Automated Productivity-Based Schedule Animation: Simulation-Based Approach to Time-Cost Trade-Off Analysis

Publication: Journal of Construction Engineering and Management
Volume 140, Issue 4

Abstract

Many studies of construction labor productivity are at a macro level. These macrolevel studies attempt to quantify the productivity or changes in productivity over the entire industry or a segment of the industry. This study is aimed at a micro or project level examination of productivity. The tool developed allows a company to predict, manage, and even optimize the productivity associated with a project or levels of projects. Automated productivity-based schedule animation (APBSA) is a dynamic scheduling methodology that stochastically utilizes weekly trended construction labor productivity data in order to automatically update the baseline schedule that was created at the beginning of the project by the construction manager. APBSA reports the construction activity duration variances and animates the progress of the job with most current data available in a four-dimensional (4D) environment. Contractors can improve their planning by utilizing APBSA with building information modeling (BIM) which will help them to improve their craft productivity. As a case study, a three-story Systems Engineering Facility III of Hanscom Air Force Base (AFB) was modeled. The model was developed in order to demonstrate the impacts of time and cost-based stochastic productivity indices on the baseline schedule. A time-cost trade-off analysis was also performed in order to show effects of duration variations on the cost of the project.

Get full access to this article

View all available purchase options and get full access to this article.

