Influence of Perceived Fairness on Contractors’ Potential to Dispute: Moderating Effect of Engineering Ethics
This article has a reply.
VIEW THE REPLYThis article has a reply.
VIEW THE REPLYPublication: Journal of Construction Engineering and Management
Volume 146, Issue 1
Abstract
The relationship between the perceived fairness of administering projects’ claims and contractors’ reduced potential to disputes is probably missing in published literature in the context of engineering ethics. In the current research, the moderating effect of engineering ethics is explored in relationship between perceived fairness and contractors’ reduced potential to dispute. The data are gathered from 90 contract administrators in the construction industry of Pakistan. The results depict that decision outcome fairness, procedural fairness, quality of treatment experienced, and control indicate a significantly positive effect on the contractors’ reduced potential to disputes. Additionally, engineering ethics positively moderated the relationship between the quality of treatment experienced and contractors’ reduced potential to disputes. These results can guide project management teams to diminish the contractors’ perceptions concerning construction claims and disputes.
Get full access to this article
View all available purchase options and get full access to this article.
Data Availability Statement
Data generated or analyzed during the study are available from the corresponding author by request. Further information about the data-sharing policy of the Journal can be found here: http://ascelibrary.org/doi/10.1061/%28ASCE%29CO.1943-7862.0001263.
References
Adams, J. S. 1965. “Inequity in social exchange.” In Vol. 2 of Advances in experimental social psychology, 267–299. Cambridge, MA: Academic Press.
Aibinu, A. A. 2009. “Avoiding and mitigating delay and disruption claims conflict: Role of precontract negotiation.” J. Leg. Aff. Dispute Resolut. Eng. Constr. 1 (1): 47–58. https://doi.org/10.1061/(ASCE)1943-4162(2009)1:1(47).
Aibinu, A. A., F. Y. Y. Ling, and G. Ofori. 2011. “Structural equation modelling of organizational justice and cooperative behaviour in the construction project claims process: Contractors’ perspectives.” Constr. Manage. Econ. 29 (5): 463–481. https://doi.org/10.1080/01446193.2011.564195.
Aibinu, A. A., G. Ofori, and F. Y. Ling. 2008. “Explaining cooperative behavior in building and civil engineering projects’ claims process: Interactive effects of outcome favorability and procedural fairness.” J. Constr. Eng. Manage. 134 (9): 681–691. https://doi.org/10.1061/(ASCE)0733-9364(2008)134:9(681).
Akaah, I. P., and D. Lund. 1994. “The influence of personal and organizational values on marketing professionals’ ethical behavior.” J. Bus. Ethics 13 (6): 417–430. https://doi.org/10.1007/BF00881450.
Alexander, S., and M. Ruderman. 1987. “The role of procedural and distributive justice in organizational behavior.” Social Justice Res. 1 (2): 177–198. https://doi.org/10.1007/BF01048015.
Bebchuk, L. A. 1984. “Litigation and settlement under imperfect information.” RAND J. Econ. 15 (3): 404–415. https://doi.org/10.2307/2555448.
Bishop, W. H. 2013. “The role of ethics in 21st century organizations.” J. Bus. Ethics 118 (3): 635–637. https://doi.org/10.1007/s10551-013-1618-1.
Blau, P. 1964. Exchange and power in social life. Hoboken, NJ: Wiley.
Bowen, P., R. Pearl, and A. Akintoye. 2007. “Professional ethics in the South African construction industry.” Build. Res. Inf. 35 (2): 189–205. https://doi.org/10.1080/09613210600980267.
Bradach, J. L., and R. G. Eccles. 1989. “Price, authority, and trust: From ideal types to plural forms.” Ann. Rev. Sociology 15 (1): 97–118. https://doi.org/10.1146/annurev.so.15.080189.000525.
Brewer, M. B., and R. M. Kramer. 1986. “Choice behavior in social dilemmas: Effects of social identity, group size, and decision framing.” J. Personality Social Psychol. 50 (3): 543. https://doi.org/10.1037/0022-3514.50.3.543.
