Examining Influence of Construction Projects’ Quality Factors on Client Satisfaction Using Partial Least Squares Structural Equation Modeling

Publication: Journal of Construction Engineering and Management
Volume 145, Issue 5

Abstract

Quality and client satisfaction is a long-established focus of attention in the construction industry due to its significant role in the success or failure of a project, yet few studies have examined the impact of a lack of quality on client satisfaction in the context of public construction projects. This study, therefore, proposes that lack of quality in construction projects has a significant impact on client satisfaction using a partial least squares structural equation modeling (PLS-SEM) technique. A conceptual model was developed for assessment of client satisfaction, and the model consisted of two main latent variables. Through the questionnaire survey, an empirical analysis was carried out to test the conceptual model. Data were collected from 484 construction experts employed in the Pakistani public construction industry. The result of the analysis found that the R2 value of the model was 0.454, which revealed that lack of quality in projects has a significant impact on client satisfaction. Based on the final form of the model, the construction-related factor (beta=0.491) has a greater influence on client satisfaction. The goodness of fit index of the conceptual model was measured to be 0.54, which revealed that the conceptual model has appropriate reliability and validity and fits the data correctly. This study adds to the body of knowledge by offering new insights and contributes toward greater understanding of lack of quality in public projects and its impact on client satisfaction, and use of applied advance statistical method, PLS-SEM, which is previously missing in the literature. The lessons from this study would be helpful for policymakers and decision makers to focus on highlighted issues and problems faced by the public construction industry worldwide.

Get full access to this article

View all available purchase options and get full access to this article.

Data Availability Statement

Data generated or analyzed during the study are available from the corresponding author by request. Information about the Journal’s data-sharing policy can be found here: http://ascelibrary.org/doi/10.1061/(ASCE)CO.1943-7862.0001263.

Acknowledgments

This research work was supported by the National Natural Science Foundation of China under Grant No. 71372085.

