Decision-Aid Frameworks for Earned Value Measurement or Assessment by the Construction Contract Engineer

Publication: Journal of Legal Affairs and Dispute Resolution in Engineering and Construction
Volume 13, Issue 3

Abstract

Construction project controls is a process that is concerned with attempting to complete the contracted works within the allocated time frame and the preagreed budget, all in accordance with the set quality standards. To this end, the earned value management (EVM) method is recognized as a well-established technique offering an integrated approach for the efficient monitoring and controlling of the project’s cost and schedule targets during the course of execution. That said, this research aimed at investigating several decision-aid frameworks that can systematically guide the construction contract engineer in making the EVM tool better accustomed and suited for exercising project control and administrating construction contracts, while making use of and benefiting from the enhanced capabilities of the technique that are widely spread in the archived literature. To this effect, the adopted multistep methodology included (1) the verification of the degree of importance of project controls in relation to project success, (2) the classification of the shortcomings reported to be encumbering EVM’s employability as a project controls tool, and (3) the compilation and synthesis of the encountered improvements. The main research outcomes further involved developing several EVM-based frameworks, which shall be of value to the engineer, through stipulating an integrated set of methods and metrics used for (1) checking the analytical schedule-based S-curve submitted by the contractor, (2) dealing with interim payment valuations and certifications, and (3) forecasting and updating the remaining duration for the construction project on hand. Finally, the related requirements to be met by contractors and the types of authority to be entrusted with the engineer are summarized for facilitating the employability of the proposed frameworks, thereby potentially minimizing the likelihood of conflicts and disputes to arise between owners and contractors on construction projects.

Get full access to this article

View all available purchase options and get full access to this article.

Data Availability Statement

Some or all data, models, or code generated or used during the study are proprietary or confidential in nature and may only be provided with restrictions. These data are related to the actual payment certification records pertaining to the project cases used in the study. Restrictions apply to the names of the projects and the identities of key participants.

Acknowledgments

The authors would like to acknowledge the generous endowed doctoral research funding granted by the Maroun Semaan Faculty of Engineering and Architecture at the American University of Beirut in support of this research.