Chau, K. 1993. “Estimating industry-level productivity trends in the building industry from building cost and price data.” Constr. Manage. Econ. 11 (5): 370–383. https://doi.org/10.1080/01446199300000041.
Cheung, S. O., W. K. Wong, T. W. Yiu, and T. W. Kwok. 2008. “Exploring the influence of contract governance on construction dispute negotiation.” J. Prof. Issues Eng. Educ. Pract. 134 (4): 391–398. https://doi.org/10.1061/(ASCE)1052-3928(2008)134:4(391).
Chin, W. W. 2010. “How to write up and report PLS analyses.” In Handbook of partial least squares, 655–690. New York: Springer.
Dijkstra, T. K., and J. Henseler. 2015. “Consistent and asymptotically normal PLS estimators for linear structural equations.” Comput. Stat. Data Anal. 81 (Jan): 10–23. https://doi.org/10.1016/j.csda.2014.07.008.
El-adaway, I. H., I. S. Abotaleb, M. S. Eid, S. May, L. Netherton, and J. Vest. 2018. “Contract administration guidelines for public infrastructure projects in the United States and Saudi Arabia: Comparative analysis approach.” J. Constr. Eng. Manage. 144 (6): 04018031. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001472.
Enshassi, A., R. M. Choudhry, and S. El-Ghandour. 2009. “Contractors’ perceptions towards causes of claims in construction projects.” Int. J. Constr. Manage. 9 (1): 79–92. https://doi.org/10.1080/15623599.2009.10773123.
Felstiner, W. L., R. L. Abel, and A. Sarat. 1980. “The emergence and transformation of disputes: Naming, blaming, claiming.” Law Soc. Rev. 15 (3/4): 631–654. https://doi.org/10.2307/3053505.
Fenn, P., D. Lowe, and C. Speck. 1997. “Conflict and dispute in construction.” Constr. Manage. Econ. 15 (6): 513–518. https://doi.org/10.1080/014461997372719.
Fornell, C., and D. F. Larcker. 1981. “Structural equation models with unobservable variables and measurement error: Algebra and statistics.” J. Marketing Res. 18 (3): 382–388. https://doi.org/10.1177/002224378101800313.
Gefen, D., and D. Straub. 2005. “A practical guide to factorial validity using PLS-Graph: Tutorial and annotated example.” Commun. Assoc. Inf. Syst. 16 (1): 91–109. https://doi.org/10.17705/1CAIS.01605.
Greenberg, J. 1982. “Approaching equity and avoiding inequity in groups and organizations.” In Equity and justice in social behavior, 389–435. Cambridge, MA: Academic Press.
Haidar, A. 2011. “Global claim: A case study.” In Global claims in construction, 215–285. New York: Springer.
Hair, J. F. Jr., M. Sarstedt, C. M. Ringle, and S. P. Gudergan. 2017. Advanced issues in partial least squares structural equation modeling. Thousand Oaks, CA: SAGE.
Hauenstein, N. M., T. McGonigle, and S. W. Flinder. 2001. “A meta-analysis of the relationship between procedural justice and distributive justice: Implications for justice research.” Employee Responsibilities Rights J. 13 (1): 39–56. https://doi.org/10.1023/A:1014482124497.
Houlden, P., S. LaTour, L. Walker, and J. Thibaut. 1978. “Preference for modes of dispute resolution as a function of process and decision control.” J. Exp. Social Psychol. 14 (1): 13–30. https://doi.org/10.1016/0022-1031(78)90057-4.
Jarkas, A. M. 2017. “Contractors’ perspective of construction project complexity: Definitions, principles, and relevant contributors.” J. Prof. Issues Eng. Educ. Pract. 143 (4): 04017007. https://doi.org/10.1061/(ASCE)EI.1943-5541.0000337.
Jones, D. A., and D. P. Skarlicki. 2013. “How perceptions of fairness can change: A dynamic model of organizational justice.” Organizational Psychol. Rev. 3 (2): 138–160. https://doi.org/10.1177/2041386612461665.
Kanfer, R., J. Sawyer, P. C. Earley, and E. A. Lind. 1987. “Participation in task evaluation procedures: The effects of influential opinion expression and knowledge of evaluative criteria on attitudes and performance.” Social Justice Res. 1 (2): 235–249. https://doi.org/10.1007/BF01048018.
