Case Studies
Aug 24, 2024

Improper Risk Management Outcomes and Lessons Learned from an EPC Water Transmission Project

Publication: Journal of Construction Engineering and Management
Volume 150, Issue 11

Abstract

The lack of a proper risk management procedure for water transmission projects is a significant problem that could lead to claims and disputes. This study explores risk management practices in an engineering, procurement, and construction (EPC) water transmission project in Bahrain. It addresses key research questions on inadequate preconstruction risk management, its impact on project execution and stakeholder satisfaction, and the potential benefits of integrated risk management and project scope strategies. Using a case study approach, the research employs content analysis of 15 claims within the case study and thematic coding to identify risks across project phases. The study reveals challenges like scope gaps, technical deficiencies, and communication breakdowns resulting in legal disputes and a cost overrun of USD 3.6 million on the original EPC contract of USD 57.27 million. The dispute was ultimately resolved through intensive negotiations, with the contractor receiving USD 2.4 million; by analyzing contract agreements, meeting decisions, site reports, contractual letters. This case study emphasizes the need for proactive risk management during procurement and vigilant monitoring during execution, offering insights for effective project delivery. Lessons from the study emphasize the importance of stakeholder identification, change management procedures, and specialized works management for successful project execution. The research contributes practical recommendations, highlighting the critical role of comprehensive risk mitigation in EPC projects and empowering stakeholders to make informed decisions for successful outcomes. The findings can also assist vendors in understanding potential risks, being aware of the consequences of improper risk management implementation and making informed decisions before signing a contract. Through its methodology, case study insights, and practical recommendations, this study significantly contributes to the body of knowledge, providing valuable lessons and strategies applicable to a broader spectrum of similar projects.

Get full access to this article

View all available purchase options and get full access to this article.

Data Availability Statement

All data used during the study are available from the corresponding author by request.

Acknowledgments

The authors acknowledge the assistance of the project’s employees and express special thanks to the contract manager for providing valuable input to this research.

