Framework for Estimating Quality-Related Incentive and Disincentive in Construction Projects

Publication: Journal of Construction Engineering and Management
Volume 149, Issue 5

Abstract

Having provisions in contracts that incentivize “better” performance has been identified as an effective means to encourage the contractor to perform better. In the construction industry, such incentive-disincentive (I/D) schemes have more widely been used for time, cost, and safety performance goals, they are conspicuous in their absence for quality-related performance. In fact, there is only limited literature available on the latter. This study presents a framework to estimate the quality I/D amounts in construction projects. The relationship between the cost of conformance and a “project defect score” has been used to estimate the I/D amount. The proposed framework for quality I/D has been validated for its effectiveness from the data of three actual recently completed projects. The findings clearly show that the proposed quality I/D scheme helped achieve a win–win situation between client and contractor. Though this study is based on data from the building industry, the proposed framework can be fine-tuned with more data and extended to other areas of construction.

Get full access to this article

View all available purchase options and get full access to this article.

Data Availability Statement

Some or all data, models, or codes that support the findings of this study are available from the corresponding author upon reasonable request.

References

Abdelsalam, H. M. E., and M. M. Gad. 2009. “Cost of quality in Dubai: An analytical case study of residential construction projects.” Int. J. Project Manage. 27 (6): 501–511. https://doi.org/10.1016/j.ijproman.2008.07.006.
Abu-Hijleh, S. F., and C. W. Ibbs. 1989. “Schedule-based construction incentives.” J. Constr. Eng. Manage. 115 (3). https://doi.org/10.1061/(ASCE)0733-9364(1989)115:3(430).
Al-Harbi, K. M. A. 1998. “Sharing fractions in cost-plus –incentive –fee contracts.” Int. J. Project Manage. 16 (2): 72–81. https://doi.org/10.1016/S0263-7863(97)00013-6.
Arditi, D., and H. M. Gunaydin. 1997. “Total quality management in the construction process.” Int. J. Project Manage. 15 (4): 235–243. https://doi.org/10.1016/S0263-7863(96)00076-2.
Arditi, D., J. Khisty, and F. Yasamis. 1997. “Incentive/disincentive provisions in highway contracts.” J. Constr. Eng. Manage. 123 (3): 302–307. https://doi.org/10.1061/(ASCE)0733-9364(1997)123:3(302).
Arditi, D., and F. Yasamis. 1998. “Incentive/disincentive contracts: Perceptions of owners and contractors.” J. Constr. Eng. Manage. 124 (5): 361–373. https://doi.org/10.1061/(ASCE)0733-9364(1998)124:5(361).
Atkinson, R. 1999. “Project management: Cost, time and quality, two best guesses and a phenomenon, it’s time to accept other success criteria.” Int. J. Project Manage. 17 (6): 337–342. https://doi.org/10.1016/S0263-7863(98)00069-6.
Badewi, A. 2016. “The impact of project management (PM) and benefits management (BM) practices on project success: Towards developing a project benefits governance framework.” Int. J. Project Manage. 34 (4): 761–778. https://doi.org/10.1016/j.ijproman.2015.05.005.
Baloi, D., and A. D. F. Price. 2003. “Modelling global risk factors affecting construction cost performance.” Int. J. Project Manage. 21 (4): 261–269. https://doi.org/10.1016/S0263-7863(02)00017-0.
Barnes, M. 1988. “Construction project management.” Int. J. Project Manage. 6 (2): 69–79. https://doi.org/10.1016/0263-7863(88)90028-2.
BCA (Building and Construction Authority). 2022. The construction quality assessment system. Singapore: BCA.
