Errata for “Improved Baseline Productivity Analysis Technique” by Chien-Liang Lin and Hong-Ming Huang

You are viewing the correction.
VIEW THE CORRECTED ARTICLE
Publication: Journal of Construction Engineering and Management
Volume 136, Issue 9
The following corrections should be made to the original paper:
1.
In Table 3, productivities for workdays 34 and 35 should not be considered DEA-classified baseline productivity, owing to the existence of slacks.
a.
Accordingly, in the old Table 4, the two figures (2.89 and 2.89) for workdays 34 and 35 (column 5) should be removed, and the eventually derived BP of DEA should be 1.95, not 2.10, as shown in the bottom of column 5.
b.
Based on the aforementioned corrections, the data in column 2 of Table 5 should be corrected accordingly.
2.
Four lines before and one line after Eq. (9) and in the notation list, “output excesses” should be changed to “output shortfalls” and “input shortfalls” should be corrected as “input excesses.”
Table 3. Daily Productivity and DEA Performance—Case Projecta
(1)(2)(3)(4)(5)(6)(7)(8)(9)(10)(11)(12)(13)(14)
Conversion factor11.763.650.5310.66Converted dailyDEAAllslacks =0
Work-dayWork-hoursPenetrations(each)Firedamper(each)Branchduct(ft)Feeder duct
SmallLargeOutputProd.Output oriented
(ft)(ft)(m)(wh/m)CCRBCCSEb
14040.000.00.047.014.32.79 1.00 1.00 1.00 Yes
24001.230.60.00.020.66.36.360.280.380.73 
34000.055.10.00.029.28.94.490.350.590.60 
44000.086.30.00.045.713.92.890.550.920.60 
54003.0400.00.032.29.84.070.460.570.81 
62400.067.50.00.035.810.92.200.720.721.00 
72400.093.60.00.049.615.11.57 1.00 1.00 1.00 Yes
82400.045.90.00.024.37.43.250.490.491.00 
92401.623.30.00.018.25.54.330.430.800.54 
102400.0017.32.318.75.74.200.661.000.66 
112400.027.24.51.519.96.13.970.370.950.39 
122402.028.70.00.022.56.93.510.541.000.54 
134000.041.70.03.024.17.35.450.330.480.68 
144000.080.20.00.042.513.03.080.510.860.60 
154000.054.75.10.034.110.43.840.380.630.61 
162402.025.10.00.020.66.33.810.501.000.50 
172400.090.96.80.054.916.71.44 1.00 1.00 1.00 Yes
182401.416.31.51.516.25.04.850.391.000.39 
192400.026.30.00.013.94.35.640.280.281.00 
202402.0580.00.038.011.62.070.851.000.85 
212400.0030.00.030.09.22.62 1.00 1.00 1.00 Yes
222400.0600.00.031.89.72.460.640.641.00 
234000.024.322.312.043.113.23.050.700.790.89 
244000.065.319.029.973.322.41.80 1.00 1.00 1.00 Yes
254000.018.80.020.323.37.15.640.680.681.00 
264000.04711.320.749.915.22.620.700.710.99 
274000.034.57.32.327.18.24.890.340.470.72 
284000.039.65.423.642.012.83.120.790.791.00 
293200.0038.10.838.611.82.720.961.000.96 
304000.011.935.20.041.512.73.150.761.000.76 
314000.056.716.20.046.214.12.850.610.860.71 
324000.033.90.00.018.05.57.310.220.360.60 
3340010.049.40.00.062.719.12.10 1.00 1.00 1.00 Yes
34c40010.016.90.00.045.513.92.891.001.001.00No
35c40010.016.90.00.045.513.92.891.001.001.00No
362400.076.80.00.040.712.41.940.820.821.00 
372400.049.50.00.026.28.02.990.530.531.00 
Total1,216443.21,4932201181,2943943.08    
a
Boldface indicates baseline subset identified by DEA.
b
SE=Scale efficiency=CCRBCC
c
Slack>0 , so not fully CCR efficient
Table 4. Baseline Productivity Sets Derived from Different BP Methods
(1)(2)(3)(4)(5)(6)(7)(8)(9)
Work-dayWork-hoursDailyoutput(m)Baseline productivity set
ThomasDEAK-meansZinkControl chart
2 STD3 STD
Iteration 4Iteration 1
14014.3 2.792.79 2.792.79
2406.3     6.36
3408.9    4.494.49
44013.9  2.89 2.892.89
5409.8    4.074.07
62410.9  2.2 2.22.2
72415.11.571.571.57 1.571.57
8247.4  3.25 3.253.25
9245.5    4.334.33
10245.7    4.24.2
11246.1  3.97 3.973.97
12246.9  3.51 3.513.51
13407.3     5.45
144013.0  3.08 3.083.08
154010.4  3.84 3.843.84
16246.3  3.81 3.813.81
172416.71.441.441.44 1.441.44
18245.0    4.854.85
19244.3     5.64
202411.6  2.07 2.072.07
21249.2 2.622.62 2.622.62
22249.7  2.46 2.462.46
234013.2  3.05 3.053.05
244022.41.801.801.80 1.801.80
25407.1     5.64
264015.22.62 2.622.622.622.62
27408.2   4.894.894.89
284012.8  3.123.123.123.12
293211.8  2.722.722.722.72
304012.7  3.153.153.153.15
314014.1  2.852.852.852.85
32405.5     7.31
334019.12.102.102.10 2.102.10
344013.9  2.89 2.892.89
354013.9  2.89 2.892.89
362412.4  1.94 1.941.94
37248.0  2.99 2.992.99
  BP1.801.952.753.103.083.48
Table 5. Summary of Different BP Methods
 (1)(2)(3)(4)(5)(6)
ThomasDEAK-meansZinkControl chart
2 STD3 STD
(1) Number of BP days562663237
(2)=(1)37 (%)1416701686100
(3) # of BP days between days 7 and 26441411720
(4)=(3)(1) (%)806754175354
(5) BP (wh/m)1.81.952.753.103.083.48
(6)=(5)AP a (%)586389101100113
(7) Rank123546
a
AP=Average Productivity=1,216394.4=3.08 (wh/m)

Information & Authors

Information

Published In

Go to Journal of Construction Engineering and Management
Journal of Construction Engineering and Management
Volume 136Issue 9September 2010
Pages: 1062 - 1063

History

Received: Feb 20, 2010
Accepted: Apr 19, 2010
Published online: Aug 13, 2010
Published in print: Sep 2010

Permissions

Request permissions for this article.

Authors

Affiliations

Chien-Liang Lin, Ph.D.
Assistant Professor, Dept. of Construction Engineering, National Kaohsiung First Univ. of Science and Technology, 2 Jhuo-yue Rd. Nanzih, Kaohsiung 811, Taiwan (corresponding author). E-mail: [email protected]
Hong-Ming Huang, Ph.D.
Senior Project Manager, United Steel Engineering and Construction Corp., 1 Zhong-gang Rd., Shiao-gang, Kaohsiung 812, Taiwan.

Metrics & Citations

Metrics

Citations

Download citation

If you have the appropriate software installed, you can download article citation data to the citation manager of your choice. Simply select your manager software from the list below and click Download.

View Options

Media

Figures

Other

Tables

Share

Share

Copy the content Link

Share with email

Email a colleague

Share