References

Ahmed, A., B. Kayis, and S. Amornsawadwatana. 2007. “A review of techniques for risk management in projects.” Benchmarking: Int. J. 14 (1): 22–36. https://doi.org/10.1108/14635770710730919.
Ayub, B., F. Ullah, F. Rasheed, and S. M. Sepasgozar. 2016. “Risks in EPC hydropower projects: A case of Pakistan.” In Proc., 8th Int. Civil Engineering Congress (ICEC) Ensuring Technological Advancement through Innovation Based Knowledge Corridor, 23–24. Karachi, Pakistan: NED Univ. of Engineering and Technology.
Baker, E., B. Mellors, S. Chalmers, and A. Lavers. 2013. FIDIC contracts: Law and practice. 1st ed. New York: Taylor and Francis.
Banaitiene, N., and A. Banaitis. 2012. “Risk management-current issues and challenges.” In Risk management in construction projects. Vilnius, Europe: InTech.
Baram, G. E. 2000. “Concurrent delays--what are they and how to deal with them?” Accessed August 6, 2023. https://libproxy.txstate.edu/login?url=https://www.proquest.com/scholarly-journals/concurrent-delays-what-are-they-how-deal-with/docview/208184029/se-2.
Befrouei, M. A. R., and M. Taghipour. 2015. “Identification and management of risks in construction projects.” Am. J. Civ. Eng. 3 (5): 170–177. https://doi.org/10.11648/j.ajce.20150305.15.
Cai, N., J. Wang, and X. Yu. 2008. “SCADA system security: Complexity, history and new developments.” In Proc., 2008 6th IEEE Int. Conf. on Industrial Informatics, 569–574. New York: IEEE.
Chapman, C., and S. Ward. 2003. Project risk management processes, techniques and insights, 255–276. New York: Wiley.
Choudhry, R. M., and K. Iqbal. 2013. “Identification of risk management system in construction industry in Pakistan.” J. Manage. Eng. 29 (1): 42–49. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000122.
Dao, B., S. Kermanshachi, J. Shane, S. Anderson, and E. Hare. 2017. “Exploring and assessing project complexity.” J. Const. Eng. Manage 143 (5): 04016126. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001275.
Dey, P. 2009. “Managing risks of large-scale construction projects.” Cost Eng. 51 (6): 23–27.
Ding, Y., X. Zhang, L. Zhou, and C. Xu. 2022. “Investment risk assessment of EPC power transmission and transformation projects under new energy grid connection based on the owner’s perspective.” Math. Probl. Eng. 2022 (1): 2258938. https://doi.org/10.1155/2022/2258938.
Edwards, P. J., and P. A. Bowen. 1998. “Risk and risk management in construction: A review and future directions for research.” Eng. Constr. Archit. Manage. 5 (4): 339–349. https://doi.org/10.1108/eb021087.
Egorova, Z., and V. Shestak. 2021. “EPC contracts: Prospects for conclusion in Russia.” In Proc., Int. Scientific and Practical Conf. “Law and modern economy: New challenges and prospects in a pandemic.” Rochester, NY: SSRN-Elsevier.
FIDIC (International Federation of Consulting Engineers). 1999. Conditions of contract for EPC/turnkey projects. 1st ed. Geneva: FIDIC.
Flyvbjerg, B., N. Bruzelius, and W. Rothengatter. 2003. Megaprojects and risk: An anatomy of ambition. Cambridge, UK: Cambridge University Press.
Galloway, P. D. 2018. “The art of allocating risk in an EPC contract to minimize disputes.” Constr. Law 38 (Mar): 26.
Gibbs, G. R. 2018. Analyzing qualitative data, 1–232. New York: SAGE.
Godwin, W. 2020. The 2017 FIDIC contracts. New York: Wiley.
Hatmoko, J. U. D., and R. R. Khasani. 2019. “Mapping delay risks of EPC projects: A case study of a platform and subsea pipeline of an oil and gas project.” IOP Conf. Ser.: Mater. Sci. Eng. 598 (1): 012095. https://doi.org/10.1088/1757-899X/598/1/012095.
Hillson, D. 2003. Effective opportunity management for projects: Exploiting positive risk. Boca Raton, FL: CRC Press.
Imbeah, W., and S. Guikema. 2009. “Managing construction projects using the advanced programmatic risk analysis and management model.” J. Constr. Eng. Manage. 135 (8): 772–781. https://doi.org/10.1061/(ASCE)0733-9364(2009)135:8(772).
Irimia-Diéguez, A. I., A. Sanchez-Cazorla, and R. Alfalla-Luque. 2014. “Risk management in megaprojects.” Procedia-Social Behav. Sci. 119 (Dec): 407–416. https://doi.org/10.1016/j.sbspro.2014.03.046.
Jaeger, A.-V., and G.-S. Hök. 2010. Vol. 24 of FIDIC: A guide for practitioners. New York: Springer.
Kabirifar, K., and M. Mojtahedi. 2019. “The impact of engineering, procurement and construction (EPC) phases on project performance: A case of large-scale residential construction project.” Buildings 9 (1): 15. https://doi.org/10.3390/buildings9010015.
Koelsch, G. 2016. “How to collect requirements.” In Requirements writing for system engineering, 211–243. Berkeley, CA: Apress.
Kululanga, G., and W. Kuotcha. 2010. “Measuring project risk management process for construction contractors with statement indicators linked to numerical scores.” Eng. Constr. Archit. Manage. 17 (4): 336–351. https://doi.org/10.1108/09699981011056556.