References

Akkan, C., Drexl, A., and Kimms, A. (2005). “Network decomposition-based benchmark results for the discrete time-cost tradeoff problem.” Eur. J. Oper. Res., 165(2), 339–358 [cited by Blaszczyk and Nowak (2009)].
Ang, A. (1975). “Analysis of activity network under uncertainty.” J. Eng. Mech., 101(4), 373–387 [cited by Ghazanfari et al. (2008) and Blaszczyk and Nowak (2009)].
Bennett, P. D., and Thomas, H. R. (1990). “A case study of the validity of daily crew-based productivity measurements.” M.S. thesis, Pennsylvania State Univ., University Park, PA [cited by Lee (2007)].
Bilal, S., and Thomas, H. R. (1990). “A comparative analysis of labor productivity of masons in seven countries.”, Pennsylvania State Univ., University Park, PA [cited by Lee (2007)].
Blaszczyk, T., and Nowak, M. (2009). “The time-cost trade-off analysis in construction project using computer simulation and interactive procedure.” Technol. Econ. Dev. Econ. Baltic J. Sustain., 15(4), 523–539.
Chen, P.-H. (2008). “Integration of cost and schedule using extensive matrix method and spreadsheets.” Autom. Constr., 18(1), 32–41 [cited by Blaszczyk and Nowak (2009)].
Chua, D. K. H., Chan, W. T., and Govindan, K. (1997). “A time-cost trade-off model with resource consideration using genetic algorithm.” Civ. Eng. Environ. Syst., 14(4), 291–311 [cited by Yang (2007), Ghazanfari et al. (2008), and Blaszczyk and Nowak (2009)].
Cook, J., Ellis, B., Lacey, M., Bhaumik, H., and Picard, H. (2004). “Efficient SCR construction.” Power-Gen Int. Conf. Proc.
Daneshgari, P. (2006). “Agile electrical construction. Part 1: The impact of job planning on profits.” Electrical Contractor Magazine, Power & Integrated Building Systems, 149–150.
De, P., Dunne, E. J., Ghosh, J. B., and Welles, C. E. (1995). “The discrete time-cost trade-off problem revisited.” Eur. J. Oper. Res., 81(2), 225–238 [cited by Feng et al. (1997) and Yang (2007)].
Dobin, B. N. (1985). “Bounding the project completion time distribution in PERT networks.” Oper. Res., 33(4), 862–881 [cited by Feng et al. (1997)].
Elmaghraby, S. E. (1977). Activity networks—Project planning and control by network models, Wiley, New York [cited by Blaszczyk and Nowak (2009)].
Feng, C.-W., Liu, L., and Burns, S. A. (1997). “Using genetic algorithms to solve construction time-cost trade-off problems.” J. Comput. Civ. Eng., 184–189 [cited by Feng et al. (1997), Yang (2007), Eshtehardian et al. (2008), and Ghazanfari et al. (2008)].
Feng, C.-W., Liu, L., and Burns, S. A. (2000). “Stochastic construction time-cost trade-off analysis.” J. Comput. Civ. Eng., 117–126 [cited by Ezeldin and Soliman (2009)].
Fulkerson, D. R. (1961). “A network flow computation for project cost curves.” Manage. Sci., 7(2), 167–178 [cited by Yang (2007) and Blaszczyk and Nowak (2009)].
Gelisen, G., and Griffis, F. H. (Bud). (2010). “Automated productivity based schedule animation (APBSA) case study: Systems engineering facility III, Hanscom AFB, MA.” Proc., Project Management Institute College of Scheduling Conf. (PMICOS10), Gantt CPM & Beyond, Calgary.
Ghazanfari, M., Shahanaghi, K., and Yousefli, A. (2008). “An application of possibility goal programming to the time-cost trade off problem.” J. Uncertain Syst., World Acad. Union, 2(1), 22–30.
Gillespie, L. (2010). “Picone/Skanska–Newtown Creek.” Construction Today, Feb. 22. 〈http://www.construction-today.com/cms1/content/view/1858/104〉 (Apr. 24, 2010).
Goldratt, E. (1997). Critical chain, North River Press, Great Barrington, MA [cited by Blaszczyk and Nowak (2009)].
Gonzalez, V., Alarcon, L. F., Maturana, S., Mundaca, F., and Bustamante, J. (2010). “Improving planning reliability and project performance using the reliable commitment model.” J. Constr. Eng. Manage., 1129–1139.
Gonzalez, V., Alarcon, L. F., and Molenaar, K. (2009). “Multiobjective design of work-in-process buffer for scheduling repetitive building projects.” Automat. Constr., 18(2), 95–108.
Griffis, F. H. (Bud), and Farr, J. V. (2000). Construction planning for engineers, McGraw-Hill, New York, 86–87, 150–151, 195–199, 208–209, 243–244.
Grimm, C. T., and Norman, K. W. (1974). “Weather effects on mason productivity.” J. Constr. Div.: Proc. (ASCE), 100(CO3), 319–335 [cited by Lee (2007)].
Haas, C. T., Borcherding, J. D., Allmon, E., and Goodrum, P. M. (1999). “US Construction labor productivity trends and technology impacts, 1970–1998.”, Center for Construction Industry Studies (CCIS), Univ. of Texas, Austin, TX.
Harris, R. B. (1978). Precedence and arrow networking techniques for construction, Wiley, New York, NY [cited by Liu et al. (1995) and Feng et al. (1997)].
Hasegawa, Y. (2006). “Construction automation and robotics in 21st century.” 23rd Int. Symp. on Automation and Robotics in Construction (ISARC), International Association for Automation and Robotics in Construction (IAARC), Goyang-Si, Republic of Korea, 565–568.
