Technical Papers
Sep 8, 2023

Prefabricated and Prefinished Volumetric Construction: Assessing Implementation Status, Perceived Benefits, and Critical Risk Factors in the Singapore Built Environment Sector

Publication: Journal of Management in Engineering
Volume 39, Issue 6

Abstract

Prefinished prefabricated volumetric construction (PPVC) represents an innovative approach within the Design for Manufacturing and Assembly (DfMA) framework aimed at enhancing efficiency in the built environment sector. Despite its promising potential, research on PPVC adoption and its associated benefits remains scarce. This study evaluated the existing level of PPVC adoption in Singapore’s built environment industry; investigated perceived benefits at industry, organizational, and project levels; and examined project performance indicators and critical risk factors related to PPVC. A comprehensive literature review yielded 28 performance risk factors, which informed a survey questionnaire targeting major disciplines within the industry. Analysis of survey data, coupled with postsurvey interviews, revealed that 57.45% of respondents had not yet participated in PPVC projects, and 55.32% of companies anticipated involvement in at least one PPVC project within the next 3 years. Respondents acknowledged the advantages of PPVC and its positive impact on cost, schedule, and quality performance. The top three risks associated with PPVC projects were found to be Volatile Economic and Social Conditions (C5), Poor Jointing (B3), and Delay in Module Delivery and Transportation (A1). These findings contribute to the scholarly discourse on strategies to increase PPVC adoption and inform policy-making, promoting a more efficient built environment sector.

Get full access to this article

View all available purchase options and get full access to this article.

Data Availability Statement

Some or all data, models, or code that support the findings of this study are available from the corresponding author upon reasonable request.

