “State of professional practice for water infrastructure project delivery.” Pract. Period. Struct. Des. Constr. 25 (3): 04020018. https://doi.org/10.1061/(ASCE)SC.1943-5576.0000500.
Francom, T., M. El Asmar, and S. T. Ariaratnam. 2014. “Using alternative project delivery methods to enhance the cost performance of trenchless construction projects.” In ASCE construction research congress 2014: Construction in a global network, 1219–1228. Reston, VA: ASCE.
Francom, T., M. El Asmar, and S. T. Ariaratnam. 2016a. “Industry perceptions of alternative project delivery methods applied to trenchless pipeline projects.” J. Pipeline Syst. Eng. Pract. 7 (1): 04015020. https://doi.org/10.1061/(ASCE)PS.1949-1204.0000220.
Francom, T., M. El Asmar, and S. T. Ariaratnam. 2016b. “Performance analysis of construction manager at risk on pipeline engineering and construction projects.” J. Manage. Eng. 32 (6): 0404016016. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000456.
Franz, B., K. Molenaar, and B. Roberts. 2020. “Revisiting project delivery system performance from 1998 to 2018.” J. Constr. Eng. Manage. 146 (9): 04020100. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001896.
Hale, D. R., P. P. Shrestha, G. E. Gibson Jr., and G. C. Migliaccio. 2009. “Empirical comparison of design/build and design/bid/build project delivery methods.” J. Constr. Eng. Manage. 135 (7): 579–587. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000017.
Hodges, J. S. 1991. “Six (or so) things you can do with a bad model.” Oper. Res. 39 (3): 355–365. https://doi.org/10.1287/opre.39.3.355.
Ji, S., M. Park, and H. Lee. 2010. “Data preprocessing–based parametric cost model for building projects: Case studies of Korean construction.” J. Constr. Eng. Manage. 136 (8): 844–853. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000197.
Konchar, M., and V. Sanvido. 1998. “Comparison of US and UK project delivery systems.” J. Constr. Eng. 124 (6): 435–444.
Ling, F., S. Chan, E. Chong, and L. Ee. 2004. “Predicting performance of design-build and design-bid-build projects.” J. Constr. Eng. Manage. 130 (1): 75–83. https://doi.org/10.1061/(ASCE)0733-9364(2004)130:1(75).
Mafakheri, F., L. Dai, D. Slezak, and F. Nasiri. 2007. “Project delivery system selection under uncertainty: Multicriteria multilevel decision aid model.” J. Manage. Eng. 23 (4): 200–206. https://doi.org/10.1061/(ASCE)0742-597X(2007)23:4(200).
Migliaccio, G. C., S. Bogus, and A. Chen. 2010. “Effect of duration of design-build procurement on performance of transportation projects.” Transp. Res. Rec. 2151 (1): 67–73. https://doi.org/10.3141/2151-09.
Molenaar, K., and A. Songer. 1998. “Model for public sector design-build project selection.” J. Constr. Eng. Manage. 124 (6): 467–479. https://doi.org/10.1061/(ASCE)0733-9364(1998)124:6(467).
Mollaoglu-Korkmaz, S., L. Swarup, and D. Riley. 2013. “Delivering sustainable, high-performance buildings: Influence of project delivery methods on integration and project outcomes.” J. Manage. Eng. 29 (1): 71–78. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000114.
Neter, J., W. Wasserman, and M. H. Kutner. 1990. Applied linear statistical models. 3rd ed. Homewood, IL: McGraw-Hill Irwin.
Nulty, D. D. 2008. “The adequacy of response rates to online and paper surveys: What can be done?” Assess. Eval. Higher Educ. 33 (3): 301–314. https://doi.org/10.1080/02602930701293231.
Rosner, J. W., A. E. Thal, and C. J. West. 2009. “Analysis of design-build delivery method in air force construction projects.” J. Constr. Eng. Manage. 135 (8): 710–717. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000029.
Shane, J., S. Bogus, and K. R. Molenaar. 2013. “Municipal water/wastewater project delivery performance comparison.” J. Manag. Eng. 29 (3): 251–258. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000139.
Shrestha, P., G. Migliaccio, J. O’Connor, and G. Gibson Jr. 2007. “Benchmarking of large design-build highway projects.” Transp. Res. Rec. 1994 (1): 17–25. https://doi.org/10.3141/1994-03.
Shrestha, P., J. O’Connor, and G. Gibson Jr. 2012. “Performance comparison of large design-build and design-bid-build highway projects.” J. Constr. Eng. Manage. 138 (1): 1–13. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000390.
Shrestha, P. P., R. Maharajan, and J. R. Batista. 2018. “Performance of design-build and construction manager-at-risk methods in water and wastewater projects.” Pract. Period. Struct. Des. Constr. 24 (1): 040189029. https://doi.org/10.1061/(ASCE)SC.1943-5576.0000415.
Sullivan, J., M. El Asmar, J. Chalhoub, and H. Obeid. 2017. “Two decades of performance comparisons for design-build, construction manager at risk, and design-bid-build: Quantitative analysis of the state of knowledge on project cost, schedule, and quality.” J. Constr. Eng. Manage. 143 (6): 04017009. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001282.
Touran, A., D. Gransberg, K. Molenaar, and K. Ghavamifar. 2011. “Selection of project delivery method in transit: Drivers and objectives.” J. Manage. Eng. 27 (1): 21–27. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000027.
Tran, D., K. Molenaar, and L. Alarcon. 2016. “A hybrid cross-impact approach to predicting cost variance of project delivery decisions for highways.” J. Infrastruct. Syst. 22 (1): 04015017. https://doi.org/10.1061/(ASCE)IS.1943-555X.0000270.
United States Bureau of Labor. 2020. “Statistics: Consumer price index.” Accessed February 10, 2020. https://www.bls.gov/cpi/.
USACE (United States Army Corps of Engineers). 2018. “DOD area cost factor (ACF) PAX.” Accessed February 10, 2020. https://usace.contentdm.oclc.org/digital/collection/p16021coll8/id/3846.
VWC (Value of Water Campaign). 2017. “The economic benefits of investing in water infrastructure.” Accessed March 10, 2020. https://thevalueofwater.org/sites/default/files/Fact%20Sheet_Economic%20Impact%20of%20Investing%20in%20Water%20Infrastructure%20FINAL.pdf.
Xu, J., and S. Moon. 2013. “Stochastic forecast of construction cost index using a cointegrated vector autoregression model.” J. Manage. Eng. 29 (1): 10–18. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000112.
Yoo, W., R. Mayberry, S. Bae, K. Singh, Q. He, and J. Lillard. 2014. “A study of effects of multicollinearity in the multivariable analysis.” Int. J. Appl. Sci. Technol. 4 (5): 9–19.
Information & Authors
Information
Published In
Copyright
© 2022 American Society of Civil Engineers.
History
Received: Nov 16, 2021
Accepted: Aug 19, 2022
Published online: Nov 7, 2022
Published in print: Feb 1, 2023
Discussion open until: Apr 7, 2023
ASCE Technical Topics:
- Analysis (by type)
- Construction costs
- Construction engineering
- Construction management
- Construction methods
- Data collection
- Design-bid-build
- Engineering fundamentals
- Environmental engineering
- Methodology (by type)
- Project delivery
- Project management
- Regression analysis
- Research methods (by type)
- Statistical analysis (by type)
- Water treatment
- Water treatment plants
Authors
Metrics & Citations
Metrics
Citations
Download citation
If you have the appropriate software installed, you can download article citation data to the citation manager of your choice. Simply select your manager software from the list below and click Download.