Kelly, J. E., Jr. (1961). “Critical path planning and scheduling: Mathematical basis.” Oper. Res., 9(3), 167–179, 296–320 [cited by Feng et al. (1997), Ghazanfari et al. (2008), and Blaszczyk and Nowak (2009)].
Kidd, J. B. (1987). “A comparison between the VERT program and other method of project duration estimation.” Omega-Int. J. Manage. Sci., 15(2), 129–134 [cited by Feng et al. (1997)].
Koehn, E., and Brown, G. (1985). “Climatic effects on construction.” J. Constr. Eng. Manage., 129–137 [cited by Lee (2007)].
Kuipers, E. J. (1976). “A method of forecasting the efficiency of construction labor in any climatological conditions.” Ph.D. dissertation, Univ. of Illinois at Urbana-Champaign, Champaign, IL, 178 [cited by Lee (2007)].
Lee, Seulkee. (2007). “Understanding and quantifying the impact of changes on construction labor productivity factors and quantification methods.” Ph.D. dissertation, Univ. of California–Berkeley, Berkeley, CA, 61–65, 213–214, 498–499.
Liu, J., and Rahbar, F. (2004). “Project time-cost trade-off optimization by maximal flow theory.” J. Constr. Eng. Manage., 607–609.
Mao, H. (1999). “Estimating labour productivity using fuzzy set theory.” M.S. thesis, Univ. of Alberta-Edmonton, Edmonton, AB, Canada.
Meyer, W. L., and Shaffer, L. R. (1965). “Extending CPM for multiform project time-cost curves.” J. Constr. Div., 91(C01), 45–67 [cited by Ghazanfari et al. (2008)].
Mojahed, S. (2005). “A project improvement system for effective management of construction projects.” Ph.D. dissertation, Louisiana State Univ. and Agricultural and Mechanical College, Baton Rouge, LA.
Moselhi, O., Assem, I., and El-Rayes, K. (2005). “Change orders impact on labor productivity.” J. Constr. Eng. Manage., 354–359.
NECA (1974). “The Effect of Temperature on Productivity.”, National Electrical Contractors Association, Bethesda, MD (republished in 2004, Index No. 5072-04) [cited by Lee (2007)].
Newtown Creek Wastewater Treatment Plant (NC WPCP). (2010). 〈http://www.nyc.gov/html/dep/html/environmental_education/newtown_wwtp.shtml〉 (Jan. 6, 2010).
Olson, R. C. (1992). “The importance of planning.” AGC productivity improvement bulletin III, Vol. 17, Associated General Contractors of America, Washington, DC, 4–5.
Picard, H. E. (2005). “Construction productivity qualifications.” 3rd Int. Structural Engineering and Construction Conf. (ISEC-03), Taylor & Francis Group, London.
Proctor & Gamble BRT. (1974). “Effect of scheduled overtime on construction projects.” Coming to grips with some major problems in the construction industry, Proctor & Gamble Business Round Table, New York (republished in 1980) [cited by Lee (2007)].
Reda, R. M., and Carr, R. I. (1989). “Time-cost trade-off among related activities.” J. Constr. Eng. Manage., 475–486 [cited by Liu et al. (1995)].
@RISK. (2004). Risk Analysis Add-in for Microsoft Excel (Version 4.5.3), Palisade Corporation, Ithaca, New York.
Rowings, J. E., Jr, and Sonmez, R. (1996). “Labor productivity modeling with neural networks.” Transacations of American Association of Cost Engineers (AACE) International, 40th Annual Meeting, PROD.1.1–PROD.1.3.
Sanders, S. R., Thomas, H. R., and Smith, G. R. (1989). “An analysis of factors affecting labor productivity in masonry construction.”, Pennsylvania State Univ., University Park, PA. Cited by Lee (2007).
Sanvido, V. E. (1988). “Conceptual construction process model.” J. Constr. Eng. Manage., 294–311.
Seals, R., and Rodriguez, J. (1980). “Scheduled overtime effect on construction projects.” Cost Eng., 48(7), 16–22.
Sklerov, F., and Roman, A. (2010). “DEP opens visitor center at Newtown Creek.” 〈http://www.nyc.gov/html/dep/html/press_releases/10-40pr.shtml〉 (Apr. 24, 2010).
Talbot, F. B. (1982). “Resource-constrained project scheduling with time-resource tradeoffs: The non-preemptive case.” Manage. Sci., 28(10), 197–210 [cited by Ghazanfari et al. (2008)].
Teicholz, P. (2004). “Labor productivity declines in the construction industry: Causes and remedies.” AECbytes, Viewpoint #4.
Thomas, H. R., and Smith, G. R. (1990). “Loss of construction labor productivity due to inefficiencies and disruptions: The weight of expert opinion.”, Pennsylvania Transportation Institute, Pennsylvania State Univ., University Park, PA Cited by Lee (2007).
Tucker, W. W. (2003). “Construction productivity study.” 〈http://mitripartite.com/survey.htm〉 (Jan. 6, 2010).
U.S. Dept. of Labor, Bureau of Labor Statistics. (2010). “Consumer Price Index: All Urban Consumers, U.S. City Average.” 〈ftp://ftp.bls.gov/pub/special.requests/cpi/cpiai.txt〉 (Jan. 6, 2010).
Wan, Y. (1994). “Resource allocation for a stochastic CPM-type network through perturbation analysis.” Eur. J. Oper. Res., 79(2), 239–248 [cited by Feng et al. (1997)].
Weather Underground. (2010). “History for KNYNEWYO17.” 〈http://www.wunderground.com/weatherstation/WXDailyHistory.asp?ID=KNYNEWYO17〉 (Jan. 6, 2010).
Weiss, G. (1986). “Stochastic bounds on distributions of optimal value functions with applications to PERT, network flows and reliability.” Oper. Res., 34(4), 595–605 [cited by Feng et al. (1997)].

