Mathematical Multiobjective Optimization Model for Trade-Offs in Small-Scale Construction Projects

Publication: Journal of Construction Engineering and Management
Volume 149, Issue 7

Abstract

As construction projects become more complex and challenging to execute, project managers need to develop work schedules that consider as many objectives as are critical to project success. A work schedule designed to optimize all these objectives is likely to enhance project performance. However, achieving a balance among these objectives is difficult because they frequently conflict with each other. Many optimization models have been developed over the years that can factor in different objectives. Although previous optimization studies have contributed to the body of knowledge by individually adding one or two objectives to the classical time–cost trade-off (TCT) problem, none of these studies simultaneously optimized more than three or four objectives at a time. Clearly, there is a need for a multiobjective optimization model to generate work schedules that increase the likelihood of achieving as many project objectives as necessary. This study was motivated by the need to fill this research gap. The objective of this study was to develop a mathematical multiobjective optimization model for the time–cost–quality–schedule flexibility-resource fluctuation trade-off problem in small-scale construction projects. The proposed model is novel because it (1) considers five important objectives of construction project scheduling at the same time, (2) quantifies all objectives to provide an accurate reflection of construction site conditions, and (3) objectively determines the optimal compromise solution using a distance-based method rather than subjectively from a set of Pareto-optimal solutions. The applicability of the proposed model is demonstrated with an illustrative example. The key results of this study are as follows: (1) the optimal solution obtained depends on the project manager’s priorities relative to the objectives; and (2) in optimization problems with more than two objectives, considering the objectives one at a time may result in misleading solutions, because the effects of the other objectives are ignored in this optimization. Consequently, multiple objectives must be considered simultaneously rather than one at a time. The proposed model is expected to provide project managers with a work schedule that balances five or more objectives, increasing the chances of successful project performance.

Get full access to this article

View all available purchase options and get full access to this article.

Data Availability Statement

Some or all data, models, or code that support the findings of this study are available from the corresponding author upon reasonable request.