Kilcullen, M., and O. J. Kooistra. 1999. “At least do no harm: Sources on the changing role of business ethics and corporate social responsibility.” Ref. Serv. Rev. 27 (2): 158–178. https://doi.org/10.1108/00907329910275150.
Koirala, S., D. Hill, and R. Morgan. 2017. “Impacts of the delay in construction of a large scale hydropower project on potential displacees.” Impact Assess. Project Appraisal 35 (1): 106–116. https://doi.org/10.1080/14615517.2016.1271540.
Konovsky, M. A., and S. D. Pugh. 1994. “Citizenship behavior and social exchange.” Academy Manage. J. 37 (3): 656–669. https://doi.org/10.5465/256704.
Kumaraswamy, M. M. 1997. “Conflicts, claims and disputes in construction.” Eng. Constr. Archit. Manage. 4 (2): 95–111. https://doi.org/10.1108/eb021042.
Lind, E. A., C. T. Kulik, M. Ambrose, and M. V. de Vera Park. 1993. “Individual and corporate dispute resolution: Using procedural fairness as a decision heuristic.” Administrative Sci. Q. 38 (2): 224–251. https://doi.org/10.2307/2393412.
Lind, E. A., and T. R. Tyler. 1988. The social psychology of procedural justice. New York: Springer.
Lloyd, H. R., and M. R. Mey. 2010. “An ethics model to develop an ethical organisation.” S. Afr. J. Hum. Resour. Manage. 8 (1): 1–12. https://doi.org/10.4102/sajhrm.v8i1.218.
MacCoun, R. J., E. A. Lind, and T. R. Tyler. 1992. “Alternative dispute resolution in trial and appellate courts.” In Handbook of psychology and law, 95–118. New York: Springer.
Marathe, A., M. S. H. M. Mehany, B. Senior, and K. Strong. 2017. “Dispute resolution and contract incentives: Perceptions of project stakeholders.” J. Leg. Aff. Dispute Resolut. Eng. Constr. 9 (4): 04517019. https://doi.org/10.1061/(ASCE)LA.1943-4170.0000243.
Marcoulides, G. A., and C. Saunders. 2006. “Editor’s comments: PLS: A silver bullet?” MIS Q. 30 (2): 3–9. https://doi.org/10.2307/25148727.
Mehany, M. S. H. M., and N. Grigg. 2015. “Causes of road and bridge construction claims: Analysis of Colorado department of transportation projects.” J. Leg. Aff. Dispute Resolut. Eng. Constr. 7 (2): 04514006. https://doi.org/10.1061/(ASCE)LA.1943-4170.0000162.
Mikula, G., B. Petri, and N. Tanzer. 1990. “What people regard as unjust: Types and structures of everyday experiences of injustice.” Eur. J. Social Psychol. 20 (2): 133–149. https://doi.org/10.1002/ejsp.2420200205.
Moliner, C., R. Cropanzano, and V. Martínez-Tur. 2017. Organizational justice: International perspectives and conceptual advances. London: Routledge.
Nasir, A. R., and R. M. Choudhry. 2010. “Claim management in highway projects of Pakistan.” In Proc., 2nd Int. Conf. on Construction in Developing Countries: Advancing and Integrating Construction Education, Research and Practice (ICCIDC-II), 883–892. Miami: Florida International Univ.
Oladinrin, T. O., and C. M. F. Ho. 2014. “Strategies for improving codes of ethics implementation in construction organizations.” Project Manage. J. 45 (5): 15–26. https://doi.org/10.1002/pmj.21444.
Palinkas, L. A., S. M. Horwitz, C. A. Green, J. P. Wisdom, N. Duan, and K. Hoagwood. 2015. “Purposeful sampling for qualitative data collection and analysis in mixed method implementation research.” Administration Policy Ment. Health Ment. Health Serv. Res. 42 (5): 533–544. https://doi.org/10.1007/s10488-013-0528-y.