References

Alaloul, W. S., M. S. Liew, N. A. W. A. Zawawi, and I. B. Kennedy. 2020. “Industrial Revolution 4.0 in the construction industry: Challenges and opportunities for stakeholders.” Ain Shams Eng. J. 11 (1): 225–230. https://doi.org/10.1016/j.asej.2019.08.010.
Armstrong, J. S., and T. S. Overton. 1977. “Estimating nonresponse bias in mail surveys.” J. Mark. Res. 14 (3): 396. https://doi.org/10.1177/002224377701400320.
Azhar, S., M. Y. Lukkad, and I. Ahmad. 2013. “An investigation of critical factors and constraints for selecting modular construction over conventional stick-built technique.” Int. J. Construct. Educ. Res. 9 (3): 203–225. https://doi.org/10.1080/15578771.2012.723115.
Badir, Y. F., M. R. A. Kadir, and A. H. Hashim. 2002. “Industrialized building systems construction in Malaysia.” J. Archit. Eng. 8 (1): 19–23. https://doi.org/10.1061/(ASCE)1076-0431(2002)8:1(19).
BCA (Building and Construction Authority). 2017. “PPVC guidebook.” Accessed January 9, 2023. https://www1.bca.gov.sg/docs/default-source/docs-corp-buildsg/ppvc_guidebook.pdf?sfvrsn=1a7b4580_2.
BCA (Building and Construction Authority). 2019. “Prefabricated prefinished volumetric construction (PPVC) information toolkit.” Accessed January 8, 2023. https://www1.bca.gov.sg/docs/default-source/docs-corp-buildsg/productivity/ppvc_info_kit.pdf?sfvrsn=e716e287_0.
BCA (Building and Construction Authority). 2020. “Generating demand for DfMA projects.” Accessed January 10, 2023. https://www1.bca.gov.sg/buildsg/productivity/design-for-manufacturing-and-assembly-dfma/generating-demand-for-dfma-projects.
BCA (Building and Construction Authority). 2021. “How digital transformation empowers us to build better.” Accessed January 8, 2023. https://www1.bca.gov.sg/buildsg-emag/articles/how-digital-transformation-empowers-us-to-build-better.
BCA (Building and Construction Authority). 2023. “Prefabricated prefinished volumetric construction (PPVC).” Accessed January 10, 2023. https://www1.bca.gov.sg/buildsg/productivity/design-for-manufacturing-and-assembly-dfma/prefabricated-prefinished-volumetric-construction-ppvc.
Bertram, N., J. L. Blanco, and J. Mischke. 2019. Voices on infrastructure: Scaling modular construction. Montreal, QC, Canada: Global Infrastructure Initiative.
Bronte-Stewart, M. 2015. “Beyond the iron triangle: Evaluating aspects of success and failure using a project status model.” Comput. Inf. Syst. 19 (2): 19–36.
Chaillan, G. 2017. “New possibilities in modular construction.” Accessed January 9, 2023. https://www.constructionplusasia.com/sg/new-possibilities-modular-construction/.
CHAS (Contractors Health and Safety Assessment Scheme). 2021. “The impact of COVID-19 on the construction industry (according to business owners).” Accessed January 9, 2023. https://www.chas.co.uk/blog/covid-impact-on-construction-industry/.
Chen, C., J. Han, Z. Liu, R. Lee, and K. Tiong. 2023. “Flow shop scheduling of hybrid make-to-stock and make-to-order in a distributed precast concrete production system.” Cleaner Logist. Supply Chain 7 (Jun): 100106. https://doi.org/10.1016/j.clscn.2023.100106.
Chiang, Y. H., E. H.-W. Chan, and L. Ka-Leung Lok. 2006. “Prefabrication and barriers to entry—A case study of public housing and institutional buildings in Hong Kong.” Habitat Int. 30 (3): 482–499. https://doi.org/10.1016/j.habitatint.2004.12.004.
Chiew, S. P. 2019. “PPVC—A DfMA game-changing technology for Singapore.” Accessed January 9, 2023. https://www.polyu.edu.hk/cnerc-steel/images/research/resources/technical-seminar-on-mic/05.pdf.
De La Torre, M. L. 1994. A review and analysis of modular construction practices. Bethlehem, PA: Lehigh Univ.
Enshassi, M. S. A., S. Walbridge, J. S. West, and C. T. Haas. 2019. “Integrated risk management framework for tolerance-based mitigation strategy decision support in modular construction projects.” J. Manage. Eng. 35 (4): 05019004. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000698.
Gerardi, J. 2021. “Understanding cost performance indexes.” Accessed January 9, 2023. https://proest.com/construction/process/cost-performance-index/.
Gilbert, R. I. 2011. “The serviceability limit states in reinforced concrete design.” Procedia Eng. 14 (Jan): 385–395. https://doi.org/10.1016/j.proeng.2011.07.048.
Goh, M., and Y. M. Goh. 2019. “Lean production theory-based simulation of modular construction processes.” Autom. Constr. 101 (Jun): 227–244. https://doi.org/10.1016/j.autcon.2018.12.017.
Groves, R. M., and E. Peytcheva. 2008. “The impact of nonresponse rates on nonresponse bias: A meta-analysis.” Public Opin. Q. 72 (2): 167–189. https://doi.org/10.1093/poq/nfn011.
Hassim, S., M. S. Jaafar, and S. A. Abu Hasan Sazalli. 2009. “The contractor perception towers industrialised building system risk in construction projects in Malaysia.” Am. J. Appl. Sci. 6 (5): 937–942. https://doi.org/10.3844/ajassp.2009.937.942.
Ho, K. M., J. P. Lam, and M. Shea. 2018. “Pre-fabricated pre-finished volumetric construction (PPVC) for residential projects.” Accessed January 10, 2023. https://www.surbanajurong.com.cn/wp-content/uploads/2018/08/1.-PPVC-Final-_18Sep18.pdf.
Hossain, M. 2019. “IPS & PPVC precast system in construction-a case study in Singaporean housing building project.” J. Syst. Manage. Sci. 9 (2): 23–42.