References

Works Cited

Abba, W. 2000. “How earned value got to primetime: A short look back and a glance ahead.” In Proc., Project Management Institute Seminars and Symp. Newtown Square, PA: Project Management Institute.
Abdul-Malak, M.-A., and L. Naeem. 2018. “Detriments of meddling with the engineer’s claims-related contract administration roles.” In Proc., Construction Research Congress 2018, 207–216. Reston, VA: ASCE. https://doi.org/10.1061/9780784481271.021.
Abdul-Malak, M.-A. U., S. Bou Hamdan, and F. S. Demachkieh. 2020. “Enhanced roles and traits of the engineer in assessing claims.” J. Leg. Aff. Dispute Resolut. Eng. Constr. 12 (3): 04520019. https://doi.org/10.1061/(ASCE)LA.1943-4170.0000398.
Abdul-Rahman, H., M. Kho, and C. Wang. 2013. “Late payment and nonpayment encountered by contracting firms in a fast-developing economy.” J. Civ. Eng. Educ. 140 (2): 04013013. https://doi.org/10.1061/(ASCE)EI.1943-5541.0000189.
Abotaleb, I. S., and I. H. El-adaway. 2017. “Administering employers’ payment obligations under national and international design–build standard forms of contract.” J. Leg. Aff. Dispute Resolut. Eng. Constr. 9 (2): 04517003. https://doi.org/10.1061/(ASCE)LA.1943-4170.0000213.
Adriaanse, M. J. 2016. Construction contract law. London: Macmillan International Higher Education.
Aliverdi, R., L. M. Naeni, and A. Salehipour. 2013. “Monitoring project duration and cost in a construction project by applying statistical quality control charts.” Int. J. Project Manage. 31 (3): 411–423. https://doi.org/10.1016/j.ijproman.2012.08.005.
Amos, S. J. 2004. Skills and knowledge of cost engineering. Morgantown, WV: AACE International.
Anantatmula, V. S. 2015. “Strategies for enhancing project performance.” J. Manage. Eng. 31 (6): 04015013. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000369.
Anbari, F. T. 2003. “Earned value project management method and extensions.” Project Manage. J. 34 (4): 12–23. https://doi.org/10.1177/875697280303400403.
Ashley, D. B., C. S. Lurie, and E. J. Jaselskis. 1987. Determinants of construction project success. Newtown Square, PA: Project Management Institute.
Askew, W., M. O’Reilly, and M. Mawdesley. 1997. Planning and controlling construction projects: The best laid plans. London: Longman.
Babar, S., M. J. Thaheem, and B. Ayub. 2016. “Estimated cost at completion: Integrating risk into earned value management.” J. Constr. Eng. Manage. 143 (3): 04016104. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001245.
Babatunde, S. O., S. Perera, L. Zhou, C. E. Udeaja, M. Kumaraswamy, and P. Lam. 2016. “Stakeholder perceptions on critical success factors for public-private partnership projects in Nigeria.” Built Environ. Project Asset Manage. 6 (1): 74–91. https://doi.org/10.1108/BEPAM-11-2014-0061.
Balkau, B. 1975. “A financial model for public works programmes.” In Proc., National ASOR Conf., 25–27. Alexandria, VA: American Society of Overseas Research.
Barraza, G. A., W. E. Back, and F. Mata. 2000. “Probabilistic monitoring of project performance using SS-curves.” J. Constr. Eng. Manage. 126 (2): 142–148. https://doi.org/10.1061/(ASCE)0733-9364(2000)126:2(142).
Barraza, G. A., W. E. Back, and F. Mata. 2004. “Probabilistic forecasting of project performance using stochastic S curves.” J. Constr. Eng. Manage. 130 (1): 25–32. https://doi.org/10.1061/(ASCE)0733-9364(2004)130:1(25).
Barraza, G. A., and R. A. Bueno. 2007. “Probabilistic control of project performance using control limit curves.” J. Constr. Eng. Manage. 133 (12): 957–965. https://doi.org/10.1061/(ASCE)0733-9364(2007)133:12(957).
Batselier, J., and M. Vanhoucke. 2015. “Evaluation of deterministic state-of-the-art forecasting approaches for project duration based on earned value management.” Int. J. Project Manage. 33 (7): 1588–1596. https://doi.org/10.1016/j.ijproman.2015.04.003.
Blyth, K., and A. Kaka. 2006. “A novel multiple linear regression model for forecasting S-curves.” Eng. Constr. Archit. Manage. 13 (1): 82–95. https://doi.org/10.1108/09699980610646511.
Booen, P. L. 2000. The FIDIC contracts guide. Geneva: Federation Internationale Des Ingineurs Conseile.
Bromilow, F., and J. Henderson. 1977. Procedures for reckoning and valuing the performance of building contracts. Canberra, Australia: Division of Building Research, Commonwealth Scientific and Industrial Research Organisation.
Bunni, N. G. 2013. The FIDIC forms of contract. New York: Wiley.