References

Abas, M., S. B. Khattak, I. Hussain, S. Maqsood, and I. Ahmad. 2015. “Evaluation of factors affecting the quality of construction projects.” Tech. J. 20 (2): 115–120. 10.15680/IJIRSET.2016.0503184.
Abdel-Razek, R. H. 1998. “Quality improvement in Egypt: Methodology and implementation.” J. Constr. Eng. Manage. 124 (5): 354–360. https://doi.org/10.1061/(ASCE)0733-9364(1998)124:5(354).
Adenuga, O. A. 2013. “Factors affecting quality in the delivery of public housing projects in Lagos State, Nigeria.” Int. J. Eng. Technol. 3 (3): 332–344.
Ahmed, S. M., and R. Kangari. 1995. “Analysis of client-satisfaction factors in construction industry.” J. Manage. Eng. 11 (2): 36–44. https://doi.org/10.1061/(ASCE)0742-597X(1995)11:2(36).
Alzahrani, J. I., and M. W. Emsley. 2013. “The impact of contractors’ attributes on construction project success: A post construction evaluation.” Int. J. Project Manage. 31 (2): 313–322. https://doi.org/10.1016/j.ijproman.2012.06.006.
Anderson, E. W., C. Fornell, and D. R. Lehmann. 1994. “Customer satisfaction, marketshare, and profitability: Findings from Sweden.” Manage. Sci. 33 (4): 525–541. https://doi.org/10.2307/1252310.
Arditi, D., and H. M. Gunaydin. 1997. “Total quality management in the construction process.” Int. J. Project Manage. 15 (4): 235–243. https://doi.org/10.1016/S0263-7863(96)00076-2.
Arditi, D., and H. M. Gunaydin. 1998. “Factors that affect process quality in the life cycle of building projects.” J. Constr. Eng. Manage. 124 (3): 194–203. https://doi.org/10.1061/(ASCE)0733-9364(1998)124:3(194).
Atkinson, A. A., J. H. Waterhouse, and R. B. Wells. 1997. “A stakeholder approach to strategic performance measurement.” MIT Sloan Manage. Rev. 38 (3): 25–38.
Band, W. A. 1991. Creating value for customers: Designing and implementing a total corporate strategy. New York: Wiley.
Barrett, P. 2000. “Systems and relationships for construction quality.” Int. J. Qual. Reliab. Manage. 17 (4/5): 377–392. https://doi.org/10.1108/02656710010298409.
Bubshait, A. A., and T. H. Al-Atiq. 1999. “ISO 9000 quality standards in construction.” J. Manage. Eng. 15 (6): 41–46. https://doi.org/10.1061/(ASCE)0742-597X(1999)15:6(41).
Calisir, F. 2007. “Factors affecting service companies’ satisfaction with ISO 9000.” Managing Serv. Qual. 17 (5): 579–593. https://doi.org/10.1108/09604520710817370.
Chan, A. P. C. 2001. Framework for measuring success of construction projects. Brisbane, Australia: Cooperative Research Centre for Construction Innovation.
Chan, A. P. C., and A. P. L. Chan. 2004. “Key performance indicators for measuring construction success.” Benchmarking 11 (2): 203–221. https://doi.org/10.1108/14635770410532624.
Chan, A. P. C., and C. M. Tam. 2000. “Factors affecting the quality of building projects in Hong Kong.” Int. J. Qual. Reliab. Manage. 17 (4): 423–441. https://doi.org/10.1108/02656710010298445.
Cherns, A. B., and D. T. Bryant. 1984. “Studying the client’s role in construction management.” Constr. Manage. Econ. 2 (2): 177–184. https://doi.org/10.1080/01446198400000016.
Chin, W. W. 1998. “The partial least squares approach to structural equation modeling.” Mod. Methods Bus. Res. 295 (2): 295–336.
Cohen, J. 1988. Statistical power analysis for the behavioral sciences. 2nd ed., 567. Mahwah, NJ: Lawrence Earlbaum Associates.
Czepiel, J. A., M. R. Solomon, C. F. Surprenant, and E. G. Gutman. 1985. “Service encounters: An overview.” In The service encounter: Managing employee/customer interaction in service businesses, 3–16. Lexington, MA: Lexington Books.
Davis, K. 2014. “Different stakeholder groups and their perceptions of project success.” Int. J. Project Manage. 32 (2): 189–201. https://doi.org/10.1016/j.ijproman.2013.02.006.
Delgado-Hernandez, D. J., and E. Aspinwall. 2008. “A framework for building quality into construction projects—Part I.” Total Qual. Manage. Bus. Excellence 19 (10): 1013–1028. https://doi.org/10.1080/14783360802264061.
Doloi, H., K. C. Iyer, and A. Sawhney. 2011. “Structural equation model for assessing impacts of contractor’s performance on project success.” Int. J. Project Manage. 29 (6): 687–695. https://doi.org/10.1016/j.ijproman.2010.05.007.
Dov, D., T. Razb, and A. J. Shenhar. 2003. “An empirical analysis of the relationship between project planning and project success project planning and project success.” Int. J. Project Manage. 21 (2): 89–95. https://doi.org/10.1016/S0263-7863(02)00012-1.
Dulaimi, M. F., A. T. Baxendale, and M. R. Jewell. 1996. “Refocusing construction to meet customer requirements.” In Proc., Organization and Management of Construction: Shaping Theory and Practice, 187–196. London: E & FN Spon.