Belout, A., and C. Gauvreau. 2004. “Factors influencing project success: The impact of human resource management.” Int. J. Project Manage. 22 (1): 1–11. https://doi.org/10.1016/S0263-7863(03)00003-6.
Bower, D., G. Ashby, K. Gerald, and W. Smyk. 2002. “Incentive mechanisms for project success.” J. Manage. Eng. 18 (65): 37–43. https://doi.org/10.1061/(ASCE)0742-597X(2002)18:1(37).
Broome, J., and J. Perry. 2002. “How practitioners set share fractions in target cost contracts.” Int. J. Project Manage. 20 (1): 59–66. https://doi.org/10.1016/S0263-7863(00)00035-1.
Bubshait, A. A. 2003. “Incentive/ Disincentive contracts and its effects on industrial projects.” Int. J. Project Manage. 21 (1): 63–70. https://doi.org/10.1016/S0263-7863(01)00078-3.
Chan, A. P. C., D. Scott, and A. P. L. Chan. 2004. “Factors affecting the success of a construction project.” J. Constr. Eng. Manage. 130 (1): 153–155. https://doi.org/10.1061/(ASCE)0733-9364(2004)130:1(153).
Chan, D. W. M., P. T. I. Lam, and A. P. C. Chan. 2010. “Achieving better performance through target cost contracts: The tale of an underground railway station modification project.” Facilities 28 (5–6): 261–277. https://doi.org/10.1108/02632771011031501.
Choi, K., and Y. H. Kwak. 2012. “Decision support model for incentive/disincentive time-cost tradeoff.” Autom. Constr. 21 (5): 219–228. https://doi.org/10.1016/j.autcon.2011.06.006.
Crosby, P. B. 1979. Quality is free. New York: McGraw-Hill.
Deming, W. E. 1986. Out of the crisis. Cambridge, UK: MIT Press.
Dulaimi, M. F., M. P. Nepal, and M. Park. 2005. “A hierarchical structural model of assessing innovation and project performance.” Construct. Manage. Econ. 23 (6): 565–577. https://doi.org/10.1080/01446190500126684.
Eriksson, P. E., and M. Westerberg. 2011. “Effects of cooperative procurement procedures on construction project performance: A conceptual framework.” Int. J. Project Manage. 29 (2): 197–208. https://doi.org/10.1016/j.ijproman.2010.01.003.
Garg, S., and S. Misra. 2021a. “Causal model for rework in building construction for building construction.” J. Build. Eng. 43 (Nov): 103180. https://doi.org/10.1016/j.jobe.2021.103180.
Garg, S., and S. Misra. 2021b. “Distribution of rework issues in various reinforced concrete building components.” J. Perform. Constr. Facil. 35 (4): 04021033. https://doi.org/10.1061/(ASCE)CF.1943-5509.0001596.
Garg, S., and S. Misra. 2021c. “Understanding the components and magnitude of the cost of quality in building construction.” Eng. Constr. Archit. Manage. 2021 (Feb): 3. https://doi.org/10.1108/ECAM-08-2020-0642.
Geller, E. S. 1999. “Behaviour-based safety: Confusion, controversy and clarification.” Occup. Health Saf. 68 (1): 40–49.
Hasan, A., and K. N. Jha. 2016. “Acceptance of the incentive/disincentive contracting strategy in developing construction markets: Empirical study from India.” J. Constr. Eng. Manage. 142 (2): 04015064. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001048.
Hasan, A., and K. N. Jha. 2019. “Client and contractor roles in schedule incentive/disincentive projects: An empirical study from India.” Eng. Constr. Archit. Manage. 26 (3): 386–407. https://doi.org/10.1108/ECAM-06-2017-0104.
Hendrickson, C., and T. Au. 2008. Project management for construction fundamental concepts for owners, engineers, architects and builders. 2nd ed. Hoboken, NJ: Prentice Hall.
Heravi, G., and A. Jafari. 2014. “Cost of quality evaluation in mass-housing projects in developing countries.” J. Constr. Eng. Manage. 140 (5): 04014004. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000837.