Caron, F., F. Ruggeri, and B. Pierini. 2016. “A Bayesian approach to improving estimate to complete.” Int. J. Project Manage. 34 (8): 1687–1702. https://doi.org/10.1016/j.ijproman.2016.09.007.
Chan, E. H., and H. C. Suen. 2005. “Dispute resolution management for international construction projects in China.” Manage. Decis. 43 (4): 589–602. https://doi.org/10.1108/00251740510593576.
Chang, C.-J., and S.-W. Yu. 2018. “Three-variance approach for updating earned value management.” J. Constr. Eng. Manage. 144 (6): 04018045. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001491.
Changali, S., A. Mohammad, and M. van Nieuwland. 2015. “The construction productivity imperative.” In How to build megaprojects better. Melbourne, Australia: Analysis & Policy Observatory.
Chao, L.-C., and H.-T. Chen. 2015. “Predicting project progress via estimation of S-curve’s key geometric feature values.” Autom. Constr. 57 (Sep): 33–41. https://doi.org/10.1016/j.autcon.2015.04.015.
Chao, L.-C., and C.-F. Chien. 2009. “Estimating project S-curves using polynomial function and neural networks.” J. Constr. Eng. Manage. 135 (3): 169–177. https://doi.org/10.1061/(ASCE)0733-9364(2009)135:3(169).
Chao, L.-C., and C.-F. Chien. 2010. “A model for updating project S-curve by using neural networks and matching progress.” Autom. Constr. 19 (1): 84–91. https://doi.org/10.1016/j.autcon.2009.09.006.
Chen, H.-L., and W.-T. Chen. 2000. “An interactive cost-schedule/payment schedule prototype integration model for cost-flow forecasting and controlling.” In Proc., 17th Int. Association for Automation and Robotics in Construction. London: International Association for Automation and Robotics in Construction.
Cheung, S. O., and T. W. Yiu. 2006. “Are construction disputes inevitable?” IEEE Trans. Eng. Manage. 53 (3): 456–470. https://doi.org/10.1109/TEM.2006.877445.
Chipulu, M., U. Ojiako, P. Gardiner, T. Williams, C. Mota, S. Maguire, Y. Shou, T. Stamati, and A. Marshall. 2014. “Exploring the impact of cultural values on project performance: The effects of cultural values, age and gender on the perceived importance of project success/failure factors.” Int. J. Oper. Prod. Manage. 34 (3): 364–389. https://doi.org/10.1108/IJOPM-04-2012-0156.
Christensen, D. S. 1998. “The costs and benefits of the earned value management process.” J. Parametrics 18 (2): 1–16. https://doi.org/10.1080/10157891.1998.10462568.
CII (Construction Industry Institute). 2012. Performance assessment. Austin, TX: CII.
Cioffi, D. F. 2005. “A tool for managing projects: An analytic parameterization of the S-curve.” Int. J. Project Manage. 23 (3): 215–222. https://doi.org/10.1016/j.ijproman.2004.08.001.
Cioffi, D. F. 2006. “Completing projects according to plans: An earned-value improvement index.” J. Oper. Res. Soc. 57 (3): 290–295. https://doi.org/10.1057/palgrave.jors.2602007.
Cooke-Davies, T. 2002. “The ‘real’ success factors on projects.” Int. J. Project Manage. 20 (3): 185–190. https://doi.org/10.1016/S0263-7863(01)00067-9.
Demachkieh, F., and M.-A. U. Abdul-Malak. 2018a. “Degree of criticality of monitoring and control to project success.” In Proc., Construction Research Congress, 389–398. Reston, VA: ASCE. https://doi.org/10.1061/9780784481271.038.
Demachkieh, F., and M.-A. U. Abdul-Malak. 2018b. “Synthesis of improvements to EVMS key parameters representation.” In Proc., Construction Research Congress, 399–408. Reston, VA: ASCE. https://doi.org/10.1061/9780784481271.039.
Demachkieh, F., and M.-A. U. Abdul-Malak. 2019b. “Comparative analyses of construction cash flow predictions using empirical S-curves.” In Proc., 2019 AACE Int. Transactions, EVM-3272. Morgantown, WV: American Association of Cost Engineers (AACE).
Demachkieh, F., and M.-A. U. Abdul-Malak. 2019c. “Emergent EVM techniques for construction schedule performance measurement and control.” In Proc., 2019 AACE Int. Transactions, EVM-3271. Morgantown, WV: American Association of Cost Engineers (AACE).
Demachkieh, F. S., and M.-A. U. Abdul-Malak. 2019a. “Administration of construction contract interim payments based on earned-value reduction techniques.” J. Leg. Aff. Dispute Resolut. Eng. Constr. 11 (4): 04519023. https://doi.org/10.1061/(ASCE)LA.1943-4170.0000309.
Dodson, M., G. Defavari, and V. de Carvalho. 2015. “Quality: The third element of earned value management.” Procedia Comput. Sci. 64: 932–939. https://doi.org/10.1016/j.procs.2015.08.610.