Enshassi, A., R. M. Choudhry, and S. El-Ghandour. 2009a. “Contractors’ perception towards causes of claims in construction projects.” Int. J. Constr. Manage. 9 (1): 79–92. https://doi.org/10.1080/15623599.2009.10773123.
Enshassi, A., S. Mohamed, and S. Abushaban. 2009b. “Factors affecting the performance of construction projects in the Gaza strip.” J. Civ. Eng. Manage. 15 (3): 269–280. https://doi.org/10.3846/1392-3730.2009.15.269-280.
Falk, R. F., and N. B. Miller. 1992. A primer for soft modeling. Akron, OH: Univ. of Akron Press.
Fornell, C., and D. F. Larcker. 1981. “Evaluating structural equation models with unobservable variables and measurement error.” J. Market. Res. 18 (1): 39–50. https://doi.org/10.2307/3151312.
Gan, Y., L. Shen, J. Chen, V. Tam, Y. Tan, and I. Illankoon. 2017. “Critical factors affecting the quality of industrialized building system projects in China.” Sustainability 9 (2): 216. https://doi.org/10.3390/su9020216.
Gunduz, M., Y. Nielsen, and M. Ozdemir. 2013. “Fuzzy assessment model to estimate the probability of delay in Turkish construction projects.” J. Manage. Eng. 31 (4): 1–14. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000261.
Hair, J. F., C. M. Ringle, and M. Sarstedt. 2011. “PLS-SEM: Indeed a silver bullet.” J. Market. Theory Pract. 19 (2): 139–152. https://doi.org/10.2753/MTP1069-6679190202.
Hair, J. F., M. Sarstedt, C. M. Ringle, and J. A. Mena. 2012. “An assessment of the use of partial least squares structural equation modeling in marketing research.” J. Acad. Market. Sci. 40 (3): 414–433.
Harmon, K. M. J. 2003. “Conflicts between owner and contractors: Proposed intervention process.” J. Manage. Eng. 19 (3): 121–125. https://doi.org/10.1061/(ASCE)0742-597X(2003)19:3(121).
Hassan, A., A. Bakar, M. Y. Nizam, M. A. Tufail, and W. Virgiyanti. 2016. “Effect of knowledge management on growth performance in construction industry.” Manage. Decis. 54 (3): 735–749. https://doi.org/10.1108/MD-01-2015-0006.
Haverila, M. J., and K. Fehr. 2016. “The impact of product superiority on customer satisfaction in project management.” Int. J. Project Manage. 34 (4): 570–583. https://doi.org/10.1016/j.ijproman.2016.02.007.
Henseler, J., C. M. Ringle, and R. Sinkovics. 2009. “The use of partial least squares path modeling in international marketing.” Adv. Int. Market. 20 (3): 277–319. https://doi.org/10.1108/S1474-7979(2009)0000020014.
Hiyassat, M. A. S. 2000. “Applying the ISO standards to a construction company: A case study.” Int. J. Project Manage. 18 (4): 275–280. https://doi.org/10.1016/S0263-7863(99)00051-4.
Hoonakker, P., P. Carayon, and T. Loushine. 2010. “Barriers and benefits of quality management in the construction industry: An empirical study.” Total Qual. Manage. Bus. Excellence 21 (9): 953–969. https://doi.org/10.1080/14783363.2010.487673.
Hulland, J. 1999. “Use of partial least squares (PLS) in strategic management research: A review of four recent studies.” Strategic Manage. J. 20 (2): 195–204. https://doi.org/10.1002/(SICI)1097-0266(199902)20:2%3C195::AID-SMJ13%3E3.0.CO;2-7.
Hussain, S., Z. Fangwei, A. F. Siddiqi, Z. Ali, and M. S. Shabbir. 2018. “Structural equation model for evaluating factors affecting quality of social infrastructure projects.” Sustainability 10 (5): 1415–1425. https://doi.org/10.3390/su10051415.
ISO. 1992. International standards for quality management. ISO 9000. 2nd ed. Geneva: ISO.
Jha, K. N., and K. C. Iyer. 2006. “Critical factors affecting quality performance in construction projects.” Total Qual. Manage. Bus. Excellence 17 (9): 1155–1170. https://doi.org/10.1080/14783360600750444.
Joslin, R., and R. Müller. 2016. “The relationship between project governance and project success.” Int. J. Project Manage. 34 (4): 613–626. https://doi.org/10.1016/j.ijproman.2016.01.008.
Kamara, J. M., C. J. Anumba, and N. Evbuomwan. 2002. Capturing client requirements in construction projects. London: Thomas Telford.
Kanji, G. K., and A. Wong. 1998. “Quality culture in the construction industry.” Total Qual. Manage. 9 (4–5): 133–140. https://doi.org/10.1080/0954412988758.
Kärnä, S. 2004. “Analysing customer satisfaction and quality in construction—The case of public and private customers.” Nord. J. Surv. Real Estate Res. 2: 67–80.
Kärnä, S., J. Junnonen, and V. Sorvala. 2009. “Modelling structure of customer satisfaction with construction.” J. Facil. Manage. 7 (2): 111–127. https://doi.org/10.1108/14725960910952505.
Kometa, S. T., P. O. Olomolaiye, and F. C. Harris. 1994. “Attributes of UK construction clients influencing project consultants’ performance.” Constr. Manage. Econ. 12 (5): 433–443. https://doi.org/10.1080/01446199400000053.