References

Afruzi, E. N., A. A. Najafi, E. Roghanian, and M. Mazinani. 2014. “A multi-objective imperialist competitive algorithm for solving discrete time, cost and quality trade-off problems with mode-identity and resource-constrained situations.” Comput. Oper. Res. 50 (Oct): 80–96. https://doi.org/10.1016/j.cor.2014.04.003.
Al Haj, R. A., and S. M. El-Sayegh. 2015. “Time–cost optimization model considering float-consumption impact.” J. Constr. Eng. Manage. 141 (5): 04015001. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000966.
Aminbakhsh, S., and R. Sonmez. 2017. “Pareto front particle swarm optimizer for discrete time-cost trade-off problem.” J. Comput. Civ. Eng. 31 (1): 04016040. https://doi.org/10.1061/(ASCE)CP.1943-5487.0000606.
Anagnostopoulos, K. P., and L. Kotsikas. 2010. “Experimental evaluation of simulated annealing algorithms for the time–cost trade-off problem.” Appl. Math. Comput. 217 (1): 260–270. https://doi.org/10.1016/j.amc.2010.05.056.
Ashuri, B., and M. Tavakolan. 2012. “Fuzzy enabled hybrid genetic algorithm–particle swarm optimization approach to solve TCRO problems in construction project planning.” J. Constr. Eng. Manage. 138 (9): 1065–1074. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000513.
Ashuri, B., and M. Tavakolan. 2015. “Shuffled frog-leaping model for solving time-cost-resource optimization problems in construction project planning.” J. Comput. Civ. Eng. 29 (1): 04014026. https://doi.org/10.1061/(ASCE)CP.1943-5487.0000315.
Babu, A. J. G., and N. Suresh. 1996. “Project management with time, cost, and quality considerations.” Eur. J. Oper. Res. 88 (2): 320–327. https://doi.org/10.1016/0377-2217(94)00202-9.
Banihashemi, S. A., and M. Khalilzadeh. 2020. “Time-cost-quality-environmental impact trade-off resource-constrained project scheduling problem with DEA approach.” Eng. Constr. Archit. Manage. 28 (7): 1979–2004. https://doi.org/10.1108/ECAM-05-2020-0350.
Banihashemi, S. A., and M. Khalilzadeh. 2022. “Towards sustainable project scheduling with reducing environmental pollution of projects: Fuzzy multi-objective programming approach to a case study of Eastern Iran.” In Environment, development and sustainability, 1–31. Singapore: Springer.
Burns, S. A., L. Liu, and C. W. Feng. 1996. “The LP/IP hybrid method for construction time-cost trade-off analysis.” Construct. Manage. Econ. 14 (3): 265–276. https://doi.org/10.1080/014461996373511.
Butcher, W. S. 1967. “Dynamic programming for project cost-time curves.” J. Constr. Div. 93 (1): 59–74. https://doi.org/10.1061/JCCEAZ.0000191.
Chen, P. H., and H. Weng. 2009. “A two-phase GA model for resource-constrained project scheduling.” Autom. Constr. 18 (4): 485–498. https://doi.org/10.1016/j.autcon.2008.11.003.
Cheng, M. Y., D. Prayogo, and D. H. Tran. 2016. “Optimizing multiple-resources leveling in multiple projects using discrete symbiotic organisms search.” J. Comput. Civ. Eng. 30 (3): 04015036 . https://doi.org/10.1061/(ASCE)CP.1943-5487.0000512.
Cheng, M. Y., and D. H. Tran. 2014. “Two-phase differential evolution for the multi-objective optimization of time–cost tradeoffs in resource-constrained construction projects.” IEEE Trans. Eng. Manage. 61 (3): 450–461. https://doi.org/10.1109/TEM.2014.2327512.
Cheng, M. Y., D. H. Tran, and N. D. Hoang. 2017. “Fuzzy clustering chaotic-based differential evolution for resource leveling in construction projects.” J. Civ. Eng. Manage. 23 (1): 113–124. https://doi.org/10.3846/13923730.2014.982699.
Damci, A., D. Arditi, and G. Polat. 2016. “Impacts of different objective functions on resource leveling in line-of-balance scheduling.” KSCE J. Civ. Eng. 20 (1): 58–67. https://doi.org/10.1007/s12205-015-0578-7.
Damci, A., and G. Polat. 2014. “Impacts of different objective functions on resource leveling in construction projects: A case study.” J. Civ. Eng. Manage. 20 (4): 537–547. https://doi.org/10.3846/13923730.2013.801909.
de La Garza, J. M., M. C. Vorster, and C. M. Parvin. 1991. “Total float traded as commodity.” J. Constr. Eng. Manage. 117 (4): 716–727. https://doi.org/10.1061/(ASCE)0733-9364(1991)117:4(716).
