Adopting BIM to Facilitate Dispute Management in the Construction Industry: A Conceptual Framework Development

Publication: Journal of Construction Engineering and Management
Volume 149, Issue 1

Abstract

Previous studies revealed that Building Information Modeling (BIM) has the potential to reduce project uncertainties, design errors, change orders, and delays, which might facilitate achieving effective dispute management in the construction industry. However, research into the adoption of BIM to holistically enhance effective dispute management is limited compared with the plentiful BIM research in the construction management field. This study explored whether and how BIM adoption can help minimize the chronic problem of dispute in the industry. A structured critical literature review method was employed in this study which involved 102 papers in the fields of BIM and construction disputes. Nine main common causes of disputes (e.g., change order, design error, site problem, contractual problem, payment problem, and delay) and eight primary benefits of BIM application (e.g., improved visual management, design optimization, improved information management, and enhanced collaboration) were identified. A conceptual framework was developed illustrating the mechanism of adopting BIM to facilitate dispute management in the overall life cycle of construction projects. The framework indicates that design error, delay, and change order can be reduced most significantly by most of the BIM benefits, whereas improved visual management, improved information management, and enhanced collaboration are three of the most frequently adopted BIM benefits that can settle the majority of dispute causes. This study contributes to dispute management with a more holistic view of adopting BIM in the life cycle of construction projects, as illustrated in the conceptual framework. In addition, the identified common causes of disputes and primary benefits of BIM application are valuable for on future research in these two areas.

Practical Applications

The research findings are valuable for practitioners to obtain a holistic understanding of the two topics of dispute causes and BIM benefits, both independently and integrally. First, the identified common causes of disputes can be used by project managers to develop more-targeted strategies for reducing potential disputes in their projects. Second, the identified BIM benefits provide a comprehensive view of the advantages of BIM application for the clients, which will enable them to use BIM in their projects more proactively. Finally, and more importantly, the research findings indicated that BIM could be used to manage disputes in the global construction industry more effectively. The identified BIM features and other technologies or tools in dispute management present comprehensive results illustrating how to use BIM directly or indirectly for dispute management. In addition, the proposed framework is valuable for practitioners to find better solutions to prevent and control construction disputes via the application of BIM throughout the project life cycle.

Get full access to this article

View all available purchase options and get full access to this article.

Data Availability Statement

Some or all data, models, or code that support the findings of this study are available from the corresponding author upon reasonable request.