Krajangsri, T., and J. Pongpeng. 2016. “Effect of sustainable infrastructure assessments on construction project success using structural equation modeling.” J. Manage. Eng. 33 (3): 4016056. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000509.
Kumaraswamy, M. M., and D. H. T. Walker. 1999. “Multiple performance criteria for evaluating construction contractors.” In Procurement systems: A guide to best practice in construction, 228–251. London: E & FN Spon.
Leung, M., S. T. Ng, and S. Cheung. 2004. “Measuring construction project participant satisfaction.” Constr. Manage. Econ. 22 (3): 319–331. https://doi.org/10.1080/01446190320000000000.
Li, T. H. Y., S. N. Thomas, and M. Skitmore. 2013. “Evaluating stakeholder satisfaction during public participation in major infrastructure and construction projects: A fuzzy approach.” Autom. Constr. 29 (1): 123–135. https://doi.org/10.1016/j.autcon.2012.09.007.
Lim, C. S., and M. Z. Mohamed. 1999. “Criteria of project success: An exploratory re-examination.” Int. J. Project Manage. 17 (4): 243–248. https://doi.org/10.1016/S0263-7863(98)00040-4.
Litwin, M. S., and A. Fink. 1995. How to measure survey reliability and validity. Thousand Oaks, CA: SAGE.
Liu, A. M. M., and A. Walker. 1998. “Evaluation of project outcomes.” Constr. Manage. Econ. 16 (2): 209–219. https://doi.org/10.1080/014461998372493.
Loushine, T. W., P. L. T. Hoonakker, P. Carayon, and M. J. Smith. 2006. “Quality and safety management in construction.” Total Qual. Manage. Bus. Excellence 17 (9): 1171–1212. https://doi.org/10.1080/14783360600750469.
Love, P. E. D., P. Mandal, and H. Li. 1999. “Determining the causal structure of rework influences in construction.” Constr. Manage. Econ. 17 (4): 505–517. https://doi.org/10.1080/014461999371420.
Luo, L. Z., C. Mao, L. Y. Shen, and Z. D. Li. 2015. “Risk factors affecting practitioners’ attitudes toward the implementation of an industrialized building system.” Eng. Constr. Archit. Manage. 22 (6): 622–643. https://doi.org/10.1108/ECAM-04-2014-0048.
Maloney, W. F. 2002. “Construction product/service and customer satisfaction.” J. Constr. Eng. Manage. 128 (6): 522–529. https://doi.org/10.1061/(ASCE)0733-9364(2002)128:6(522).
Mbachu, J., and R. Nkado. 2006. “Conceptual framework for assessment of client needs and satisfaction in the building development process.” Constr. Manage. Econ. 24 (1): 31–44. https://doi.org/10.1080/01446190500126866.
Mbachu, J. I. C. 2003. A critical study of client needs and satisfaction in the South African building industry. Gauteng, South Africa: National Research Foundation Nexus.
McDermott, P. 1999. “Strategic and emergent issues in construction procurement.” In Procurement systems: A guide to best practice in construction, 3–26. London: E & FN Spon.
Nkado, R. N., and J. I. Mbachu. 2001. “Modelling client needs and satisfaction in the built environment.” In Proc., Association of Researchers in Construction Management (ARCOM), 5–7. London: Association of Researchers in Construction Management.
Oyedele, L. O., B. E. Jaiyeoba, K. O. Kadiri, S. O. Folagbade, I. K. Tijani, and R. O. Salami. 2015. “Critical factors affecting construction quality in Nigeria: Evidence from industry professionals.” Int. J. Sustainable Build. Technol. Urban Dev. 6 (2): 103–113. https://doi.org/10.1080/2093761X.2015.1033662.
Oyewobi, L. O., R. Jimoh, B. Olanrewaju Ganiyu, and A. Adewale Shittu. 2015. “Analysis of causes and impact of variation order on educational building projects.” J. Facil. Manage. 14 (2): 139–164. https://doi.org/10.1108/JFM-01-2015-0001.
Rashvand, P., M. Zaimi, and A. Majid. 2014. “Critical criteria on client and customer satisfaction for the issue of performance measurement.” J. Manage. Eng. 30 (1): 10–18. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000183.
Rigdon, E. E. 2012. “Rethinking partial least squares path modeling: In praise of simple methods.” Long Range Plann. 45 (5–6): 341–358. https://doi.org/10.1016/j.lrp.2012.09.010.
Ringle, C. M., S. Wende, and A. Will. 2005. “SmartPLS 3.0.” Accessed November 27, 2017. http://www.smartpls.de.
Rönkkö, M., C. N. McIntosh, J. Antonakis, and J. R. Edwards. 2016. “Partial least squares path modeling: Time for some serious second thoughts.” J. Oper. Manage. 47–48 (8): 9–27. https://doi.org/10.1016/j.jom.2016.05.002.
Sambasivan, M., and Y. W. Soon. 2007. “Causes and effects of delays in Malaysian construction industry.” Int. J. Project Manage. 25 (5): 517–526. https://doi.org/10.1016/j.ijproman.2006.11.007.
