HSM-Simulation–Based Planning Method for Construction Projects
Publication: Journal of Construction Engineering and Management
Volume 121, Issue 3
Abstract
Construction projects are characterized by the random nature of the conditions under which they are implemented and by the dynamic use of available resources. Since site conditions vary randomly and resources perform a multitude of functions on various work tasks, planning of construction projects using traditional tools like the critical path method becomes limited and induces deficiency in the resulting plan. This paper demonstrates that a simulation-based methodology is appropriate for modeling such a scenario. The hierarchical simulation modeling (HSM) method, a simulation-based method, for planning of construction projects is presented. HSM enhances and combines the concepts of work breakdown structure and process modeling to arrive at an advanced framework for planning. Hierarchical and modular simulation constructs form the basis of this method. The construction of a bridge (Peace River Bridge) is used to illustrate HSM concepts and its advantages.
Get full access to this article
View all available purchase options and get full access to this article.
References
1.
AbouRizk, S. M., and Dozzi, S. P.(1992). “Applications of simulation in resolving construction disputes.”J. Constr. Engrg. and Mgmt., ASCE, 119(2), 355–373.
2.
Ahuja, N. T. H., and Nandakumar, V.(1985). “Simulation model to forecast project completion time.”J. Constr. Engrg. and Mgmt., ASCE, 111(4), 325–342.
3.
Carr, R. I.(1979). “Simulation of construction project duration.”J. Constr. Engrg. and Mgmt., ASCE, 105(2), 117–128.
4.
Dabbas, M., and Halpin, D. W. (1982). “Integrated project and process management.”J. Constr. Div., ASCE 109(1), 361–373.
5.
Halpin, D. W.(1977). “CYCLONE: method for modeling of job site processes.”J. Constr. Div., ASCE, 103(3), 489–499.
6.
Halpin, D. W. (1990). MicroCYCLONE user's manual . Div. of Constr. Engrg. and Mgmt., Purdue University, West Lafayette, Ind.
7.
Luna, J. (1992). “Hierarchical, modular concepts applied to an object-oriented simulation model development environment.”Proc., Winter Simulation Conf., IEEE, New York, N.Y., 694–699.
8.
Microsoft visual basic—programmer's guide. Version 3.0. (1993a). Microsoft Corp., Redmond, Wash.
9.
Microsoft visual C++—user's guide. Version 1.0. (1993b). Microsoft Corp., Redmond, Wash.
10.
Odeh, A. M., Tommelein, I. D., and Carr, R. I. (1992). “Knowledge-based simulation of construction plans.”Proc., Eighth Conf. on Comp. in Civ. Engrg., ASCE, New York, N.Y., 1042–1049.
11.
Pritsker, A. A. B. (1986). Introduction to simulation and SLAM II . Second Ed., Wiley and Pritsker Associates, New York, N.Y., and West Lafayette, Ind.
12.
Pritsker, A., Sigal, C., and Hammesfahr, R. (1989). SLAM II network models for decision support . Prentice Hall, Inc., Englewood Cliffs, N.J.
13.
Riggs, L. S.(1989). “Risk management in CPM network.”Microcomp. in Civ. Engrg., 3(3), 229–235.
14.
Sawhney, A. (1994). “Simulation based planning method for construction,” PhD thesis, University of Alberta, Edmonton, Alberta, Canada.
15.
Woolery, J. C., and Crandall, K. C.(1983). “Stochastic network model for planning scheduling.”J. Constr. Engrg. and Mgmt., ASCE, 109(3), 342–354.
Information & Authors
Information
Published In
Copyright
Copyright © 1995 American Society of Civil Engineers.
History
Published online: Sep 1, 1995
Published in print: Sep 1995
Authors
Metrics & Citations
Metrics
Citations
Download citation
If you have the appropriate software installed, you can download article citation data to the citation manager of your choice. Simply select your manager software from the list below and click Download.