References

Acharya, N. K., Y. D. Lee, and H. M. Im. 2006. “Conflicting factors in construction projects: Korean perspective.” Eng. Constr. Archit. Manage. 13 (6): 543–566. https://doi.org/10.1108/09699980610712364.
Ahankoob, A., K. Manley, and B. Abbasnejad. 2019. “The role of contractors’ building information modelling (BIM) experience in realising the potential values of BIM.” Int. J. Constr. Manage. 22 (4): 588–599. https://doi.org/10.1080/15623599.2019.1639126.
Ali, B., H. Zahoor, A. R. Nasir, A. Maqsoom, R. W. A. Khan, and K. M. Mazher. 2020. “BIM-based claims management system: A centralized information repository for extension of time claims.” Autom. Constr. 110 (Feb): 102937. https://doi.org/10.1016/j.autcon.2019.102937.
Alnuaimi, A. S., R. A. Taha, M. A. Mohsin, and A. S. Al-Harthi. 2010. “Causes, effects, benefits, and remedies of change orders on public construction projects in Oman.” J. Constr. Eng. Manage. 136 (5): 615–622. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000154.
Arcadis. 2020. “Global construction dispute report: Collaborating to achieve project excellence.” In Proc., 10th Annual Global Construction Disputes Report. Amsterdam, Netherlands: Arcadis.
Ashcraft, H. W. 2008. “Building information modelling: A framework for collaboration.” Constr. Lawyer 28 (3): 1–14.
Assaad, R., I. H. El-adaway, A. H. Hakea, M. J. Parker, T. I. Henderson, C. R. Ralvo, and M. O. Ahmed. 2020. “Contractual perspective for BIM utilization in US construction projects.” J. Constr. Eng. Manage. 146 (12): 04020128. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001927.
Assaf, A., M. A. Hassanain, A. Abdallah, A. M. Z. Sayed, and A. Alshahrani. 2019. “Significant causes of claims and disputes in construction projects in Saudi Arabia.” Built Environ. Project Asset Manage. 9 (5): 597–615. https://doi.org/10.1108/BEPAM-09-2018-0113.
Awwad, R., B. Barakat, and C. Menassa. 2016. “Understanding dispute resolution in the Middle East region from perspectives of different stakeholders.” J. Manage. Eng. 32 (6): 05016019. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000465.
Barlish, K., and K. Sullivan. 2012. “How to measure the benefits of BIM—A case study approach.” Autom. Constr. 24 (Jul): 149–159. https://doi.org/10.1016/j.autcon.2012.02.008.
BCT (Beijing Arbitration Commission). 2021. “Research report on dispute resolution mechanism of belt and road projects.” [In Chinese.] Accessed October 30, 2021. https://www.bjac.org.cn/news/view?id=3919.
Bortolini, R., C. T. Formoso, and D. D. Viana. 2019. “Site logistics planning and control for engineer-to-order prefabricated building systems using BIM 4D modelling.” Autom. Constr. 98 (Feb): 248–264. https://doi.org/10.1016/j.autcon.2018.11.031.
Bryde, D., M. Broquetas, and J. M. Volm. 2013. “The project benefits of building information modelling (BIM).” Int. J. Project Manage. 31 (7): 971–980. https://doi.org/10.1016/j.ijproman.2012.12.001.
Cakmak, P. I. 2016. “Causes of disputes in the Turkish construction industry: Case of public sector projects.” J. Faculty Archit. 13 (3): 109–118.
Chahrour, R., M. A. Hafeez, A. M. Ahmad, H. I. Sulieman, H. Dawood, S. Rodriguez-Trejo, M. Kassem, K. K. Naji, and N. Dawood. 2021. “Cost-benefit analysis of BIM-enabled design clash detection and resolution.” Construct. Manage. Econ. 39 (1): 55–72. https://doi.org/10.1080/01446193.2020.1802768.
Chan, D. W. M., T. O. Olawumi, and A. M. L. Ho. 2019. “Perceived benefits of and barriers to building information modelling (BIM) implementation in construction: The case of Hong Kong.” J. Build. Eng. 25 (Sep): 100764. https://doi.org/10.1016/j.jobe.2019.100764.
Chan, E. H. W., and H. C. H. Suen. 2005. “Dispute resolution management for international construction projects in China.” Manage. Decis. 43 (4): 589–602. https://doi.org/10.1108/00251740510593576.
Charefa, R., H. Alakaa, and S. Emmitt. 2018. “Beyond the third dimension of BIM: A systematic review of literature and assessment of professional views.” J. Build. Eng. 19 (Sep): 242–257. https://doi.org/10.1016/j.jobe.2018.04.028.
Chen, K., W. Lu, Y. Peng, S. Rowlinson, and G. Q. Huang. 2015. “Bridging BIM and building: From a literature review to an integrated conceptual framework.” Int. J. Project Manage. 33 (6): 1405–1416. https://doi.org/10.1016/j.ijproman.2015.03.006.