Peng, D. X., and F. Lai. 2012. “Using partial least squares in operations management research: A practical guideline and summary of past research.” J. Oper. Manage. 30 (6): 467–480. https://doi.org/10.1016/j.jom.2012.06.002.
Posner, R. A. 2014. Economic analysis of law. Alphen aan den Rijn, Netherlands: Wolters Kluwer Law & Business.
Rajeh, M., J. E. Tookey, and J. O. B. Rotimi. 2015. “Estimating transaction costs in the New Zealand construction procurement: A structural equation modelling methodology.” Eng. Constr. Archit. Manage. 22 (2): 242–267. https://doi.org/10.1108/ECAM-10-2014-0130.
Sheppard, B. H., and R. J. Lewicki. 1987. “Toward general principles of managerial fairness.” Social Justice Res. 1 (2): 161–176. https://doi.org/10.1007/BF01048014.
Simons, T., and Q. Roberson. 2003. “Why managers should care about fairness: The effects of aggregate justice perceptions on organizational outcomes.” J. Appl. Psychol. 88 (3): 432–443. https://doi.org/10.1037/0021-9010.88.3.432.
Sohail, M., and S. Cavill. 2008. “Accountability to prevent corruption in construction projects.” J. Constr. Eng. Manage. 134 (9): 729–738. https://doi.org/10.1061/(ASCE)0733-9364(2008)134:9(729).
Spittler, J. R., and G. H. Jentzen. 1992. “Dispute resolution: Managing construction conflict with step negotiations.” AACE Int. Trans. D9: 1–10.
Thibaut, J., and L. Walker. 1978. “A theory of procedure.” California Law Rev. 66 (3): 541. https://doi.org/10.2307/3480099.
Tow, D., and M. Loosemore. 2009. “Corporate ethics in the construction and engineering industry.” J. Leg. Aff. Dispute Resolut. Eng. Constr. 1 (3): 122–129. https://doi.org/10.1061/(ASCE)LA.1943-4170.0000012.
Tyler, T., and S. Blader. 2000. Cooperation in groups: Procedural justice, social identity, and behavioral engagement. Philadelphia: Taylor & Francis.
Tyler, T. R. 1989. “The psychology of procedural justice: A test of the group-value model.” J. Personality Social Psychol. 57 (5): 830–838. https://doi.org/10.1037/0022-3514.57.5.830.
Urbach, N., and F. Ahlemann. 2010. “Structural equation modeling in information systems research using partial least squares.” J. Inf. Technol. Theory Appl. 11 (2): 5–40.
Winch, G. 1989. “The construction firm and the construction project: A transaction cost approach.” Constr. Manage. Econ. 7 (4): 331–345. https://doi.org/10.1080/01446198900000032.
Wold, H. 1985. “Partial least squares.” In Vol. 6 of Encyclopedia of statistical sciences, edited by S. Kotz, and N. L. Johnson, 581–591. New York: Wiley.
Yates, J. K., and A. Epstein. 2006. “Avoiding and minimizing construction delay claim disputes in relational contracting.” J. Prof. Issues Eng. Educ. Pract. 132 (2): 168–179. https://doi.org/10.1061/(ASCE)1052-3928(2006)132:2(168).
Youngblood, S. A., L. K. Trevino, and M. Favia. 1992. “Reactions to unjust dismissal and third-party dispute resolution: A justice framework.” Employee Responsibilities Rights J. 5 (4): 283–307. https://doi.org/10.1007/BF01388306.
Zhang, S. B., Y. F. Fu, Y. Gao, and X. D. Zheng. 2016. “Influence of trust and contract on dispute negotiation behavioral strategy in construction subcontracting.” J. Manage. Eng. 32 (4): 04016001. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000427.
Information & Authors
Information
Published In
Copyright
©2019 American Society of Civil Engineers.
History
Received: Feb 24, 2019
Accepted: May 21, 2019
Published online: Oct 31, 2019
Published in print: Jan 1, 2020
Discussion open until: Mar 31, 2020
Authors
Metrics & Citations
Metrics
Citations
Download citation
If you have the appropriate software installed, you can download article citation data to the citation manager of your choice. Simply select your manager software from the list below and click Download.