Loosemore, M., J. Raftery, C. Reilly, and D. Higgon. 2012. Risk management in projects. Oxfordshire, UK: Routledge.
Loots, P., and N. Henchie. 2007. “Worlds apart: EPC and EPCM contracts: Risk issues and allocation.” Int. Constr. Law Rev. 24 (1/4): 252.
Ma, G., H. Luo, and J. Zheng. 2016. “Research on the risks of international high-speed railway projects based on the FIDIC-EPC total price contract.” In Proc., Int. Conf. on Construction and Real Estate Management, 1402–1411. Reston, VA: ASCE.
Mills, A. 2001. “A systematic approach to risk management for construction.” Struct. Surv. 19 (5): 245–252. https://doi.org/10.1108/02630800110412615.
Nabawy, M., and L. M. Khodeir. 2020. “A systematic review of quantitative risk analysis in construction of mega projects.” Ain Shams Eng. J. 11 (4): 1403–1410. https://doi.org/10.1016/j.asej.2020.02.006.
Nan, C., I. Eusgeld, and W. Kröger. 2013. “Analyzing vulnerabilities between SCADA system and SUC due to interdependencies.” Reliab. Eng. Syst. Saf. 113 (May): 76–93. https://doi.org/10.1016/j.ress.2012.12.014.
Olsson, G. 2015. Water and energy: Threats and opportunities. London: IWA Publishing.
Pícha, J., A. Tomek, and H. Löwitt. 2015. “Application of EPC contracts in international power projects.” Procedia Eng. 123 (Jan): 397–404. https://doi.org/10.1016/j.proeng.2015.10.061.
Project Management Institute. 2019. The standard for risk in portfolios, programs, and projects. Newtown Square, PA: Project Management Institute.
Project Management Institute. 2021. The standard for project management and a guide to the project management body of knowledge (PMBOK® Guide). Newtown Square, PA: Project Management Institute.
Raz, T., and E. Michael. 2001. “Use and benefits of tools for project risk management.” Int. J. Project Manage. 19 (1): 9–17. https://doi.org/10.1016/S0263-7863(99)00036-8.
Sadeh, H., C. Mirarchi, and A. Pavan. 2021. “Integrated approach to construction risk management: Cost implications.” J. Constr. Eng. Manage. 147 (10): 04021113. https://doi.org/10.1061/(ASCE)CO.1943-7862.0002140.
Schieg, M. 2006. “Risk management in construction project management.” J. Bus. Econ. Manage. 7 (2): 77–83. https://doi.org/10.3846/16111699.2006.9636126.
Serpella, A. F., X. Ferrada, R. Howard, and L. Rubio. 2014. “Risk management in construction projects: A knowledge-based approach.” Procedia-Social Behav. Sci. 119 (Dec): 653–662. https://doi.org/10.1016/j.sbspro.2014.03.073.
Sharma, S. K., and N. Swain. 2011. “Risk management in construction projects.” Asia Pac. Bus. Rev. 7 (3): 107–120. https://doi.org/10.1177/097324701100700310.
Shen, W., W. Tang, W. Yu, C. F. Duffield, F. K. P. Hui, Y. Wei, and J. Fang. 2017. “Causes of contractors’ claims in international engineering-procurement-construction projects.” J. Constr. Eng. Manage. 23 (6): 727–739. https://doi.org/10.3846/13923730.2017.1281839.
Shin, K. C. K. 2000. “Identification of critical dispute characteristics (CDCs) during construction project operations.” Ph.D. dissertation, School of Civil and Environmental Engineering, Georgia Institute of Technology.
Shnookal, T., and D. Charrett. 2010. “Standard form contracting the role for FIDIC contracts domestically and internationally.” In Vol. 30 of Proc., Society of Construction Law Conf. Sydney, NSW, Australia: Society of Construction Law Australia.
Sunna, E., and O. A. Saadoon. 2007. “FIDIC in the middle east.” Accessed December 15, 2023. https://www.fidic.org/sites/default/files/FIDIC%20in%20the%20Middle-East.pdf.
Thweatt, W. T., and R. J. Long. 2017. EPC contract risk analysis associated with onshore projects in developing countries. Littleton, CO: Long International.
Vidal, L. A., and F. Marle. 2008. “Understanding project complexity: Implications on project management.” Kybernetes 37 (8): 1094–1110. https://doi.org/10.1108/03684920810884928.
Vu, T. Q., C. P. Pham, T. A. Nguyen, P. T. Nguyen, P. T. Pham, and Q. L. H. T. T. Nguyen. 2020. “Factors influencing cost overruns in construction projects of international contractors in Vietnam.” J. Asian Finance Econ. Bus. 7 (9): 389. https://doi.org/10.13106/jafeb.2020.vol7.no9.389.
Wu, Y., Z. Song, L. Li, and R. Xu. 2018. “Risk management of public-private partnership charging infrastructure projects in China based on a three-dimension framework.” Energy Sci. Direct 165 (Jun): 1089–1101. https://doi.org/10.1016/j.energy.2018.09.092.
Zhang, Z., M. Huang, and B. Wu. 2020. “Risk analysis and control factors based on excavation of a large underground subway station under construction.” Symmetry 12 (10): 1629. https://doi.org/10.3390/sym12101629.
Zhi, H. 1995. “Risk management for overseas construction projects.” Int. J. Project Manage. 13 (4): 231–237. https://doi.org/10.1016/0263-7863(95)00015-I.