Cheung, S. O., and K. H. Y. Pang. 2013. “Anatomy of construction disputes.” J. Constr. Eng. Manage. 139 (1): 15–23. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000532.
CIB (International Council for Research and Innovation in Building and Construction). 2019. “Partner journals.” Accessed October 1, 2021. https://cibworld.org/partner-journals/.
Craveiro, F., J. P. Duarte, H. Bartolo, and P. J. Bartolo. 2019. “Additive manufacturing as an enabling technology for digital construction: A perspective on Construction 4.0.” Autom. Constr. 103 (Jul): 251–267. https://doi.org/10.1016/j.autcon.2019.03.011.
Crowther, J., and S. O. Ajayi. 2021. “Impacts of 4D BIM on construction project performance.” Int. J. Constr. Manage. 21 (7): 724–737. https://doi.org/10.1080/15623599.2019.1580832.
Deng, Y., V. J. L. Gan, M. Das, J. C. P. Cheng, and C. Anumba. 2019. “Integrating 4D BIM and GIS for construction supply chain management.” J. Constr. Eng. Manage. 145 (4): 04019016. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001633.
Diekmann, J. E., and M. C. Nelson. 1985. “Construction claims frequency and severity.” J. Constr. Eng. Manage. 111 (1): 74–81. https://doi.org/10.1061/(ASCE)0733-9364(1985)111:1(74).
Ding, L., Y. Zhou, and B. Akinci. 2014. “Building information modeling (BIM) application framework: The process of expanding from 3D to computable nD.” Autom. Constr. 46 (Oct): 82–93. https://doi.org/10.1016/j.autcon.2014.04.009.
Du, J., D. Zhao, R. R. A. Issa, and N. Singh. 2020. “BIM for improved project communication networks: Empirical evidence from email logs.” J. Comput. Civ. Eng. 34 (5): 04020027. https://doi.org/10.1061/(ASCE)CP.1943-5487.0000912.
Eastman, C. M., P. M. Teicholz, R. Sacks, and L. Ghang. 2018. BIM handbook: A guide to building information modeling for owners, managers, designers, engineers and contractors. 3rd ed. Hoboken, NJ: Wiley.
El-Hawary, A., and A. H. Nassar. 2016. “The effect of building information modelling on construction claims.” Int. J. Sci. Technol. Res. 5 (12): 25–33.
El-Sayegh, S., I. Ahmad, M. Aljanabi, R. Herzallah, S. Metry, and O. El-Ashwal. 2020. “Construction disputes in the UAE: Causes and resolution methods.” Buildings 10 (10): 171. https://doi.org/10.3390/buildings10100171.
Fanning, B., C. M. Clevenger, M. E. Ozbek, and H. Mahmoud. 2015. “Implementing BIM on infrastructure: Comparison of two bridge construction projects.” Pract. Period. Struct. Des. Constr. 20 (4): 04014044. https://doi.org/10.1061/(ASCE)SC.1943-5576.0000239.
Farnsworth, C. B., S. Beveridge, K. R. Miller, and J. P. Christofferson. 2015. “Applications, advantages, and methods associated with using BIM in commercial construction.” Int. J. Constr. Educ. Res. 11 (3): 218–236. https://doi.org/10.1080/15578771.2013.865683.
Fatima, I., A. Humayun, U. Iqbal, and M. Shafiq. 2019. “Dimensions of service quality in healthcare: A systematic review of literature.” Int. J. Quality Health Care 31 (1): 11–29. https://doi.org/10.1093/intqhc/mzy125.
Garbett, J., T. Hartley, and D. Heesom. 2021. “A multi-user collaborative BIM-AR system to support design and construction.” Autom. Constr. 122 (Feb): 103487. https://doi.org/10.1016/j.autcon.2020.103487.
Georgiadou, M. C. 2019. “An overview of benefits and challenges of building information modelling (BIM) adoption in UK residential projects.” Constr. Innovation 19 (3): 298–320. https://doi.org/10.1108/CI-04-2017-0030.
Gholizadeh, P., B. Esmaeili, and P. Goodrum. 2018. “Diffusion of building information modeling functions in the construction industry.” J. Manage. Eng. 34 (2): 04017060. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000589.
Grant, M. J., and A. Booth. 2009. “A typology of reviews: An analysis of 14 review types and associated methodologies.” Health Inf. Libraries J. 26 (2): 91–108. https://doi.org/10.1111/j.1471-1842.2009.00848.x.
Guevremont, M., and A. Hammand. 2018. “Visualization of delay claim analysis using 4D simulation.” J. Leg. Aff. Dispute Resolut. Eng. Constr. 10 (3): 1–8. https://doi.org/10.1061/(ASCE)LA.1943-4170.0000267.
Guevremont, M., and A. Hammand. 2021. “Ontology for linking delay claims with 4D simulation to analyze effects-causes and responsibilities.” J. Leg. Aff. Dispute Resolut. Eng. Constr. 13 (4): 04521024. https://doi.org/10.1061/(ASCE)LA.1943-4170.0000489.