Sarstedt, M., C. M. Ringle, D. Smith, R. Reams, and J. F. Hair. 2014. “Partial least squares structural equation modeling (PLS-SEM): A useful tool for family business researchers.” J. Family Bus. Strategy 5 (1): 105–115. https://doi.org/10.1016/j.jfbs.2014.01.002.
Schubring, S., I. Lorscheid, M. Meyer, and C. M. Ringle. 2016. “The PLS agent: Predictive modeling with PLS-SEM and agent-based simulation.” J. Bus. Res. 69 (10): 4604–4612. https://doi.org/10.1016/j.jbusres.2016.03.052.
Shammas-Toma, M., D. Seymour, and L. Clark. 1998. “Obstacles to implementing total quality management in the UK construction industry.” Constr. Manage. Econ. 16 (2): 177–192. https://doi.org/10.1080/014461998372475.
Shanmugapriya, S., and K. Subramanian. 2015. “Structural equation model to investigate the factors influencing quality performance in Indian construction projects.” Sadhana 40 (6): 1975–1987. https://doi.org/10.1007/s12046-015-0421-3.
Shehu, Z., I. R. Endut, A. Akintoye, and G. D. Holt. 2014. “Cost overrun in the Malaysian construction industry projects: A deeper insight.” Int. J. Project Manage. 32 (8): 1471–1480. https://doi.org/10.1016/j.ijproman.2014.04.004.
Singels, J., G. Ruël, and H. van de Water. 2001. “ISO 9000 series–Certification and performance.” Int. J. Qual. Reliab. Manage. 18 (1): 62–75. https://doi.org/10.1108/02656710110364477.
Sroufe, R., and S. Curkovic. 2008. “An examination of ISO 9000:2000 and supply chain quality assurance.” J. Oper. Manage. 26 (4): 503–520. https://doi.org/10.1016/j.jom.2007.06.006.
Tam, V. W. Y., L. Y. Shen, C. M. Tam, and W. W. S. Pang. 2007. “Investigating the intentional quality risks in public foundation projects: A Hong Kong study.” Build. Environ. 42 (1): 330–343. https://doi.org/10.1016/j.buildenv.2005.08.025.
Tan, R. R., and Y. Lu. 1995. “On the quality of construction engineering design projects: Criteria and impacting factors.” Int. J. Qual. Reliab. Manage. 12 (5): 18–37. https://doi.org/10.1108/02656719510089975.
Tang, S. L., M. Lu, and Y. L. Chan. 2003. “Achieving client satisfaction for engineering consulting firms.” J. Manage. Eng. 19 (4): 166–172. https://doi.org/10.1061/(ASCE)0742-597X(2003)19:4(166).
Tenenhaus, M., V. Esposito Vinzi, Y.-M. Chatelin, and C. Lauro. 2005. “PLS path modeling.” Comput. Stat. Data Anal. 48 (1): 159–205. https://doi.org/10.1016/j.csda.2004.03.005.
Toor, S., and S. O. Ogunlana. 2009. “Construction professionals’ perception of critical success factors for large-scale construction projects.” Constr. Innovation 9 (2): 149–167. https://doi.org/10.1108/14714170910950803.
Torbica, Z. M., and R. C. Stroh. 1999. “Impact of total quality management on home-buyer satisfaction.” J. Constr. Eng. Manage. 125 (3): 198–203. https://doi.org/10.1061/(ASCE)0733-9364(1999)125:3(198).
Torbica, Z. M., and R. C. Stroh. 2001. “Customer satisfaction in home building.” J. Constr. Eng. Manage. 127 (1): 82–86. https://doi.org/10.1061/(ASCE)0733-9364(2001)127:1(82).
Turner, A. 1990. Building procurement. London: Macmillan.
Turner, R., and R. Zolin. 2012. “Forecasting success on large projects: Developing reliable scales to predict multiple perspectives by multiple stakeholders over multiple time frames.” Project Manage. J. 43 (5): 87–99. https://doi.org/10.1002/pmj.21289.
Vinzi, V. E., W. W. Chin, J. Henseler, and H. Wang. 2010. Handbook of partial least squares: Concepts, methods and applications. New York: Springer.
Wetzels, M., G. Odekerken-Schröder, and C. Van Oppen. 2009. “Using PLS path modeling for assessing hierarchical construct models: Guidelines and empirical illustration.” MIS Quart. 33 (1): 177–195. https://doi.org/10.2307/20650284.
Yang, J., and C. Kao. 2011. “Critical path effect based delay analysis method for construction projects.” Int. J. Project Manage. 30 (3): 385–397. https://doi.org/10.1016/j.ijproman.2011.06.003.
Yang, J.-B., and S.-C. Peng. 2008. “Development of a customer satisfaction evaluation model for construction project management.” Build. Environ. 43 (4): 458–468. https://doi.org/10.1016/j.buildenv.2006.07.044.
Yeung, J. F., A. P. C. Chan, and D. W. M. Chan. 2009. “Developing a performance index for relationship-based construction projects in Australia: Delphi study.” J. Manage. Eng. 25 (2): 59–68. https://doi.org/10.1061/(ASCE)0742-597X(2009)25:2(59).
Yu, A. T. W., E. H. W. Chan, D. W. M. Chan, P. T. I. Lam, and P. W. L. Tang. 2010. “Management of client requirements for design and build projects in the construction industry of Hong Kong.” Facilities 28 (13/14): 657–672. https://doi.org/10.1108/02632771011083694.
Yung, P., and B. Yip. 2010. “Construction quality in China during transition: A review of literature and empirical examination.” Int. J. Project Manage. 28 (1): 79–91. https://doi.org/10.1016/j.ijproman.2009.03.003.