Elazouni, A. M., and A. A. Gab-Allah. 2004. “Finance-based scheduling of construction projects using integer programming.” J. Constr. Eng. Manage. 130 (1): 15–24. https://doi.org/10.1061/(ASCE)0733-9364(2004)130:1(15).
Elbeltagi, E., M. Ammar, H. Sanad, and M. Kassab. 2016. “Overall multiobjective optimization of construction projects scheduling using particle swarm.” Eng. Constr. Archit. Manage. 23 (3): 265–282. https://doi.org/10.1108/ECAM-11-2014-0135.
Elkholy, D. M., T. M. El-Korany, and A. H. A. Khalil. 2019. “Time-cost optimization model with probabilistic path and float consumption impact.” Int. J. Adv. Struct. Geotech. Eng. 3 (4): 1–15.
El-Rayes, K., and D. H. Jun. 2009. “Optimizing resource leveling in construction projects.” J. Constr. Eng. Manage. 135 (11): 1172–1180. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000097.
El-Rayes, K., and A. Kandil. 2005. “Time-cost-quality trade-off analysis for highway construction.” J. Constr. Eng. Manage. 131 (4): 477–486. https://doi.org/10.1061/(ASCE)0733-9364(2005)131:4(477).
El-Sayegh, S. M., and R. Al-Haj. 2017. “A new framework for time-cost trade-off considering float loss impact.” J. Financ. Manage. Prop. Constr. 22 (1): 20–36. https://doi.org/10.1108/JFMPC-02-2016-0007.
Eshtehardian, E., A. Afshar, and R. Abbasnia. 2008. “Time–cost optimization: Using GA and fuzzy sets theory for uncertainties in cost.” Construct. Manage. Econ. 26 (7): 679–691. https://doi.org/10.1080/01446190802036128.
Feng, C. W., L. Liu, and S. A. Burns. 1997. “Using genetic algorithms to solve construction time-cost trade-off problems.” J. Comput. Civ. Eng. 11 (3): 184–189. https://doi.org/10.1061/(ASCE)0887-3801(1997)11:3(184).
Feylizadeh, M. R., A. Mahmoudi, M. Bagherpour, and D. F. Li. 2018. “Project crashing using a fuzzy multi-objective model considering time, cost, quality and risk under fast tracking technique: A case study.” J. Intell. Fuzzy Syst. 35 (3): 3615–3631. https://doi.org/10.3233/JIFS-18171.
Geem, Z. W. 2010. “Multi-objective optimization of time-cost trade-off using harmony search.” J. Constr. Eng. Manage. 136 (6): 711–716. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000167.
Ghoddousi, P., E. Eshtehardian, S. Jooybanpour, and A. Javanmardi. 2013. “Multi-mode resource-constrained discrete time–cost-resource optimization in project scheduling using non-dominated sorting genetic algorithm.” Autom. Constr. 30 (Mar): 216–227. https://doi.org/10.1016/j.autcon.2012.11.014.
Glover, F., and K. Sörensen. 2015. “Metaheuristics.” Scholarpedia 10 (4): 6532. https://doi.org/10.4249/scholarpedia.6532.
Hamta, N., M. Ehsanifar, and J. Sarikhani. 2021. “Presenting a goal programming model in the time-cost-quality trade-off.” Int. J. Construct. Manage. 21 (1): 1–11. https://doi.org/10.1080/15623599.2018.1502930.
Hariga, M., A. Shamayleh, and F. El-Wehedi. 2019. “Integrated time–cost tradeoff and resources leveling problems with allowed activity splitting.” Int. Tran. Oper. Res. 26 (1): 80–99. https://doi.org/10.1111/itor.12329.
Hazır, Ö., E. Erel, and Y. Günalay. 2011. “Robust optimization models for the discrete time/cost trade-off problem.” Int. J. Prod. Econ. 130 (1): 87–95. https://doi.org/10.1016/j.ijpe.2010.11.018.
Hegazy, T. 1999. “Optimization of construction time-cost trade-off analysis using genetic algorithms.” Can. J. Civ. Eng. 26 (6): 685–697. https://doi.org/10.1139/l99-031.
Hegazy, T., and Z. Abuwarda. 2019. “Schedule flexibility and compression horizon: New key parameters for effective corrective actions.” In Proc., 2019 Canadian Society for Civil Engineering Annual Conf., CSCE 2019. Surrey, BC, Canada: Canadian Society for Civil Engineering.
Heravi, G., and S. Faeghi. 2014. “Group decision making for stochastic optimization of time, cost, and quality in construction projects.” J. Comput. Civ. Eng. 28 (2): 275–283. https://doi.org/10.1061/(ASCE)CP.1943-5487.0000264.
Isikyildiz, S., and C. Akcay. 2020. “Multi-objective optimization of time-cost-quality in construction projects using genetic algorithm.” Rev. Constr. 19 (3): 335–346.