Ham, N., S. Moon, J.-H. Kim, and J.-J. Kim. 2018. “Economic analysis of design errors in BIM-based high-rise construction projects: Case study of Haeundae L project.” J. Constr. Eng. Manage. 144 (6): 05018006. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001498.
Hamledari, H., and M. Fischer. 2021. “Role of blockchain-enabled smart contracts in automating construction progress payments.” J. Leg. Aff. Dispute Resolut. Eng. Constr. 13 (1): 04520038. https://doi.org/10.1061/(ASCE)LA.1943-4170.0000442.
Handayani, T. N., V. Likhitruangsilp, and N. Yabuki. 2019. “A building information modelling (BIM)-integrated system for evaluating the impact of change order.” Eng. J. 23 (4): 67–90. https://doi.org/10.4186/ej.2019.23.4.67.
Hanna, A., F. Boodai, and M. El Asmar. 2013. “State of practice of building information modeling in mechanical and electrical construction industries.” J. Constr. Eng. Manage. 139 (10): 4013009. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000747.
Hardin, B., and D. McCool. 2015. BIM and construction management: Proven tools, methods, and workflows. 2nd ed. New York: Wiley.
Hassan, F. U., T. Le, and X. Lv. 2021. “Addressing legal and contractual matters in construction using natural language processing: A critical review.” J. Constr. Eng. Manage. 147 (9): 03121004. https://doi.org/10.1061/(ASCE)CO.1943-7862.0002122.
Haugen, T., and A. Singh. 2015. “Dispute resolution strategy selection.” J. Leg. Aff. Dispute Resolut. Eng. Constr. 7 (3): 1–9. https://doi.org/10.1061/(ASCE)LA.1943-4170.0000160.
Hosseini, M. R., M. Maghrebi, A. Akbarnezhad, I. Martek, and M. Arashpour. 2018. “Analysis of citation networks in building information modeling research.” J. Constr. Eng. Manage. 144 (8): 04018064. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001492.
Ibraheem, R. A. R., and A. M. R. Mahjoob. 2022. “Facilitating claims settlement using building information modeling in the school building projects.” Innovative Infrastruct. Solutions 7 (40): 1–7. https://doi.org/10.1007/s41062-021-00646-2.
Illankoon, I. M. C. S., V. W. Y. Tam, K. N. Le, and K. A. T. O. Ranadewa. 2019. “Causes of disputes, factors affecting dispute resolution and effective alternative dispute resolution for Sri Lankan construction industry.” Int. J. Constr. Manage. 22 (2): 218–228. https://doi.org/10.1080/15623599.2019.1616415.
Jahren, C. T., and B. F. Dammeier. 1990. “Investigation into construction disputes.” J. Manage. Eng. 6 (1): 39–46. https://doi.org/10.1061/(ASCE)9742-597X(1990)6:1(39).
Jamil, A. H. A., and M. S. Fathi. 2020. “Enhancing BIM-based information interoperability: Dispute resolution from legal and contractual perspective.” J. Constr. Eng. Manage. 146 (7): 05020007. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001868.
Jergeas, G., and F. Hartman. 1994. “Contractors’ construction-claims avoidance.” J. Constr. Eng. Manage. 120 (3): 553–560. https://doi.org/10.1061/(ASCE)0733-9364(1994)120:3(553).
Jin, R., C. Hancock, L. Tang, C. Chen, D. Wanatowski, and L. Yang. 2017. “Empirical study of BIM implementation–based perceptions among Chinese practitioners.” J. Manage. Eng. 33 (5): 04017025. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000538.
Kalach, M., M.-A. Abdul-Malak, and I. Srour. 2021. “BIM-enabled streaming of changes and potential claims induced by fast-tracking design-build projects.” J. Leg. Aff. Dispute Resolut. Eng. Constr. 13 (1): 04520042. https://doi.org/10.1061/(ASCE)LA.1943-4170.0000450.
Kim, H., H. S. Lee, M. P. Park, B. Y. Chung, and S. Hwang. 2015. “Information retrieval framework for hazard identification in construction.” J. Comput. Civ. Eng. 29 (3): 04014052. https://doi.org/10.1061/(ASCE)CP.1943-5487.0000340.
Kumaraswamy, M. M. 1997. “Conflicts, claims and disputes in construction.” Eng. Constr. Archit. Manage. 4 (2): 95–111. https://doi.org/10.1108/eb021042.
Le, P. L., A. Chaabane, and T.-M. Dao. 2019. “BIM contributions to construction supply chain management trends: An exploratory study in Canada.” Int. J. Constr. Manage. 22 (1): 66–84. https://doi.org/10.1080/15623599.2019.1639124.
Lee, S.-I., J.-S. Bae, and Y. S. Cho. 2012. “Efficiency analysis of set-based design with structural building information modeling (S-BIM) on high-rise building structures.” Autom. Constr. 23 (May): 20–32. https://doi.org/10.1016/j.autcon.2011.12.008.