Hsu, P.-Y., P. Angeloudis, and M. Aurisicchio. 2018. “Optimal logistics planning for modular construction using two-stage stochastic programming.” Autom. Constr. 94 (May): 47–61. https://doi.org/10.1016/j.autcon.2018.05.029.
Hwang, B. G., J. Ngo, and P. W. Y. Her. 2020. “Integrated digital delivery: Implementation status and project performance in the Singapore construction industry.” J. Cleaner Prod. 262 (Jul): 121396. https://doi.org/10.1016/j.jclepro.2020.121396.
Hwang, B. G., M. Shan, and K. Y. Looi. 2018a. “Key constraints and mitigation strategies for prefabricated prefinished volumetric construction.” J. Cleaner Prod. 183 (May): 183–193. https://doi.org/10.1016/j.jclepro.2018.02.136.
Hwang, B. G., M. Shan, and K. Y. Looi. 2018b. “Knowledge-based decision support system for prefabricated prefinished volumetric construction.” Autom. Constr. 94 (Dec): 168–178. https://doi.org/10.1016/j.autcon.2018.06.016.
Hwang, B. G., X. Zhao, and L. P. Toh. 2014. “Risk management in small construction projects in Singapore: Status, barriers and impact.” Int. J. Project Manage. 32 (1): 116–124. https://doi.org/10.1016/j.ijproman.2013.01.007.
Jaillon, L., and C. S. Poon. 2008. “Sustainable construction aspects of using prefabrication in dense urban environment: A Hong Kong case study.” Construct. Manage. Econ. 26 (9): 953–966. https://doi.org/10.1080/01446190802259043.
Jeong, G., H. Kim, H. S. Lee, M. Park, and H. Hyun. 2022. “Analysis of safety risk factors of modular construction to identify accident trends.” J. Asian Archit. Build. Eng. 21 (3): 1040–1052. https://doi.org/10.1080/13467581.2021.1877141.
Jin, R., S. Gao, A. Cheshmehzangi, and E. Aboagye-Nimo. 2018. “A holistic review of off-site construction literature published between 2008 and 2018.” J. Cleaner Prod. 202 (Nov): 1202–1219. https://doi.org/10.1016/j.jclepro.2018.08.195.
Kamali, M., and K. Hewage. 2016. “Life cycle performance of modular buildings: A critical review.” Renewable Sustainable Energy Rev. 62 (Sep): 1171–1183. https://doi.org/10.1016/j.rser.2016.05.031.
Keeter, S., C. Kennedy, M. Dimock, J. Best, and P. Craighill. 2006. “Gauging the impact of growing nonresponse on estimates from a national RDD telephone survey.” Public Opin. Q. 70 (5): 759–779. https://doi.org/10.1093/poq/nfl035.
Khoo, S. B. 2017. “Design for manufacturing & assessment—Prefabricated pre-finished volumetric construction (DfMA PPVC).” Accessed January 9, 2023. https://media.arcadis.com/-/media/project/arcadiscom/com/perspectives/asia/publications/insights/prefabricated-pre-finished-volumetric-construction.pdf?rev=3ca5adcf068e4cc6baad7f42c305bde00%0A.
Lee, M. 2017. “Some builders not keen to be first movers in PPVC.” Business Times. Accessed January 10, 2023. https://www.businesstimes.com.sg/companies-markets/some-builders-not-keen-to-be-first-movers-in-ppvc.
Li, C. Z., J. Hong, C. Fan, X. Xu, and G. Q. Shen. 2018. “Schedule delay analysis of prefabricated housing production: A hybrid dynamic approach.” J. Cleaner Prod. 195 (Sep): 1533–1545. https://doi.org/10.1016/j.jclepro.2017.09.066.
Liao, L., and E. A. L. Teo. 2019. “Managing critical drivers for building information modelling implementation in the Singapore construction industry: An organizational change perspective.” Int. J. Construct. Manage. 19 (3): 240–256. https://doi.org/10.1080/15623599.2017.1423165.
Liew, J. Y. R., Y. S. Chua, and Z. Dai. 2019. “Steel concrete composite systems for modular construction of high-rise buildings.” Structures 21 (Nov): 135–149. https://doi.org/10.1016/j.istruc.2019.02.010.
Liu, W. Q., B. G. Hwang, M. Shan, and K. Y. Looi. 2019. “Prefabricated prefinished volumetric construction: Key constraints and mitigation strategies.” IOP Conf. Ser.: Earth Environ. Sci. 385 (1): 012001. https://doi.org/10.1088/1755-1315/385/1/012001.
Looi, K. Y. 2017. Adoption of prefabricated prefinished volumetric construction (PPVC) in Singapore: Constraints, decision-making factors and assessment framework. Singapore: National Univ. of Singapore.
Low, S. P., and H. S. Lau. 2019. Construction quality and the economy. Singapore: Springer.
Mao, C., Q. Shen, W. Pan, and K. Ye. 2015. “Major barriers to off-site construction: The developer’s perspective in China.” J. Manage. Eng. 31 (3): 04014043. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000246.
Ministry of National Development. 2020. Written answer by Ministry of National Development on adoption of prefabricated prefinished volumetric construction. Singapore: Ministry of National Development.
Ngo, J., B. G. Hwang, and C. Zhang. 2020. “Factor-based big data and predictive analytics capability assessment tool for the construction industry.” Autom. Constr. 110 (Feb): 103042. https://doi.org/10.1016/j.autcon.2019.103042.
Niu, S., Y. Yang, and W. Pan. 2019. “Logistics planning and visualization of modular integrated construction projects based on BIM-GIS integration and vehicle routing algorithm.” In Proc., Modular and Offsite Construction (MOC) Summit, 579–586. Edmonton, AB, Canada: Univ. of Alberta.
Pan, W., A. G. F. Gibb, and A. R. J. Dainty. 2012. “Strategies for integrating the use of off-site production technologies in house building.” J. Constr. Eng. Manage. 138 (11): 1331–1340. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000544.
