Change Orders: Automating Comparative Data Analysis and Controlling Impacts in Public Projects

Publication: Journal of Construction Engineering and Management
Volume 145, Issue 11

Abstract

Change orders grant public-project owners exceptional flexibility to alleviate construction problems and respond promptly to project needs. Recently, in the Middle East, change orders have become common, leading to significant major problems and disputes. The negative impacts of this phenomenon on project cost and time create a critical need for systems that enable public agencies to identify the technical causes of change orders and investigate their impacts in order to prepare relevant response strategies. This study presents the development of a model for change-order data analysis that is capable of quantifying the impact of change orders on project cost and time. The model incorporates newly developed elements that enable (1) identifying the leading technical causes of change orders by project type and instigator; (2) quantifying the influence of project type and size on change-order cost and duration; and (3) automating the development of periodic reports that can be used to mitigate the negative impacts of change orders. To illustrate the viability of the developed model, a computerized system was developed and populated with data collected from 38 public projects that included 67 change orders. The leading technical causes of change orders identified through record analysis were poor definition of work scope, lack of coordination with authorities, and unplanned interruptions. An inverse exponential relationship is observed between the project size and both the percent time change and percent cost change of change orders. In projects that experienced scope-of-work changes, the percent time and cost changes were substantially higher compared with projects without scope-of-work changes. The paper’s primary contributions to the overall body of knowledge are (1) the development of a standard model to facilitate and automate the comparative analysis of change-order data across public-project types and sizes; and (2) the empirical demonstration of its viability for the analysis of change-order data.

Get full access to this article

View all available purchase options and get full access to this article.

Data Availability Statement

All data generated or analyzed during the study are included in the published paper.