Information & Authors

Information

Published In

Go to Journal of Construction Engineering and Management
Journal of Construction Engineering and Management
Volume 145Issue 5May 2019

History

Received: Jan 22, 2018
Accepted: Nov 7, 2018
Published online: Mar 12, 2019
Published in print: May 1, 2019
Discussion open until: Aug 12, 2019

Permissions

Request permissions for this article.

Authors

Affiliations

Shahid Hussain, Ph.D. [email protected]
Assistant Professor, Dept. of Business Management and Economics, Univ. of Baltistan, Skardu, Gilgit-Baltistan 16100, Pakistan (corresponding author). Email: [email protected]; [email protected]
Zhu FangWei [email protected]
Professor, Faculty of Management and Economics, Dalian Univ. of Technology, Dalian 116024, China. Email: [email protected]
Zaigham Ali [email protected]
Assistant Professor, Dept. of Business Management, Karakoram International Univ., Gilgit-Baltistan 15100, Pakistan. Email: [email protected]

Metrics & Citations

Metrics

Citations

Download citation

If you have the appropriate software installed, you can download article citation data to the citation manager of your choice. Simply select your manager software from the list below and click Download.

Cited by

View Options

Get Access

Access content

Please select your options to get access

Log in/Register Log in via your institution (Shibboleth)
ASCE Members: Please log in to see member pricing

Purchase

Save for later Information on ASCE Library Cards
ASCE Library Cards let you download journal articles, proceedings papers, and available book chapters across the entire ASCE Library platform. ASCE Library Cards remain active for 24 months or until all downloads are used. Note: This content will be debited as one download at time of checkout.

Terms of Use: ASCE Library Cards are for individual, personal use only. Reselling, republishing, or forwarding the materials to libraries or reading rooms is prohibited.
ASCE Library Card (5 downloads)
$105.00
Add to cart
ASCE Library Card (20 downloads)
$280.00
Add to cart
Buy Single Article
$35.00
Add to cart

Get Access

Access content

Please select your options to get access

Log in/Register Log in via your institution (Shibboleth)
ASCE Members: Please log in to see member pricing

Purchase

Save for later Information on ASCE Library Cards
ASCE Library Cards let you download journal articles, proceedings papers, and available book chapters across the entire ASCE Library platform. ASCE Library Cards remain active for 24 months or until all downloads are used. Note: This content will be debited as one download at time of checkout.

Terms of Use: ASCE Library Cards are for individual, personal use only. Reselling, republishing, or forwarding the materials to libraries or reading rooms is prohibited.
ASCE Library Card (5 downloads)
$105.00
Add to cart
ASCE Library Card (20 downloads)
$280.00
Add to cart
Buy Single Article
$35.00
Add to cart

Media

Figures

Other

Tables

Share

Share

Copy the content Link

Share with email

Email a colleague

Share