Kamal, M., S. A. Jalil, S. M. Muneeb, and I. Ali. 2018. “A distance-based method for solving multi-objective optimization problems.” J. Mod. Appl. Stat. Methods 17 (1): 21. https://doi.org/10.22237/jmasm/1532525455.
Kaveh, A., and F. Rajabi. 2022. “Fuzzy-multi-mode resource-constrained discrete time-cost-resource optimization in project scheduling using ENSCBO.” Period. Polytech.-Civ. 66 (1): 50–62. https://doi.org/10.3311/PPci.19145.
Kelley, J. E., Jr. 1961. “Critical-path planning and scheduling: Mathematical basis.” Oper. Res. 9 (3): 296–320. https://doi.org/10.1287/opre.9.3.296.
Kelley, J. E., Jr., and M. R. Walker. 1959. “Critical-path planning and scheduling.” In Proc., Papers Presented at the December 1-3, 1959, Eastern Joint IRE-AIEE-ACM Computer Conf., 160–173. New York: Association for Computing Machinery. https://doi.org/10.1145/1460299.1460318.
Khalili-Damghani, K., M. Tavana, A. R. Abtahi, and F. J. Santos Arteaga. 2015. “Solving multi-mode time–cost–quality trade-off problems under generalized precedence relations.” Optim. Methods Software 30 (5): 965–1001. https://doi.org/10.1080/10556788.2015.1005838.
Khang, D. B., and Y. M. Myint. 1999. “Time, cost and quality trade-off in project management: A case study.” Int. J. Project Manage. 17 (4): 249–256. https://doi.org/10.1016/S0263-7863(98)00043-X.
Klanšek, U., and M. Pšunder. 2008. “Cost optimal project scheduling.” Organizacija 41 (4): 153–158. https://doi.org/10.2478/v10051-008-0017-3.
Lavely, J. A., G. Wakefield, and B. Barrett. 1980. “Toward enhancing beta estimates.” J. Portfolio Manage. 6 (4): 43–46. https://doi.org/10.3905/jpm.1980.408768.
Li, H., and P. Love. 1997. “Using improved genetic algorithms to facilitate time-cost optimization.” J. Constr. Eng. Manage. 123 (3): 233–237. https://doi.org/10.1061/(ASCE)0733-9364(1997)123:3(233).
Liu, D., H. Li, H. Wang, C. Qi, and T. Rose. 2020. “Discrete symbiotic organisms search method for solving large-scale time-cost trade-off problem in construction scheduling.” Expert Syst. Appl. 148 (Jun): 113230. https://doi.org/10.1016/j.eswa.2020.113230.
Liu, L., S. A. Burns, and C. W. Feng. 1995. “Construction time-cost trade-off analysis using LP/IP hybrid method.” J. Constr. Eng. Manage. 121 (4): 446–454. https://doi.org/10.1061/(ASCE)0733-9364(1995)121:4(446).
Long, L. D., D. H. Tran, and P. T. Nguyen. 2019. “Hybrid multiple objective evolutionary algorithms for optimising multi-mode time, cost and risk trade-off problem.” Int. J. Comput. Appl. Technol. 60 (3): 203–214. https://doi.org/10.1504/IJCAT.2019.100299.
Lotfi, R., Z. Yadegari, S. Hosseini, A. Khameneh, E. Tirkolaee, and G. E. Weber. 2022. “A robust time-cost-quality-energy-environment trade-off with resource-constrained in project management: A case study for a bridge construction project.” J. Ind. Manage. Optim. 18 (1): 375–396. https://doi.org/10.3934/jimo.2020158.
Luong, D. L., D. H. Tran, and P. T. Nguyen. 2021. “Optimizing multi-mode time-cost-quality trade-off of construction project using opposition multiple objective difference evolution.” Int. J. Construct. Manage. 21 (3): 271–283. https://doi.org/10.1080/15623599.2018.1526630.
Meyer, W. L., and L. R. Shaffer. 1965. “Extending CPM for multiform project time-cost curves.” J. Constr. Div. 91 (1): 45–67. https://doi.org/10.1061/JCCEAZ.0000137.
Mokhtari, H., R. B. Kazemzadeh, and A. Salmasnia. 2010. “Time-cost tradeoff analysis in project management: An ant system approach.” IEEE Trans. Eng. Manage. 58 (1): 36–43. https://doi.org/10.1109/TEM.2010.2058859.
Moradi, S., R. Ansari, and R. Taherkhani. 2021. “A systematic analysis of construction performance management: Key performance indicators from 2000 to 2020.” Iran. J. Sci. Technol. 2022 (46): 15–31. https://doi.org/10.1007/s40996-021-00626-7.
Moselhi, O. 1993. “Schedule compression using the direct stiffness method.” Can. J. Civ. Eng. 20 (1): 65–72. https://doi.org/10.1139/l93-007.