References

Akhavian, R., and A. H. Behzadan. 2012. “An integrated data collection and analysis framework for remote monitoring and planning of construction operations.” Adv. Eng. Inf. 26 (4): 749–761. https://doi.org/10.1016/j.aei.2012.04.004.
Alaryan, A. 2014. “Causes and effects of change orders on construction projects in Kuwait.” Int. J. Eng. Res. Appl. 4 (7): 01–08.
Al-Dubaisi, A. H. 2000. “Change orders in construction projects in Saudi Arabia.” M.S. thesis, Dept. of Construction Engineering and Management, King Fahd Univ. of Petroleum and Minerals.
Alnuaimi, A. S., R. A. Taha, M. Al Mohsin, and A. S. Al-Harthi. 2009. “Causes, effects, benefits, and remedies of change orders on public construction projects in Oman.” J. Constr. Eng. Manage. 136 (5): 615–622. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000154.
Arain, F. M., and L. S. Pheng. 2005. “How design consultants perceive potential causes of variation orders for institutional buildings in Singapore.” Archit. Eng. Des. Manage. 1 (3): 181–196. https://doi.org/10.1080/17452007.2005.9684592.
Arain, F. M., and L. S. Pheng. 2006. “Developers’ views of potential causes of variation orders for institutional buildings in Singapore.” Archit. Sci. Rev. 49 (1): 59–74. https://doi.org/10.3763/asre.2006.4908.
Asamaoh, R. O., and K. Offei-Nyako. 2013. “Variation determinants in building construction: Ghanaian professionals perspective.” J. Constr. Eng. Project Manage. 3 (4): 20–25. https://doi.org/10.6106/JCEPM.2013.3.4.020.
Choi, K., H. W. Lee, J. Bae, and D. Bilbo. 2015. “Time-cost performance effect of change orders from accelerated contract provisions.” J. Constr. Eng. Manage. 142 (3): 04015085. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001071.
CII (Construction Industry Institute). 2010. Project definition rating index—Infrastructure projects. Austin, TX: CII.
CII (Construction Industry Institute). 2012. CII best practices guide, improving project performance, version 4.0. Austin, TX: CII.
Dickson, O. D., and M. Gerryshom. 2015. “Variations in civil engineering construction projects in Kenya: Causes and effects.” Int. J. Eng. Res. Technol. 4 (2): 1124–1129.
Ekhator, O. J. 2016. “Identifying factors causing changes in private residential building projects in Lagos State, Nigeria.” Int. J. Sci. Environ. Technol. 5 (5): 3583–3595.
Gbeleyi, S. A. 2002. “An evaluation of the causes and effects of variation on building project execution in Nigeria.” B.Sc. dissertation, Dept. of Quantity Surveying, Obafemi Awolowo Univ.
Halwatura, R. U., and N. P. Ranasinghe. 2013. “Causes of variation orders in road construction projects in Sri Lanka.” ISRN Constr. Eng. 2013: 1–7. https://doi.org/10.1155/2013/381670.
Hanif, H., M. B. Khurshid, S. Nauman, and S. Lindhard. 2016. “Impact of change orders on time and cost in mega hydropower projects of Pakistan.” J. Constr. Dev. Countries 21 (2): 37–53.
Hanna, A. S., and K. A. Iskandar. 2017. “Quantifying and modeling the cumulative impact of change orders.” J. Constr. Eng. Manage. 143 (10): 04017076. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001385.
Hibberd, P. R. 1986. Variations on construction contracts. London: Collins Professional and Technical Books.
Ibbs, C. W. 1997. “Quantitative impacts of project change: Size issues.” J. Constr. Eng. Manage. 123 (3): 308–311. https://doi.org/10.1061/(ASCE)0733-9364(1997)123:3(308).
Ibbs, C. W., C. K. Wong, and Y. H. Kwak. 2001. “Project change management system.” J. Manage. Eng. 17 (3): 159–165. https://doi.org/10.1061/(ASCE)0742-597X(2001)17:3(159).
Ibbs, W. 2005. “Impact of change’s timing on labor productivity.” J. Constr. Eng. Manage. 131 (11): 1219–1223. https://doi.org/10.1061/(ASCE)0733-9364(2005)131:11(1219).
Koushki, P. A., K. Al-Rashid, and N. Kartam. 2005. “Delays and cost increases in the construction of private residential projects in Kuwait.” Constr. Manage. Econ. 23 (3): 285–294. https://doi.org/10.1080/0144619042000326710.
Memon, A. H., I. A. Rahman, and M. F. A. Hasan. 2014. “Significant causes and effects of variation orders in construction projects.” Res. J. Appl. Sci. Eng. Technol. 7 (21): 4494–4502. https://doi.org/10.19026/rjaset.7.826.
Miresco, E. T., and J. C. Pomerol. 1995. “A knowledge-based decision support system for construction project management.” In Vol. 2 of Proc., Sixth Int. Conf. on Computing in Civil and Building Engineering, 1501–1507. Reston, VA: ASCE.
Mohammad, N., A. I. C. Ani, R. A. O. K. Rakmat, and M. A. Yusof. 2010. “Investigation on the causes of variation orders in the construction of building project: A study in the state of Selangor, Malaysia.” J. Build. Perform. 1 (1): 73–82.
Mokhtar, A., C. Bedard, and P. Fazio. 2000. “Collaborative planning and scheduling of interrelated design changes.” J. Archit. Eng. 6 (2): 66–75. https://doi.org/10.1061/(ASCE)1076-0431(2000)6:2(66).
Molloy, J. 1999. Building and construction claims and disputes. Avalon, Australia: Construction Publications.
Msallam, M., M. Abojaradeh, B. Jrew, and I. Zaki. 2015. “Controlling of variation orders in highway projects in Jordan.” J. Eng. Archit. 3 (2): 95–104. https://doi.org/10.15640/jea.v3n2a11.
PMI (Project Management Institute). 2011. Practice standard for scheduling. Newtown Square, PA: PMI.
Sambasivan, M., and Y. W. Soon. 2007. “Causes and effects of delays in Malaysian construction industry.” Int. J. Project Manage. 25 (5): 517–526. https://doi.org/10.1016/j.ijproman.2006.11.007.
Senouci, A., A. Alsarraj, M. Gunduz, and N. Eldin. 2017. “Analysis of change orders in Qatari construction projects.” Int. J. Constr. Manage. 17 (4): 280–292. https://doi.org/10.1080/15623599.2016.1211973.
Taylor, T. R., M. Uddin, P. M. Goodrum, A. McCoy, and Y. Shan. 2012. “Change orders and lessons learned: Knowledge from statistical analyses of engineering change orders on Kentucky highway projects.” J. Constr. Eng. Manage. 138 (12): 1360–1369. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000550.
Thomas, H. R., and C. L. Napolitan. 1995. “Quantitative effects of construction changes on labor productivity.” J. Constr. Eng. Manage. 121 (3): 290–296. https://doi.org/10.1061/(ASCE)0733-9364(1995)121:3(290).
Wambeke, B. W., S. M. Hisiana, and M. A. Liu. 2011. “Causes of variation in construction project task starting times and duration.” J. Constr. Eng. Manage. 137 (9): 663–677. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000342.