Dvir, D., and T. Lechler. 2004. “Plans are nothing, changing plans is everything: The impact of changes on project success.” Res. Policy 33 (1): 1–15. https://doi.org/10.1016/j.respol.2003.04.001.
El-adaway, I. H., S. A. Fawzy, K. Cody, S. Fast, G. Spencer, D. Bond, D. Cushman, and T. Stieffel. 2013. “Contract administration guidelines for contractors working under AIA A201-2007 contract for construction.” J. Leg. Aff. Dispute Resolut. Eng. Constr. 6 (1): 03013002. https://doi.org/10.1061/(ASCE)LA.1943-4170.0000131.
Elshaer, R. 2013. “Impact of sensitivity information on the prediction of project’s duration using earned schedule method.” Int. J. Project Manage. 31 (4): 579–588. https://doi.org/10.1016/j.ijproman.2012.10.006.
Evans, R., A. Kaka, and J. Lewis. 1996. “Development of a computer based model to assist contractors to plan, forecast and control cash flow.” In Proc., ARCOM: Proc., 12th Annual Conf. and Annual General Meeting, 556–565. Edinburgh, UK: Heriot Watt Univ.
Fawzy, S. A., and I. H. El-adaway. 2011. “Contract administration guidelines for US contractors working under World Bank–funded projects.” J. Leg. Aff. Dispute Resolut. Eng. Constr. 4 (2): 40–50. https://doi.org/10.1061/(ASCE)LA.1943-4170.0000088.
FIDIC (International Federation for Consulting Engineers). 1999. Conditions of contract for construction. 1st ed. Geneva: Thomas Telford.
Fleming, Q. W., and J. M. Koppelman. 2003. “What’s your project’s real price tag?” Harv. Bus. Rev. 81 (9): 20.
Fleming, Q. W., and J. M. Koppelman. 2006. “Earned value project management a powerful tool for software projects.” Software Manage. 16: 337.
Forouzanpour, H., A. Mirzazadeh, and S. Nodoust. 2016. “An evidential reasoning approach for the earned value management.” Sci. Iran. 23 (2): 685.
Görög, M. 2009. “A comprehensive model for planning and controlling contractor cash-flow.” Int. J. Project Manage. 27 (5): 481–492. https://doi.org/10.1016/j.ijproman.2008.08.001.
Hernández, J. I. M., J. R. O. Olaso, and J. R. Gómez. 2013. Technical performance based earned value as a management tool for engineering projects. London: Intech.
Hinze, J. 2001. Construction contracts. New York: McGraw-Hill.
Jacob, D. 2003. “Forecasting project schedule completion with earned value metrics.” Measurable News 1 (11): 7–9.
Jacob, D., and M. Kane. 2004. “Forecasting schedule completion using earned value metrics revisited.” Measurable News 1 (11): 7.
Kaka, A. P., and A. D. Price. 1991. “Net cashflow models: Are they reliable?” Constr. Manage. Econ. 9 (3): 291–308. https://doi.org/10.1080/01446199100000023.
Kaka, A. P. F. 1990. Corporate financial model for construction contractors. Ph.D. dissertation, School of Architecture, Building and Civil Engineering, Loughborough Univ.
Kalach, M., M.-A. Abdul-Malak, and I. Srour. 2019a. “Architect and engineer’s spectrum of engagement under alternative delivery methods: Agreement negotiation and formation implications.” J. Leg. Aff. Dispute Resolut. Eng. Constr. 12 (1): 04519048. https://doi.org/10.1061/(ASCE)LA.1943-4170.0000360.
Kalach, M., M.-A. Abdul-Malak, and I. Srour. 2019b. “Liability exposure and indemnity for architecture and engineering professionals acting as independent consultants or design subcontractors.” J. Leg. Aff. Dispute Resolut. Eng. Constr. 11 (4): 04519019. https://doi.org/10.1061/(ASCE)LA.1943-4170.0000306.
Kartam, N. A., and S. A. Kartam. 2001. “Risk and its management in the Kuwaiti construction industry: A contractors’ perspective.” Int. J. Project Manage. 19 (6): 325–335. https://doi.org/10.1016/S0263-7863(00)00014-4.
Kenley, R., and O. D. Wilson. 1986. “A construction project cash flow model—An idiographic approach.” Constr. Manage. Econ. 4 (3): 213–232. https://doi.org/10.1080/01446198600000017.
Kennedy, P. 2006. “Progress of statutory adjudication as a means of resolving disputes in construction in the United Kingdom.” J. Civ. Eng. Educ. 132 (3): 236–247. https://doi.org/10.1061/(ASCE)1052-3928(2006)132:3(236).
Kerzner, H. R. 2013. Project management: A systems approach to planning, scheduling, and controlling. New York: Wiley.
Khamooshi, H., and A. Abdi. 2016. “Project duration forecasting using earned duration management with exponential smoothing techniques.” J. Manage. Eng. 33 (1): 04016032. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000475.
Khamooshi, H., and H. Golafshani. 2014. “EDM: Earned duration management, a new approach to schedule performance management and measurement.” Int. J. Project Manage. 32 (6): 1019–1041. https://doi.org/10.1016/j.ijproman.2013.11.002.