Information & Authors

Information

Published In

Go to Journal of Construction Engineering and Management
Journal of Construction Engineering and Management
Volume 150Issue 11November 2024

History

Received: Oct 13, 2023
Accepted: Mar 20, 2024
Published online: Aug 24, 2024
Published in print: Nov 1, 2024
Discussion open until: Jan 24, 2025

Permissions

Request permissions for this article.

Authors

Affiliations

Mohamed Abaza, S.M.ASCE [email protected]
Graduate Assistant, Dept. of Engineering Technology, Texas State Univ., San Marcos, TX 78666. Email: [email protected]
Associate Professor, Dept. of Engineering Technology, Texas State Univ., San Marcos, TX 78666 (corresponding author). ORCID: https://orcid.org/0000-0003-1850-5747. Email: [email protected]

Metrics & Citations

Metrics

Citations

Download citation

If you have the appropriate software installed, you can download article citation data to the citation manager of your choice. Simply select your manager software from the list below and click Download.

View Options

Get Access

Access content

Please select your options to get access

Log in/Register Log in via your institution (Shibboleth)
ASCE Members: Please log in to see member pricing

Purchase

Save for later Information on ASCE Library Cards
ASCE Library Cards let you download journal articles, proceedings papers, and available book chapters across the entire ASCE Library platform. ASCE Library Cards remain active for 24 months or until all downloads are used. Note: This content will be debited as one download at time of checkout.

Terms of Use: ASCE Library Cards are for individual, personal use only. Reselling, republishing, or forwarding the materials to libraries or reading rooms is prohibited.
ASCE Library Card (5 downloads)
$105.00
Add to cart
ASCE Library Card (20 downloads)
$280.00
Add to cart
Buy Single Article
$35.00
Add to cart

Get Access

Access content

Please select your options to get access

Log in/Register Log in via your institution (Shibboleth)
ASCE Members: Please log in to see member pricing

Purchase

Save for later Information on ASCE Library Cards
ASCE Library Cards let you download journal articles, proceedings papers, and available book chapters across the entire ASCE Library platform. ASCE Library Cards remain active for 24 months or until all downloads are used. Note: This content will be debited as one download at time of checkout.

Terms of Use: ASCE Library Cards are for individual, personal use only. Reselling, republishing, or forwarding the materials to libraries or reading rooms is prohibited.
ASCE Library Card (5 downloads)
$105.00
Add to cart
ASCE Library Card (20 downloads)
$280.00
Add to cart
Buy Single Article
$35.00
Add to cart

Media

Figures

Other

Tables

Share

Share

Copy the content Link

Share with email

Email a colleague

Share