Pan, W., and C. K. Hon. 2020. “Briefing: Modular integrated construction for high-rise buildings.” Proc. Inst. Civ. Eng. Munic. Eng. 173 (2): 64–68. https://doi.org/10.1680/jmuen.18.00028.
Pan, W., and Z. Zhang. 2019. “Benchmarking the sustainability of concrete and steel modular construction for buildings in urban development.” Accessed January 9, 2023. https://ssrn.com/abstract=4193537.
Pang, S. D., J. Y. R. Liew, Z. Dai, and Y. Wang. 2016. “Prefabricated prefinished volumetric construction joining techniques review.” In Proc., Modular and Offsite Construction (MOC) Summit, 249–256. Edmonton, AB, Canada: Univ. of Alberta.
Rahman, M. M. 2014. “Barriers of implementing modern methods of construction.” J. Manage. Eng. 30 (1): 69–77. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000173.
Rausch, C., C. Edwards, and C. Haas. 2020. “Benchmarking and improving dimensional quality on modular construction projects—A case study.” Int. J. Industrialized Constr. 1 (1): 2–21. https://doi.org/10.29173/ijic212.
Rogelberg, S. G., and J. M. Stanton. 2007. “With organizational survey nonresponse.” Organ. Res. Methods 10 (2): 195–209. https://doi.org/10.1177/1094428106294693.
Rui, O. Y., and K. Yahya. 2016. The productivity rate of prefabricated pre-finished volumetric construction (PPVC), 67–77. Skudai, Malaysia: Universiti Teknologi Malaysia.
Sim, Z. 2021. Singapore’s construction firms in managing the COVID-19 crisis. Singapore: National Univ. of Singapore.
Sunindijo, R. Y. 2015. “Project manager skills for improving project performance.” Int. J. Bus. Perform. Manage. 16 (1): 67–83. https://doi.org/10.1504/IJBPM.2015.066041.
Tan, N. L., and J. Y. Yong. 2022. “BCA expects 2022 construction demand between S$27b and S$32b, supported by public sector projects.” Accessed January 10, 2023. https://www.businesstimes.com.sg/international/bca-expects-2022-construction-demand-between-s27b-and-s32b-supported-public-sector.
Teo, E. A. L., S. L. Chan, and P. H. Tan. 2007. “Empirical investigation into factors affecting exporting construction services in SMEs in Singapore.” J. Constr. Eng. Manage. 133 (8): 582–591. https://doi.org/10.1061/(ASCE)0733-9364(2007)133:8(582).
Velamati, S. 2012. Feasibility, benefits and challenges of modular construction in high rise development in the United States: A developer’s perspective. Cambridge, MA: Massachusetts Institute of Technology.
Verma, J. P., and A. S. G. Abdel-Salam. 2019. Testing statistical assumptions in research. New York: Wiley.
Won, D., B.-G. Hwang, and N. K. Binte Mohd Samion. 2022. “Cloud computing adoption in the construction industry of Singapore: Drivers, challenges, and strategies.” J. Manage. Eng. 38 (2): 1–14. https://doi.org/10.1061/(ASCE)ME.1943-5479.0001001.
Wuni, I. Y., and G. Q. Shen. 2020. “Critical success factors for management of the early stages of prefabricated prefinished volumetric construction project life cycle.” Eng. Constr. Archit. Manage. 27 (9): 2315–2333. https://doi.org/10.1108/ECAM-10-2019-0534.
Wuni, I. Y., G. Q. Shen, and B.-G. Hwang. 2020. “Risks of modular integrated construction: A review and future research directions.” Front. Eng. Manage. 7 (1): 63–80. https://doi.org/10.1007/s42524-019-0059-7.
Wuni, I. Y., G. Q. P. Shen, and A. T. Mahmud. 2022. “Critical risk factors in the application of modular integrated construction: A systematic review.” Int. J. Constr. Manage. 22 (2): 133–147. https://doi.org/10.1080/15623599.2019.1613212.
Yang, Y., M. Pan, W. Pan, and Z. Zhang. 2021. “Sources of uncertainties in offsite logistics of modular construction for high-rise building projects.” J. Manage. Eng. 37 (3): 04021011. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000905.
Yevu, S. K., A. T. W. Yu, E. Adinyira, A. Darko, and M. F. Antwi-Afari. 2022. “Optimizing the application of strategies promoting electronic procurement systems towards sustainable construction in the building lifecycle: A neurofuzzy model approach.” J. Cleaner Prod. 336 (Dec): 130343. https://doi.org/10.1016/j.jclepro.2021.130343.
Zhang, R., A. S. J. Zhou, S. Tahmasebi, and J. Whyte. 2019. “Long-standing themes and new developments in offsite construction: The case of UK housing.” Proc. Inst. Civ. Eng. Civ. Eng. 172 (6): 29–35. https://doi.org/10.1680/jcien.19.00011.
Zhang, W., M. W. Lee, L. Jaillon, and C. S. Poon. 2018. “The hindrance to using prefabrication in Hong Kong’s building industry.” J. Cleaner Prod. 204 (Dec): 70–81. https://doi.org/10.1016/j.jclepro.2018.08.190.
Zhao, X., B. G. Hwang, and G. S. Yu. 2013. “Identifying the critical risks in underground rail international construction joint ventures: Case study of Singapore.” Int. J. Project Manage. 31 (4): 554–566. https://doi.org/10.1016/j.ijproman.2012.10.014.
Zhao, X., and N. Singhaputtangkul. 2016. “Effects of firm characteristics on enterprise risk management: Case study of Chinese construction firms operating in Singapore.” J. Manage. Eng. 32 (4): 05016008. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000434.
Zhou, S., L. Mosca, and J. Whyte. 2023. “How the reliability of external competences shapes the modularization strategies of industrialized construction firms.” Construct. Manage. Econ. 41 (7): 608–619. https://doi.org/10.1080/01446193.2023.2187071.