Khosrowshahi, F., and A. Kaka. 2007. “A decision support model for construction cash flow management.” Comput.-Aided Civ. Infrastruct. Eng. 22 (7): 527–539. https://doi.org/10.1111/j.1467-8667.2007.00508.x.
Kim, B.-C. 2014. “Dynamic control thresholds for consistent earned value analysis and reliable early warning.” J. Manage. Eng. 31 (5): 04014077. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000309.
Kim, B.-C., and H.-J. Kim. 2014. “Sensitivity of earned value schedule forecasting to S-curve patterns.” J. Constr. Eng. Manage. 140 (7): 04014023. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000856.
Kim, B.-C., and K. F. Reinschmidt. 2010. “Probabilistic forecasting of project duration using Kalman filter and the earned value method.” J. Constr. Eng. Manage. 136 (8): 834–843. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000192.
Kim, E., W. G. Wells, and M. R. Duffey. 2003. “A model for effective implementation of Earned Value Management methodology.” Int. J. Project Manage. 21 (5): 375–382. https://doi.org/10.1016/S0263-7863(02)00049-2.
Kim, T., Y.-W. Kim, and H. Cho. 2015. “Customer earned value: Performance indicator from flow and value generation view.” J. Manage. Eng. 32 (1): 04015017. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000377.
Kwak, Y. H., and F. T. Anbari. 2012. “History, practices, and future of earned value management in government: Perspectives from NASA.” Project Manage. J. 43 (1): 77–90. https://doi.org/10.1002/pmj.20272.
Lipke, W. 2003. “Schedule is different.” Measurable News 31 (4): 31–34.
Lipke, W. 2004. “Connecting earned value to the schedule.” Measurable News 1 (4): 6–16.
Maravas, A., and J.-P. Pantouvakis. 2012. “Project cash flow analysis in the presence of uncertainty in activity duration and cost.” Int. J. Project Manage. 30 (3): 374–384. https://doi.org/10.1016/j.ijproman.2011.08.005.
Mavrotas, G., Y. Caloghirou, and J. Koune. 2005. “A model on cash flow forecasting and early warning for multi-project programmes: Application to the Operational Programme for the Information Society in Greece.” Int. J. Project Manage. 23 (2): 121–133. https://doi.org/10.1016/j.ijproman.2004.07.009.
Miskawi, Z. 1989. “An S-curve equation for project control.” Constr. Manage. Econ. 7 (2): 115–124. https://doi.org/10.1080/01446198900000016.
Moradi, N., S. M. Mousavi, and B. Vahdani. 2017. “An earned value model with risk analysis for project management under uncertain conditions.” J. Intell. Fuzzy Syst. 32 (1): 97–113. https://doi.org/10.3233/JIFS-151139.
Morin, J. 2009. “How it all began. The creation of earned value and the evolution of C/SPCS and C/SCSC.” PM World Today 11 (12): 1–8.
Moslemi-Naeni, L., and A. Salehipour. 2011. “Evaluating fuzzy earned value indices and estimates by applying alpha cuts.” Expert Syst. Appl. 38 (7): 8193–8198.
Naeni, L. M., S. Shadrokh, and A. Salehipour. 2014. “A fuzzy approach for the earned value management.” Int. J. Project Manage. 32 (4): 709–716. https://doi.org/10.1016/j.ijproman.2013.02.002.
Najafi, A., and F. Azimi. 2016. “An extension of the earned value management to improve the accuracy of schedule analysis results.” Iran. J. Manage. Stud. 9 (1): 63.
Odeyinka, H. A., J. Lowe, and A. Kaka. 2008. “An evaluation of risk factors impacting construction cash flow forecast.” J. Financ. Manage. Property Constr. 13 (1): 5–17. https://doi.org/10.1108/13664380810882048.
Omopariola, E. D., A. Windapo, D. J. Edwards, and W. D. Thwala. 2019. “Contractors’ perceptions of the effects of cash flow on construction projects.” J. Eng. Des. Technol. 18 (2): 308–325.
Orgut, R. E., M. Batouli, J. Zhu, A. Mostafavi, and E. J. Jaselskis. 2019. “Critical factors for improving reliability of project control metrics throughout project life cycle.” J. Manage. Eng. 36 (1): 04019033. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000710.
Paquin, J. P., J. Couillard, and D. J. Ferrand. 2000. “Assessing and controlling the quality of a project end product: The earned quality method.” IEEE Trans. Eng. Manage. 47 (1): 88–97. https://doi.org/10.1109/17.820728.
Park, H. K., S. H. Han, and J. S. Russell. 2005. “Cash flow forecasting model for general contractors using moving weights of cost categories.” J. Manage. Eng. 21 (4): 164–172. https://doi.org/10.1061/(ASCE)0742-597X(2005)21:4(164).