Li, J., N. Li, J. Peng, H. Cui, and Z. Wu. 2018. “A review of current applied building information modeling tools of construction in China.” J. Cleaner Prod. 201 (Nov): 358–368. https://doi.org/10.1016/j.jclepro.2018.08.037.
Lin, G., and Q. Shen. 2007. “Measuring the performance of value management studies in construction: Critical review.” J. Manage. Eng. 23 (1): 2–9. https://doi.org/10.1061/(ASCE)0742-597X(2007)23:1(2).
Lin, J. J., and M. Golparvar-Fard. 2021. “Visual and virtual production management system for proactive project controls.” J. Constr. Eng. Manage. 147 (7): 04021058. https://doi.org/10.1061/(ASCE)CO.1943-7862.0002045.
Lin, S.-S., S.-L. Shen, A. Zhou, and Y.-S. Xu. 2021. “Risk assessment and management of excavation system based on fuzzy set theory and machine learning methods.” Autom. Constr. 122 (Feb): 103490. https://doi.org/10.1016/j.autcon.2020.103490.
Lin, Y.-C. 2014. “Construction 3D BIM-based knowledge management system: A case study.” J. Civ. Eng. Manage. 20 (2): 186–200. https://doi.org/10.3846/13923730.2013.801887.
Love, P., P. Davis, J. Ellis, and S. O. Cheung. 2010. “Dispute causation: Identification of pathogenic influences in construction.” Eng. Constr. Archit. Manage. 17 (4): 404–423. https://doi.org/10.1108/09699981011056592.
Lu, W., A. Fung, Y. Peng, C. Liang, and S. Rowlinson. 2014. “Cost-benefit analysis of building information modeling implementation in building projects through demystification of time-effort distribution curves.” Build. Environ. 82 (Dec): 317–327. https://doi.org/10.1016/j.buildenv.2014.08.030.
Lu, W., Y. Peng, Q. Shen, and H. Li. 2013. “Generic model for measuring benefits of BIM as a learning tool in construction tasks.” J. Constr. Eng. Manage. 139 (2): 195–203. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000585.
Lu, Y., P. Gong, Y. Tang, S. Sun, and Q. Li. 2021. “BIM-integrated construction safety risk assessment at the design stage of building projects.” Autom. Constr. 124 (Apr): 103553. https://doi.org/10.1016/j.autcon.2021.103553.
Ma, X., F. Xiong, T. O. Olawumi, N. Dong, and A. P. C. Chan. 2018. “Conceptual framework and roadmap approach for integrating BIM into lifecycle project management.” J. Manage. Eng. 34 (6): 05018011. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000647.
Mahdi, I. M., M. A. Mohamedien, H. M. H. Ibrahim, and M. A. E. M. Khalil. 2019. “Proposed management system of marine works based on BIM approach (technology).” J. Eng. Appl. Sci. 66 (6): 771–790.
Martins, S. S., A. C. J. Evangelista, A. W. A. Hammad, V. W. Y. Tam, and A. Haddad. 2020. “Evaluation of 4D BIM tools applicability in construction planning efficiency.” Int. J. Constr. Manage. 1–14. https://doi.org/10.1080/15623599.2020.1837718.
Marzouk, M., A. Othman, M. Enaba, and M. Zaher. 2018. “Using BIM to identify claims early in the construction industry: Case study.” J. Leg. Aff. Dispute Resolut. Eng. Constr. 10 (3): 05018001. https://doi.org/10.1061/(ASCE)LA.1943-4170.0000254.
Mehany, M. S. H., and N. Grigg. 2015. “Causes of road and bridge construction claims: Analysis of Colorado department of transportation projects.” J. Leg. Aff. Dispute Resolut. Eng. Constr. 7 (2): 1–7. https://doi.org/10.1061/(ASCE)LA.1943-4170.0000162.
Merschbrock, C., and B. E. Munkvold. 2015. “Effective digital collaboration in the construction industry—A case study of BIM deployment in a hospital construction project.” Comput. Ind. 73 (Oct): 1–7. https://doi.org/10.1016/j.compind.2015.07.003.
Mirzaei, A., F. Nasirzadeh, M. P. Jalal, and Y. Zamani. 2018. “4D-BIM dynamic time–space conflict detection and quantification system for building construction projects.” J. Constr. Eng. Manage. 144 (7): 04018056. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001504.
Mitropoulos, P., and G. Howell. 2001. “Model for understanding, preventing, and resolving project disputes.” J. Constr. Eng. Manage. 127 (3): 223–231. https://doi.org/10.1061/(ASCE)0733-9364(2001)127:3(223).
Mostafa, S., K. P. Kim, V. W. Y. Tam, and P. Rahnamayiezekavat. 2020. “Exploring the status, benefits, barriers and opportunities of using BIM for advancing prefabrication practice.” Int. J. Constr. Manage. 20 (2): 146–156. https://doi.org/10.1080/15623599.2018.1484555.
