Simulation of Learning Development in Repetitive Construction
Publication: Journal of Construction Engineering and Management
Volume 120, Issue 4
Abstract
This paper presents the methodology used to model the learning development phenomenon in the CYCLONE format using the Boeing learning curve. The learning development enhancement was coded in the MicroCYCLONE (a microcomputer version of CYCLONE) environment using QuickBASIC programming. The enhancement allows the user to specify the rate of learning expressed as a percentage, the realization count required for the task duration to increment due to learning, and the threshold at which no more learning improvement can be realized. The existing routines for generating deterministic durations and stochastic durations based on uniform, triangular, and beta distributions were upgraded to calculate durations that reflect the impact of learning development. The learning development enhancement can be extended for use with other simulation programs based on the CYCLONE modeling format. The developed learning‐development enhancement was used to model and simulate the learning‐development phenomenon for linear construction operation illustrative examples. Findings from the simulation experimentation performed for the illustrative examples are provided. The significance, capabilities, and implementation of the learning‐development enhancement are discussed.
Get full access to this article
View all available purchase options and get full access to this article.
References
1.
Alden, R. (1974). “Learning curves: an example.” Industrial Engrg., 6(12), 34–37.
2.
Carlson, J. (1973). “Cubic learning curves: precision tool for labor estimating.” Manufacturing Engrg. and Mgmt., Nov. 22–25.
3.
Chang, D. Y.‐M. (1986). “RESQUE: a resource based simulation system for construction process planning,” PhD thesis, University of Michigan, Ann Arbor, Mich.
4.
Cochran, E. (1960). “New concept of the learning curve.” J. Industrial Engrg., July– August, 317–327.
5.
Cunningham, J. (1980). “Using the learning curve as a management tool.” IEEE Spectrum, 45–48.
6.
Halpin, D. W. (1973). “An investigation of the use of simulation networks for modeling construction operations,” PhD thesis, University of Illinois, Urbana, Ill.
7.
Halpin, D. W. (1990). MicroCYCLONE user's manual. Div. of Constr. Engrg. and Mgmt., Purdue University, West Lafayette, Ind.
8.
Hijazi, A. (1989). “Simulation analysis of linear construction processes,” PhD thesis, Purdue University, West Lafayette, Ind.
9.
Ioannou, P. G. (1989). UM‐CYCLONE user's guide, Dept. of Civ. Engrg., University of Michigan, Ann Arbor, Mich.
10.
Kalk, A. (1980). “INSIGHT‐interactive simulation of construction operations using graphical techniques.” Tech. Rep. No. 238, Dept. of Civ. Engrg., Stanford University, Stanford, Calif.
11.
Lluch, J. F. (1981). “Analysis of construction operations using microcomputers,” PhD thesis, Georgia Institute of Technology, Atlanta, Ga.
12.
Lutz, J. D. (1990). “Planning of linear construction projects using simulation and line of balance,” PhD thesis, Purdue University, West Lafayette, Ind.
13.
Spencer, W. (1986). “Comparing learning curves.” Production Engrg., May, 56–58.
14.
Tanner, J. (1985). “The learning curve.” Production Engrg., May, 72–78.
15.
Thomas, H. R., Mathews, C. T., and Ward, J. G. (1986). “Learning curve models of construction productivity.” J. Constr. Engrg. and Mgmt., ASCE, 112(2), 245–258.
Information & Authors
Information
Published In
Copyright
Copyright © 1994 American Society of Civil Engineers.
History
Received: Mar 30, 1992
Published online: Dec 1, 1994
Published in print: Dec 1994
Authors
Metrics & Citations
Metrics
Citations
Download citation
If you have the appropriate software installed, you can download article citation data to the citation manager of your choice. Simply select your manager software from the list below and click Download.