Picornell, M., E. Pellicer, C. Torres-Machí, and M. Sutrisna. 2016. “Implementation of earned value management in unit-price payment contracts.” J. Manage. Eng. 33 (3): 06016001. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000500.
PMI (Project Management Institute). 2011. Practice standard for earned value management. Newtown Square, PA: PMI.
PMI (Project Management Institute). 2018. A guide to the project management body of knowledge (PMBOK guide). Newtown Square, PA: PMI.
Ponz-Tienda, J. L., E. Pellicer, and V. Yepes. 2012. “Complete fuzzy scheduling and fuzzy earned value management in construction projects.” J. Zhejiang Univ. Sci. A 13 (1): 56–68. https://doi.org/10.1631/jzus.A1100160.
Ramachandra, T., and J. O. B. Rotimi. 2014. “Mitigating payment problems in the construction industry through analysis of construction payment disputes.” J. Leg. Aff. Dispute Resolut. Eng. Constr. 7 (1): A4514005. https://doi.org/10.1061/(ASCE)LA.1943-4170.0000156.
Samer Ezeldin, A., and G. G. Ali. 2017. “Cash flow optimization for construction portfolios.” In Proc., Int. Conf. on Sustainable Infrastructure 2017, 26–37. Reston, VA: ASCE. https://doi.org/10.1061/9780784481202.003.
San Cristóbal, J. 2017. “The S-curve envelope as a tool for monitoring and control of projects.” Procedia Comput. Sci. 121: 756–761. https://doi.org/10.1016/j.procs.2017.11.097.
Seifert, B. M. 2005. “International construction dispute adjudication under International Federation of Consulting Engineers conditions of contract and the Dispute Adjudication Board.” J. Civ. Eng. Educ. 131 (2): 149–157. https://doi.org/10.1061/(ASCE)1052-3928(2005)131:2(149).
Stein, S. G. M., and R. Hiss. 2003. “Here comes the judge—Duties and responsibilities of design professionals when deciding disputes.” J. Civ. Eng. Educ. 129 (3): 177–183. https://doi.org/10.1061/(ASCE)1052-3928(2003)129:3(177).
Thamhain, H. J. 1998. “Integrating project management tools with the project team.” In Proc., 29th Annual PMI Seminars and Symp. Newtown Square, PA: Project Management Institute.
Toor, S.-U.-R., and S. O. Ogunlana. 2009. “Construction professionals’ perception of critical success factors for large-scale construction projects.” Constr. Innovation 9 (2): 149–167. https://doi.org/10.1108/14714170910950803.
Torp, O., K. Austeng, and J. M. Wubishet. 2004. Critical success factors for project performance: A study from front-end assessments of large public projects in Norway. Gløshaugen, Norway: Norwegian Univ. of Science and Technology.
Vanhoucke, M. 2012. “Dynamic scheduling: Integrating schedule risk analysis with earned value management.” Measurable News 2: 11–13.
Vargas, R. V. 2003. “Earned value analysis in the control of projects: Success or failure?” AACE Int. Trans. 21 (4): 211–214.
Wai, S., A. M. Yusof, S. Ismail, and C. Ng. 2013. “Exploring success factors of social infrastructure projects in Malaysia.” Int. J. Eng. Bus. Manage. 5 (1): 1.
Wauters, M., and M. Vanhoucke. 2014. “Support vector machine regression for project control forecasting.” Autom. Constr. 47 (Nov): 92–106. https://doi.org/10.1016/j.autcon.2014.07.014.
West, S., and S. McElroy. 2001. “EVMS: A managerial tool vs. a reporting tool.” In Proc., Nashville: 32nd Annual Project Management Institute Seminars and Symp., 12–16. Newtown Square, PA: Project Management Institute.
Wideman, R. M. 1995. Cost control of capital projects and the project cost management system requirements: A handbook for owners, architects, engineers, and all those involved in project management of constructed facilities, AEW services. Richmond, BC, Canada: BiTech.
Williams, T. 2003. “Assessing extension of time delays on major projects.” Int. J. Project Manage. 21 (1): 19–26. https://doi.org/10.1016/S0263-7863(01)00060-6.
Williams, T. 2005. “Assessing and moving on from the dominant project management discourse in the light of project overruns.” IEEE Trans. Eng. Manage. 52 (4): 497–508. https://doi.org/10.1109/TEM.2005.856572.
Williams, T. M. 2013. Managing and modelling complex projects. New York: Springer.
Wood, D. A. 2016. “High-level integrated deterministic, stochastic and fuzzy cost-duration analysis aids project planning and monitoring, focusing on uncertainties and earned value metrics.” J. Nat. Gas Sci. Eng. 37 (Jan): 303–326. https://doi.org/10.1016/j.jngse.2016.11.045.
Zhong, S., and X. Wang. 2011. “Improvement and application of earned value analysis in coal project management.” Procedia Eng. 26 (18): 1983–1989. https://doi.org/10.1016/j.proeng.2011.11.2394.