Nguyen, D. T., D. T. V. Doan, N. N. C. Tran, and D. H. Tran. 2023. “A novel multiple objective whale optimization for time-cost-quality tradeoff in non-unit repetitive projects.” Int. J. Construct. Manage. 23 (5): 843–854. https://doi.org/10.1080/15623599.2021.1938939.
Nguyen, D. T., L. Le-Hoai, P. B. Tarigan, and D. H. Tran. 2022. “Tradeoff time cost quality in repetitive construction project using fuzzy logic approach and symbiotic organism search algorithm.” Alexandria Eng. J. 61 (2): 1499–1518. https://doi.org/10.1016/j.aej.2021.06.058.
Osipova, E., and P. E. Eriksson. 2013. “Balancing control and flexibility in joint risk management: Lessons learned from two construction projects.” Int. J. Project Manage. 31 (3): 391–399. https://doi.org/10.1016/j.ijproman.2012.09.007.
Park, Y. J., and C. Y. Yi. 2021. “Resource-based quality performance estimation method for construction operations.” Appl. Sci. 11 (9): 4122. https://doi.org/10.3390/app11094122.
Patterson, J. H., and W. D. Huber. 1974. “A horizon-varying, zero-one approach to project scheduling.” Manage. Sci. 20 (6): 990–998. https://doi.org/10.1287/mnsc.20.6.990.
Perera, S. 1980. “Linear programming solution to network compression.” J. Constr. Div. 106 (3): 315–326. https://doi.org/10.1061/JCCEAZ.0000899.
Popescu, C. M., and C. Charoenngam. 1995. Project planning, scheduling, and control in construction: An encyclopedia of terms and applications. New York: Wiley.
Prager, W. 1963. “A structural method of computing project cost polygons.” Manage. Sci. 9 (3): 394–404. https://doi.org/10.1287/mnsc.9.3.394.
Rahimi, M., and H. Iranmanesh. 2008. “Multi objective particle swarm optimization for a discrete time, cost and quality trade-off problem.” World Appl. Sci. J. 4 (2): 270–276.
Ray, P., D. K. Bera, and A. K. Rath. 2021. “Time cost optimization using genetic algorithm of a construction project.” In Recent developments in sustainable infrastructure, 909–927. Singapore: Springer.
Raz, T., and B. Marshall. 1996. “Effect of resource constraints on float calculations in project networks.” Int. J. Project Manage. 14 (4): 241–248. https://doi.org/10.1016/0263-7863(95)00090-9.
Robinson, D. R. 1975. “A dynamic programming solution to cost-time tradeoff for CPM.” Manage. Sci. 22 (2): 158–166. https://doi.org/10.1287/mnsc.22.2.158.
Safapour, E., S. Kermanshachi, and I. Ramaji. 2023. “Selection of best practices that enhance phase-based cost and schedule performances in complex construction projects.” Eng. Manage. J. 35 (1): 84–99. https://doi.org/10.1080/10429247.2022.2036068.
Said, S. S., and M. Haouari. 2015. “A hybrid simulation-optimization approach for the robust discrete time/cost trade-off problem.” Appl. Math. Comput. 259 (May): 628–636. https://doi.org/10.1016/j.amc.2015.02.092.
Sakka, Z. I., and S. M. El-Sayegh. 2007. “Float consumption impact on cost and schedule in the construction industry.” J. Constr. Eng. Manage. 133 (2): 124–130. https://doi.org/10.1061/(ASCE)0733-9364(2007)133:2(124).
Shafiei, I., E. Eshtehardian, F. Nasirzadeh, and S. Arabi. 2023. “Dynamic modeling to reduce the cost of quality in construction projects.” Int. J. Construct. Manage. 23 (1): 24–37. https://doi.org/10.1080/15623599.2020.1845425.
Sharma, K., and M. K. Trivedi. 2021. “Development of multi-objective scheduling model for construction projects using opposition-based NSGA-III.” J. Inst. Eng. (India): Ser. A 102 (2): 435–449. https://doi.org/10.1007/s40030-021-00529-w.
Shishehgarkhaneh, M. B., M. Azizi, M. Basiri, and R. C. Moehler. 2022. “BIM-based resource tradeoff in project scheduling using fire hawk optimizer (FHO).” Buildings 12 (9): 1472. https://doi.org/10.3390/buildings12091472.
Siemens, N. 1971. “A simple CPM time-cost tradeoff algorithm.” Manage. Sci. 17 (6): B-354. https://doi.org/10.1287/mnsc.17.6.B354.
Son, J., and M. J. Skibniewski. 1999. “Multi-heuristic approach for resource leveling problem in construction engineering: Hybrid approach.” J. Constr. Eng. Manage. 125 (1): 23–31. https://doi.org/10.1061/(ASCE)0733-9364(1999)125:1(23).
Son, P. V. H., and L. N. Q. Khoi. 2022. “Utilizing artificial intelligence to solving time-cost-quality trade-off problem.” Sci. Rep. 12: 20112. https://doi.org/10.1038/s41598-022-24668-7.