Noruwa, B. I., A. O. Arewa, and C. Merschbrock. 2022. “Effects of emerging technologies in minimising variations in construction projects in the UK.” Int. J. Constr. Manage. 22 (11): 2199–2206. https://doi.org/10.1080/15623599.2020.1772530.
Oraee, M., M. R. Hosseini, J. D. Edwards, H. Li, E. Papadonikolaki, and D. Cao. 2019. “Collaboration barriers in BIM-based construction networks: A conceptual model.” Int. J. Project Manage. 37 (6): 839–854. https://doi.org/10.1016/j.ijproman.2019.05.004.
Oswald, D., and A. Dainty. 2020. “Ethnographic research in the construction industry: A critical review.” J. Constr. Eng. Manage. 146 (10): 3120003. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001917.
Paik, S. M., P. Leviakangas, and J. Choi. 2022. “Making most of BIM in design: Analysis of the importance of design coordination.” Int. J. Constr. Manage. 22 (12): 2225–2233. https://doi.org/10.1080/15623599.2020.1774837.
Pan, Y., and L. Zhang. 2021. “Roles of artificial intelligence in construction engineering and management: A critical review and future trends.” Autom. Constr. 122 (Feb): 103517. https://doi.org/10.1016/j.autcon.2020.103517.
Park, J. H., and G. Lee. 2017. “Design coordination strategies in a 2D and BIM mixed-project environment: Social dynamics and productivity.” Build. Res. Inf. 45 (6): 631–648. https://doi.org/10.1080/09613218.2017.1288998.
Pradeep, A. S. E., T. W. Yiu, Y. Zou, and R. Amor. 2021. “Blockchain-aided information exchange records for design liability control and improved security.” Autom. Constr. 126 (Jun): 103667. https://doi.org/10.1016/j.autcon.2021.103667.
Providakis, S., C. D. F. Rogers, and D. N. Chapman. 2019. “Predictions of settlement risk induced by tunnelling using BIM and 3D visualization tools.” Int. J. Project Manage. 92 (Oct): 103049. https://doi.org/10.1016/j.tust.2019.103049.
Ragab, M. A., and M. Marzouk. 2021. “BIM adoption in construction contracts: Content analysis approach.” J. Constr. Eng. Manage. 147 (8): 04021094. https://doi.org/10.1061/(ASCE)CO.1943-7862.0002123.
Romero-Jaren, R., and J. J. Arranz. 2021. “Automatic segmentation and classification of BIM elements from point clouds.” Autom. Constr. 124 (Apr): 103576. https://doi.org/10.1016/j.autcon.2021.103576.
Sacks, R., L. Koskela, B. A. Dave, and R. Owen. 2010. “Interaction of lean and building information modeling in construction.” J. Constr. Eng. Manage. 136 (9): 968–980. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000203.
Saka, A. B., and D. W. M. Chan. 2020. “Adoption and implementation of building information modelling (BIM) in small and medium-sized enterprises (SMEs): A review and conceptualization.” Eng. Constr. Archit. Manage. https://doi.org/10.1108/ECAM-06-2019-0332.
Sami Ur Rehman, M., M. J. Thaheem, A. R. Nasir, and K. I. A. Khan. 2022. “Project schedule risk management through building information modelling.” Int. J. Constr. Manage. 22 (8): 1489–1499. https://doi.org/10.1080/15623599.2020.1728606.
Sanni-Anibire, M. O., R. M. Zin, and S. O. Olatunji. 2022. “Causes of delay in the global construction industry: A meta analytical review.” Int. J. Constr. Manage. 22 (8): 1395–1407. https://doi.org/10.1080/15623599.2020.1716132.
Saoud, L. A., J. Omran, B. Hassan, T. Vilutiene, and A. Kiaulakis. 2017. “A method to predict change propagation within building information model.” J. Civ. Eng. Manage. 23 (6): 836–846. https://doi.org/10.3846/13923730.2017.1323006.
Semple, C., F. T. Hartman, and G. Jergeas. 1994. “Construction claims and disputes: Causes and cost/time overruns.” J. Constr. Eng. Manage. 120 (4): 785–795. https://doi.org/10.1061/(ASCE)0733-9364(1994)120:4(785).
Seuring, S., and M. Muller. 2008. “From a literature review to a conceptual framework for sustainable supply chain management.” J. Cleaner Prod. 16 (15): 1699–1710. https://doi.org/10.1016/j.jclepro.2008.04.020.
Shahhosseini, V., and H. Hajarolasvadi. 2021. “A conceptual framework for developing a BIM-enabled claim management system.” Int. J. Constr. Manage. 21 (2): 208–222. https://doi.org/10.1080/15623599.2018.1512182.
Siahboomy, M. A., H. Sarvari, D. W. M. Chan, H. Nassereddine, and Z. Chen. 2022. “A multi-criteria optimization study for locating industrial warehouses with the integration of BIM and GIS data.” Archit. Eng. Des. Manage. 17 (5–6): 478–495. https://doi.org/10.1080/17452007.2021.1881880.