Information & Authors

Information

Published In

Go to Journal of Legal Affairs and Dispute Resolution in Engineering and Construction
Journal of Legal Affairs and Dispute Resolution in Engineering and Construction
Volume 13Issue 3August 2021

History

Received: Oct 30, 2020
Accepted: Mar 8, 2021
Published online: May 6, 2021
Published in print: Aug 1, 2021
Discussion open until: Oct 6, 2021

Permissions

Request permissions for this article.

ASCE Technical Topics:

Authors

Affiliations

Lecturer, Dept. of Civil and Environmental Engineering, Maroun Semaan Faculty of Engineering and Architecture, American Univ. of Beirut, Bechtel Engineering Bldg., Beirut 1107 2020, Lebanon. ORCID: https://orcid.org/0000-0001-9105-2495. Email: [email protected]
Professor of Construction Engineering and Management, Dept. of Civil and Environmental Engineering, Maroun Semaan Faculty of Engineering and Architecture, American Univ. of Beirut, Bechtel Engineering Bldg., Beirut 1107 2020, Lebanon (corresponding author). ORCID: https://orcid.org/0000-0003-3382-2257. Email: [email protected]

Metrics & Citations

Metrics

Citations

Download citation

If you have the appropriate software installed, you can download article citation data to the citation manager of your choice. Simply select your manager software from the list below and click Download.

View Options

Get Access

Access content

Please select your options to get access

Log in/Register Log in via your institution (Shibboleth)
ASCE Members: Please log in to see member pricing

Purchase

Save for later Information on ASCE Library Cards
ASCE Library Cards let you download journal articles, proceedings papers, and available book chapters across the entire ASCE Library platform. ASCE Library Cards remain active for 24 months or until all downloads are used. Note: This content will be debited as one download at time of checkout.

Terms of Use: ASCE Library Cards are for individual, personal use only. Reselling, republishing, or forwarding the materials to libraries or reading rooms is prohibited.
ASCE Library Card (5 downloads)
$105.00
Add to cart
ASCE Library Card (20 downloads)
$280.00
Add to cart
Buy Single Article
$35.00
Add to cart

Get Access

Access content

Please select your options to get access

Log in/Register Log in via your institution (Shibboleth)
ASCE Members: Please log in to see member pricing

Purchase

Save for later Information on ASCE Library Cards
ASCE Library Cards let you download journal articles, proceedings papers, and available book chapters across the entire ASCE Library platform. ASCE Library Cards remain active for 24 months or until all downloads are used. Note: This content will be debited as one download at time of checkout.

Terms of Use: ASCE Library Cards are for individual, personal use only. Reselling, republishing, or forwarding the materials to libraries or reading rooms is prohibited.
ASCE Library Card (5 downloads)
$105.00
Add to cart
ASCE Library Card (20 downloads)
$280.00
Add to cart
Buy Single Article
$35.00
Add to cart

Media

Figures

Other

Tables

Share

Share

Copy the content Link

Share with email

Email a colleague

Share