Information & Authors

Information

Published In

Go to Journal of Construction Engineering and Management
Journal of Construction Engineering and Management
Volume 140Issue 4April 2014

History

Received: Dec 14, 2010
Accepted: Jan 2, 2013
Published online: Dec 27, 2013
Published in print: Apr 1, 2014
Discussion open until: May 27, 2014

Permissions

Request permissions for this article.

Authors

Affiliations

Gokhan Gelisen, Ph.D. [email protected]
P.E.
M.ASCE
Cost Manager, Skanska USA Civil Northeast, Inc., 5214 39th Ave., Unit 2C, Queens, NY 11377 (corresponding author). E-mail: [email protected]
F. H. (Bud) Griffis, Ph.D. [email protected]
P.E.
F.ASCE
Professor, Civil Engineering, Center for Construction Management Technology, Rogers Hall 407, Polytechnic Institute of New York Univ., Brooklyn, NY 11201. E-mail: [email protected]

Metrics & Citations

Metrics

Citations

Download citation

If you have the appropriate software installed, you can download article citation data to the citation manager of your choice. Simply select your manager software from the list below and click Download.

Cited by

View Options

Get Access

Access content

Please select your options to get access

Log in/Register Log in via your institution (Shibboleth)
ASCE Members: Please log in to see member pricing

Purchase

Save for later Information on ASCE Library Cards
ASCE Library Cards let you download journal articles, proceedings papers, and available book chapters across the entire ASCE Library platform. ASCE Library Cards remain active for 24 months or until all downloads are used. Note: This content will be debited as one download at time of checkout.

Terms of Use: ASCE Library Cards are for individual, personal use only. Reselling, republishing, or forwarding the materials to libraries or reading rooms is prohibited.
ASCE Library Card (5 downloads)
$105.00
Add to cart
ASCE Library Card (20 downloads)
$280.00
Add to cart
Buy Single Article
$35.00
Add to cart

Get Access

Access content

Please select your options to get access

Log in/Register Log in via your institution (Shibboleth)
ASCE Members: Please log in to see member pricing

Purchase

Save for later Information on ASCE Library Cards
ASCE Library Cards let you download journal articles, proceedings papers, and available book chapters across the entire ASCE Library platform. ASCE Library Cards remain active for 24 months or until all downloads are used. Note: This content will be debited as one download at time of checkout.

Terms of Use: ASCE Library Cards are for individual, personal use only. Reselling, republishing, or forwarding the materials to libraries or reading rooms is prohibited.
ASCE Library Card (5 downloads)
$105.00
Add to cart
ASCE Library Card (20 downloads)
$280.00
Add to cart
Buy Single Article
$35.00
Add to cart

Media

Figures

Other

Tables

Share

Share

Copy the content Link

Share with email

Email a colleague

Share