Sibanyama, G., M. Muya, and C. Kaliba. 2012. “An overview of construction claims: A case study of the Zambian construction industry.” Int. J. Constr. Manage. 12 (1): 65–81. https://doi.org/10.1080/15623599.2012.10773185.
Siraj, N. B., and A. R. Fayek. 2019. “Risk identification and common risks in construction: Literature review and content analysis.” J. Constr. Eng. Manage. 145 (9): 03119004. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001685.
Sloot, R. N. F., A. Heutink, and J. T. Voordijk. 2019. “Assessing usefulness of 4D BIM tools in risk mitigation strategies.” Autom. Constr. 106 (Oct): 102881. https://doi.org/10.1016/j.autcon.2019.102881.
Son, H., C. Kim, and Y. K. Cho. 2017. “Automated schedule updates using as-built data and a 4D building information model.” J. Manage. Eng. 33 (4): 4017012. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000528.
Tak, A. N., H. Taghaddos, A. Mousaei, A. Bolourani, and U. Hermann. 2021. “BIM-based 4D mobile crane simulation and onsite operation management.” Autom. Constr. 128 (Aug): 103766. https://doi.org/10.1016/j.autcon.2021.103766.
Tetteh, M. O., A. P. C. Chan, A. Darko, and G. Nani. 2020. “Factors affecting international construction joint ventures: A systematic literature review.” Int. J. Constr. Manage. https://doi.org/10.1080/15623599.2020.1850203.
Viswanathan, S. K., A. Panwar, S. Kar, R. Lavingiya, and K. N. Jha. 2020. “Causal modeling of disputes in construction projects.” J. Leg. Aff. Dispute Resolut. Eng. Constr. 12 (4): 04520035. https://doi.org/10.1061/(ASCE)LA.1943-4170.0000432.
Wang, H., Y. Pan, and X. Luo. 2019. “Integration of BIM and GIS in sustainable built environment: A review and bibliometric analysis.” Autom. Constr. 103 (Jul): 41–52. https://doi.org/10.1016/j.autcon.2019.03.005.
Winfield, M., and S. Rock. 2018. “Overcoming the legal and contractual barriers of BIM.” Accessed October 1, 2021. https://www.ukbimalliance.org/winfield-rock-report/.
Wing, C. K. 1997. “The ranking of construction management journals.” Construct. Manage. Econ. 15 (4): 387–398. https://doi.org/10.1080/014461997372953.
Wnuk, K., and T. Garrepalli. 2018. “Knowledge management in software testing: A systematic snowball literature review.” E-Inf. Software Eng. J. 12 (1): 51–78. https://doi.org/10.5277/e-Inf180103.
Won, J., G. Lee, C. Dossick, and J. Messner. 2013. “Where to focus for successful adoption of building information modeling within organization.” J. Constr. Eng. Manage. 139 (11): 04013014. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000731.
Xue, J., G. Q. Shen, R. J. Yang, H. Wu, X. Li, X. Lin, and F. Xue. 2020. “Mapping the knowledge domain of stakeholder perspective studies in construction projects: A bibliometric approach.” Int. J. Project Manage. 38 (6): 313–326. https://doi.org/10.1016/j.ijproman.2020.07.007.
Yi, W., and A. P. C. Chan. 2014. “Critical review of labor productivity research in construction journals.” J. Manage. Eng. 30 (2): 214–225. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000194.
Zaneldin, E. K. 2020. “Investigating the types, causes and severity of claims in construction projects in the UAE.” Int. J. Constr. Manage. 20 (5): 385–401. https://doi.org/10.1080/15623599.2018.1484863.
Zhang, S., A. P. C. Chan, Y. Feng, H. Duan, and Y. Ke. 2016. “Critical review on PPP research—A search from the Chinese and international journals.” Int. J. Project Manage. 34 (4): 597–612. https://doi.org/10.1016/j.ijproman.2016.02.008.
Zhang, S., C. Shang, C. Wang, R. Song, and X. Wang. 2019. “Real-time safety risk identification model during metro construction adjacent to buildings.” J. Constr. Eng. Manage. 145 (6): 04019034. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001657.
Zhao, X., B.-G. Hwang, and G. S. Yu. 2013. “Identifying the critical risks in underground rail international construction joint ventures: Case study of Singapore.” Int. J. Project Manage. 31 (4): 554–566. https://doi.org/10.1016/j.ijproman.2012.10.014.
Zhou, Z., Y. M. Goh, and Q. Li. 2015. “Overview and analysis of safety management studies in the construction industry.” Saf. Sci. 72 (Feb): 337–350. https://doi.org/10.1016/j.ssci.2014.10.006.
Zou, P. X. W., G. Zhang, and J. Wang. 2007. “Understanding the key risks in construction projects in China.” Int. J. Project Manage. 25 (6): 601–614. https://doi.org/10.1016/j.ijproman.2007.03.001.