Information & Authors

Information

Published In

Go to Journal of Construction Engineering and Management
Journal of Construction Engineering and Management
Volume 145Issue 11November 2019

History

Received: Jul 16, 2018
Accepted: Feb 26, 2019
Published online: Aug 24, 2019
Published in print: Nov 1, 2019
Discussion open until: Jan 24, 2020

Permissions

Request permissions for this article.

Authors

Affiliations

Assistant Professor, Dept. of Civil Engineering, Kuwait Univ., P.O. Box 5969, Safat 13060, Kuwait; Assistant Professor, Dept. of Civil Engineering, Cairo Univ., Cairo 12613, Egypt (corresponding author). ORCID: https://orcid.org/0000-0002-8846-7398. Email: [email protected]; [email protected]
Yasmin Shalaby [email protected]
Graduate Student, Dept. of Civil Engineering, Kuwait Univ., P.O. Box 5969, Safat 13060, Kuwait. Email: [email protected]

Metrics & Citations

Metrics

Citations

Download citation

If you have the appropriate software installed, you can download article citation data to the citation manager of your choice. Simply select your manager software from the list below and click Download.

Cited by

View Options

Get Access

Access content

Please select your options to get access

Log in/Register Log in via your institution (Shibboleth)
ASCE Members: Please log in to see member pricing

Purchase

Save for later Information on ASCE Library Cards
ASCE Library Cards let you download journal articles, proceedings papers, and available book chapters across the entire ASCE Library platform. ASCE Library Cards remain active for 24 months or until all downloads are used. Note: This content will be debited as one download at time of checkout.

Terms of Use: ASCE Library Cards are for individual, personal use only. Reselling, republishing, or forwarding the materials to libraries or reading rooms is prohibited.
ASCE Library Card (5 downloads)
$105.00
Add to cart
ASCE Library Card (20 downloads)
$280.00
Add to cart
Buy Single Article
$35.00
Add to cart

Get Access

Access content

Please select your options to get access

Log in/Register Log in via your institution (Shibboleth)
ASCE Members: Please log in to see member pricing

Purchase

Save for later Information on ASCE Library Cards
ASCE Library Cards let you download journal articles, proceedings papers, and available book chapters across the entire ASCE Library platform. ASCE Library Cards remain active for 24 months or until all downloads are used. Note: This content will be debited as one download at time of checkout.

Terms of Use: ASCE Library Cards are for individual, personal use only. Reselling, republishing, or forwarding the materials to libraries or reading rooms is prohibited.
ASCE Library Card (5 downloads)
$105.00
Add to cart
ASCE Library Card (20 downloads)
$280.00
Add to cart
Buy Single Article
$35.00
Add to cart

Media

Figures

Other

Tables

Share

Share

Copy the content Link

Share with email

Email a colleague

Share