Information & Authors

Information

Published In

Go to Journal of Management in Engineering
Journal of Management in Engineering
Volume 39Issue 6November 2023

History

Received: Jan 17, 2023
Accepted: Jul 5, 2023
Published online: Sep 8, 2023
Published in print: Nov 1, 2023
Discussion open until: Feb 8, 2024

Permissions

Request permissions for this article.

ASCE Technical Topics:

Authors

Affiliations

Visiting Scientist, School of Civil and Environmental Engineering (CEE), Nanyang Technological Univ., 50 Nanyang Ave., Singapore 639798; Technical Consultant, buildingSMART China (bSC), 9 Shouti Rd. South, Haidian District, Beijing 100044, China; Lecturer, School of Science and Technology, Singapore Univ. of Social Sciences, 463 Clementi Rd., Singapore 599494. ORCID: https://orcid.org/0000-0002-7641-1450. Email: [email protected]; [email protected]
Professor, Dept. of the Built Environment, National Univ. of Singapore, 4 Architecture Dr., Singapore 117566 (corresponding author). ORCID: https://orcid.org/0000-0002-9034-2033. Email: [email protected]
Justin Minghan Lim [email protected]
Researcher, Dept. of the Built Environment, National Univ. of Singapore, 4 Architecture Dr., Singapore 117566. Email: [email protected]

Metrics & Citations

Metrics

Citations

Download citation

If you have the appropriate software installed, you can download article citation data to the citation manager of your choice. Simply select your manager software from the list below and click Download.

Cited by

  • Construction Waste Reduction in Buildings through Modular and Offsite Construction, Journal of Management in Engineering, 10.1061/JMENEA.MEENG-5828, 40, 4, (2024).

View Options

Get Access

Access content

Please select your options to get access

Log in/Register Log in via your institution (Shibboleth)
ASCE Members: Please log in to see member pricing

Purchase

Save for later Information on ASCE Library Cards
ASCE Library Cards let you download journal articles, proceedings papers, and available book chapters across the entire ASCE Library platform. ASCE Library Cards remain active for 24 months or until all downloads are used. Note: This content will be debited as one download at time of checkout.

Terms of Use: ASCE Library Cards are for individual, personal use only. Reselling, republishing, or forwarding the materials to libraries or reading rooms is prohibited.
ASCE Library Card (5 downloads)
$105.00
Add to cart
ASCE Library Card (20 downloads)
$280.00
Add to cart
Buy Single Article
$35.00
Add to cart

Get Access

Access content

Please select your options to get access

Log in/Register Log in via your institution (Shibboleth)
ASCE Members: Please log in to see member pricing

Purchase

Save for later Information on ASCE Library Cards
ASCE Library Cards let you download journal articles, proceedings papers, and available book chapters across the entire ASCE Library platform. ASCE Library Cards remain active for 24 months or until all downloads are used. Note: This content will be debited as one download at time of checkout.

Terms of Use: ASCE Library Cards are for individual, personal use only. Reselling, republishing, or forwarding the materials to libraries or reading rooms is prohibited.
ASCE Library Card (5 downloads)
$105.00
Add to cart
ASCE Library Card (20 downloads)
$280.00
Add to cart
Buy Single Article
$35.00
Add to cart

Media

Figures

Other

Tables

Share

Share

Copy the content Link

Share with email

Email a colleague

Share