Information & Authors

Information

Published In

Go to Journal of Construction Engineering and Management
Journal of Construction Engineering and Management
Volume 149Issue 1January 2023

History

Published online: Oct 19, 2022
Published in print: Jan 1, 2023
Discussion open until: Mar 19, 2023

Permissions

Request permissions for this article.

ASCE Technical Topics:

Authors

Affiliations

Ph.D. Candidate, School of Mechanical, Aerospace, and Civil Engineering, Univ. of Manchester, Manchester M13 9PL, UK. ORCID: https://orcid.org/0000-0002-6930-6978. Email: [email protected]
Shang Zhang [email protected]
Associate Professor and Head, Dept. of Construction Management, Suzhou Univ. of Science and Technology, Suzhou 215011, China (corresponding author). Email: [email protected]
Reader, School of Mechanical, Aerospace and Civil Engineering, Univ. of Manchester, Manchester M13 9PL, UK. Email: [email protected]
Xiaowei Luo [email protected]
Associate Professor, Dept. of Architecture and Civil Engineering, The City Univ. of Hong Kong, Hong Kong 999077, China. Email: [email protected]
Researcher, Faculty of Civil Engineering and Geosciences, Delft Univ. of Technology, Delft CN 2628, Netherlands; Research Fellow, School of Management and Engineering, Nanjing Univ., Nanjing 210093, China. ORCID: https://orcid.org/0000-0001-8706-6712. Email: [email protected]
Ph.D. Candidate, School of Architecture, Civil and Building Engineering, Loughborough Univ., Loughborough, Leicestershire LE11 3TU, UK. ORCID: https://orcid.org/0000-0002-4251-7281. Email: [email protected]

Metrics & Citations

Metrics

Citations

Download citation

If you have the appropriate software installed, you can download article citation data to the citation manager of your choice. Simply select your manager software from the list below and click Download.

Cited by

  • Automated Management of Time Extension Claims, Journal of Legal Affairs and Dispute Resolution in Engineering and Construction, 10.1061/JLADAH.LADR-1104, 16, 2, (2024).
  • Development of an Integrated Hybrid Risk Assessment System for Construction Disputes during the Preconstruction Phase Using the Delphi Method, Journal of Construction Engineering and Management, 10.1061/JCEMD4.COENG-14492, 150, 7, (2024).
  • Digital Technologies for Preventing, Mitigating, and Resolving Contractual Disagreements in the AEC Industry: A Systematic Literature Review, Journal of Construction Engineering and Management, 10.1061/JCEMD4.COENG-14032, 150, 6, (2024).
  • Prospects of Promoting MMC across the Public Construction Sector: A Systematic Review against the Diffusion of Innovation Theory, Journal of Architectural Engineering, 10.1061/JAEIED.AEENG-1547, 29, 3, (2023).

View Options

Get Access

Access content

Please select your options to get access

Log in/Register Log in via your institution (Shibboleth)
ASCE Members: Please log in to see member pricing

Purchase

Save for later Information on ASCE Library Cards
ASCE Library Cards let you download journal articles, proceedings papers, and available book chapters across the entire ASCE Library platform. ASCE Library Cards remain active for 24 months or until all downloads are used. Note: This content will be debited as one download at time of checkout.

Terms of Use: ASCE Library Cards are for individual, personal use only. Reselling, republishing, or forwarding the materials to libraries or reading rooms is prohibited.
ASCE Library Card (5 downloads)
$105.00
Add to cart
ASCE Library Card (20 downloads)
$280.00
Add to cart
Buy Single Article
$35.00
Add to cart

Get Access

Access content

Please select your options to get access

Log in/Register Log in via your institution (Shibboleth)
ASCE Members: Please log in to see member pricing

Purchase

Save for later Information on ASCE Library Cards
ASCE Library Cards let you download journal articles, proceedings papers, and available book chapters across the entire ASCE Library platform. ASCE Library Cards remain active for 24 months or until all downloads are used. Note: This content will be debited as one download at time of checkout.

Terms of Use: ASCE Library Cards are for individual, personal use only. Reselling, republishing, or forwarding the materials to libraries or reading rooms is prohibited.
ASCE Library Card (5 downloads)
$105.00
Add to cart
ASCE Library Card (20 downloads)
$280.00
Add to cart
Buy Single Article
$35.00
Add to cart

Media

Figures

Other

Tables

Share

Share

Copy the content Link

Share with email

Email a colleague

Share