Sonmez, R., S. Aminbakhsh, and T. Atan. 2020. “Activity uncrashing heuristic with noncritical activity rescheduling method for the discrete time-cost trade-off problem.” J. Constr. Eng. Manage. 146 (8): 04020084. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001870.
Sonmez, R., and Ö. H. Bettemir. 2012. “A hybrid genetic algorithm for the discrete time–cost trade-off problem.” Expert Syst. Appl. 39 (13): 11428–11434. https://doi.org/10.1016/j.eswa.2012.04.019.
Szidarovszky, F., D. Goodman, R. Thompson, and H. Manhaeve. 2018. “Alternative multivariate methods for state estimation, anomaly detection, and prognostics.” In Proc., 2018 IEEE Autotestcon, 1–5. New York: IEEE.
Tareghian, H. R., and S. H. Taheri. 2007. “A solution procedure for the discrete time, cost and quality tradeoff problem using electromagnetic scatter search.” Appl. Math. Comput. 190 (2): 1136–1145. https://doi.org/10.1016/j.amc.2007.01.100.
Tavana, M., A. R. Abtahi, and K. Khalili-Damghani. 2014. “A new multi-objective multi-mode model for solving preemptive time–cost–quality trade-off project scheduling problems.” Expert Syst. Appl. 41 (4): 1830–1846. https://doi.org/10.1016/j.eswa.2013.08.081.
Toğan, V., N. Berberoğlu, and T. Dede. 2022. “Optimizing of discrete time-cost in construction projects using new adaptive weight formulations.” KSCE J. Civ. Eng. 26 (2): 511–521. https://doi.org/10.1007/s12205-021-0783-5.
Tran, D. H. 2020. “Optimizing time–cost in generalized construction projects using multiple-objective social group optimization and multi-criteria decision-making methods.” Eng. Constr. Archit. Manage. 27 (9): 2287–2313. https://doi.org/10.1108/ECAM-08-2019-0412.
Tran, D. H., M. Y. Cheng, and M. T. Cao. 2015. “Hybrid multiple objective artificial bee colony with differential evolution for the time–cost–quality tradeoff problem.” Knowl.-Based Syst. 74 (Jan): 176–186. https://doi.org/10.1016/j.knosys.2014.11.018.
Tran, D. H., M. Y. Cheng, and D. Prayogo. 2016. “A novel multiple objective symbiotic organisms search (MOSOS) for time–cost–labor utilization tradeoff problem.” Knowl.-Based Syst. 94 (Feb): 132–145. https://doi.org/10.1016/j.knosys.2015.11.016.
Tran, D. H., and L. D. Long. 2018. “Project scheduling with time, cost and risk trade-off using adaptive multiple objective differential evolution.” Eng. Constr. Archit. Manage. 25 (5): 623–638. https://doi.org/10.1108/ECAM-05-2017-0085.
Turkoglu, H., G. Polat, and F. D. Akin. 2023. “Crashing construction projects considering schedule flexibility: An illustrative example.” Int. J. Construct. Manage. 23 (4): 619–628. https://doi.org/10.1080/15623599.2021.1901559.
Wang, T., M. Abdallah, C. Clevenger, and S. Monghasemi. 2019. “Time–cost–quality trade-off analysis for planning construction projects.” Eng. Constr. Archit. Manage. 28 (1): 82–100. https://doi.org/10.1108/ECAM-12-2017-0271.
Yang, I. T. 2007. “Using elitist particle swarm optimization to facilitate bicriterion time-cost trade-off analysis.” J. Constr. Eng. Manage. 133 (7): 498–505. https://doi.org/10.1061/(ASCE)0733-9364(2007)133:7(498).
Zahraie, B., and M. Tavakolan. 2009. “Stochastic time-cost-resource utilization optimization using nondominated sorting genetic algorithm and discrete fuzzy sets.” J. Constr. Eng. Manage. 135 (11): 1162–1171. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000092.
Zhang, H., and H. Li. 2010. “Multi objective particle swarm optimization for construction time-cost tradeoff problems.” Construct. Manage. Econ. 28 (1): 75–88. https://doi.org/10.1080/01446190903406170.
Zhang, Y., and S. Thomas Ng. 2012. “An ant colony system-based decision support system for construction time-cost optimization.” J. Civ. Eng. Manage. 18 (4): 580–589. https://doi.org/10.3846/13923730.2012.704164.
Zheng, D. X., S. T. Ng, and M. M. Kumaraswamy. 2005. “Applying Pareto ranking and niche formation to genetic algorithm-based multi-objective time-cost optimization.” J. Constr. Eng. Manage. 131 (1): 81–91. https://doi.org/10.1061/(ASCE)0733-9364(2005)131:1(81).

Information & Authors

Information

Published In

Go to Journal of Construction Engineering and Management
Journal of Construction Engineering and Management
Volume 149Issue 7July 2023

History

Received: Oct 5, 2022
Accepted: Feb 27, 2023
Published online: May 9, 2023
Published in print: Jul 1, 2023
Discussion open until: Oct 9, 2023

Permissions

Request permissions for this article.

Authors

Affiliations

Ph.D. Candidate, Dept. of Civil Engineering, Istanbul Technical Univ., Maslak, Istanbul 34469, Turkey (corresponding author). ORCID: https://orcid.org/0000-0002-2484-4553. Email: [email protected]
Professor Emeritus, Dept. of Civil, Architectural, and Environmental Engineering, Illinois Institute of Technology, Chicago, IL 60616. ORCID: https://orcid.org/0000-0002-1580-324X. Email: [email protected]
Professor, Dept. of Civil Engineering, Istanbul Technical Univ., Maslak, Istanbul 34469, Turkey. ORCID: https://orcid.org/0000-0003-2431-033X. Email: [email protected]

Metrics & Citations

Metrics

Citations

Download citation

If you have the appropriate software installed, you can download article citation data to the citation manager of your choice. Simply select your manager software from the list below and click Download.

View Options

Get Access

Access content

Please select your options to get access

Log in/Register Log in via your institution (Shibboleth)
ASCE Members: Please log in to see member pricing

Purchase

Save for later Information on ASCE Library Cards
ASCE Library Cards let you download journal articles, proceedings papers, and available book chapters across the entire ASCE Library platform. ASCE Library Cards remain active for 24 months or until all downloads are used. Note: This content will be debited as one download at time of checkout.

Terms of Use: ASCE Library Cards are for individual, personal use only. Reselling, republishing, or forwarding the materials to libraries or reading rooms is prohibited.
ASCE Library Card (5 downloads)
$105.00
Add to cart
ASCE Library Card (20 downloads)
$280.00
Add to cart
Buy Single Article
$35.00
Add to cart

Get Access

Access content

Please select your options to get access

Log in/Register Log in via your institution (Shibboleth)
ASCE Members: Please log in to see member pricing

Purchase

Save for later Information on ASCE Library Cards
ASCE Library Cards let you download journal articles, proceedings papers, and available book chapters across the entire ASCE Library platform. ASCE Library Cards remain active for 24 months or until all downloads are used. Note: This content will be debited as one download at time of checkout.

Terms of Use: ASCE Library Cards are for individual, personal use only. Reselling, republishing, or forwarding the materials to libraries or reading rooms is prohibited.
ASCE Library Card (5 downloads)
$105.00
Add to cart
ASCE Library Card (20 downloads)
$280.00
Add to cart
Buy Single Article
$35.00
Add to cart

Media

Figures

Other

Tables

Share

Share

Copy the content Link

Share with email

Email a colleague

Share