Herbsman, Z. J., W. T. Chen, and W. C. Epstein. 1995. “Time is money: Innovative contracting methods in highway construction.” J. Constr. Eng. Manage. 121 (1): 273–281. https://doi.org/10.1061/(ASCE)0733-9364(1995)121:3(273).
Hosseinian, S. 2016. “An optimal time incentive/disincentive-based compensation in contracts with multiple agents.” Constr. Econ. Build. 16 (4): 35–53. https://doi.org/10.5130/AJCEB.v16i4.4983.
Ibbs, C. W., and D. B. Ashley. 1987. “Impact of various construction contract clauses.” J. Constr. Eng. Manage. 113 (3): 501–521. https://doi.org/10.1061/(ASCE)0733-9364(1987)113:3(501).
Ika, L. 2009. “Project success as a topic in project management journals.” Project Manage. J. 40 (4): 6–19. https://doi.org/10.1002/pmj.20137.
Jaafari, A. 1996. “Twinning time and cost in incentive-based contracts.” J. Manage. Eng. 12 (4): 62–72. https://doi.org/10.1061/(ASCE)0742-597X(1996)12:4(62).
Jaraiedi, M., R. W. Plummer, and M. S. Aber. 1995. “Incentives/disincentives guidelines for highway construction contracts.” J. Constr. Eng. Manage. 121 (1): 112–120. https://doi.org/10.1061/(ASCE)0733-9364(1995)121:1(112).
Jha, K., and K. Iyer. 2007. “Commitment, coordination, competence and the iron triangle.” Int. J. Project Manage. 25 (5): 527–540. https://doi.org/10.1016/j.ijproman.2006.11.009.
Jiang, Y., H. Chen, and S. Li. 2010. “Determination of contract time and incentive and disincentive values of highway construction projects.” Int. J. Constr. Educ. Res. 6 (4): 285–302. https://doi.org/10.1080/15578771.2010.521540.
Jugdev, K., and R. Müller. 2005. “A retrospective look at our evolving understanding of project success.” Project Manage. J. 36 (4): 19–31. https://doi.org/10.1177/875697280503600403.
Juran, J. M. 1962. Quality-control handbook. 2nd ed. New York: McGraw-Hill.
Kam, K. J., and A. H. Abdul Hamid. 2015. “The true motives behind the adoption of QLASSIC-CIS 7: 2006: As a quality assurance initiative in construction industry.” Int. J. Quality Reliab. Manage. 32 (6): 603–616. https://doi.org/10.1108/IJQRM-07-2013-0108.
Kamath, A., and R. Jayaraman. 2013. “CONQUAS systems standard for high quality project management.” Global’s Int. J. Manage. 1 (1): 51–67.
Kazaz, A., M. Birgonul, and S. Ulubeyli. 2005. “Cost-based analysis of quality in developing countries: A case study of building projects.” Build. Environ. 40 (10): 1356–1365. https://doi.org/10.1016/j.buildenv.2004.11.010.
Kwak, Y. H., and B. M. Smith. 2009. “Managing risks in mega defense acquisition projects: Performance, policy, and opportunities.” Int. J. Project Manage. 27 (8): 812–820. https://doi.org/10.1016/j.ijproman.2009.02.002.
Lee, E., and D. Alleman. 2018. “Ensuring efficient incentive and disincentive values for highway construction projects: A systematic approach balancing road user, agency and contractor acceleration costs and savings.” Sustainablity 10 (701): 1–22. https://doi.org/10.3390/su10030701.
Levy, S. M. 2007. Project Management in construction. 5th ed. New York: McGraw Hill.
Love, P. E. D., and J. Smith. 2003. “Benchmarking, benchaction and benchlearning: Rework mitigation in projects.” J. Manage. Eng. 19 (4): 147–159. https://doi.org/10.1061/(ASCE)0742-597X(2003)19:4(147).
Luu, V. T., S. Y. Kim, and T. A. Huynh. 2008. “Improving project management performance of large contractors using benchmarking approach.” Int. J. Project Manage. 26 (7): 758–769. https://doi.org/10.1016/j.ijproman.2007.10.002.
Manap, N., Y. K. Goh, and N. Syahrom. 2017. “Compulsory of Malaysia’s quality assessment system in construction (QLASSIC).” IOP Conf. Ser.: Earth Environ. Sci. 109 (1): 012008. https://doi.org/10.1088/1755-1315/109/1/012008.
Matthews, O., and G. A. Howell. 2005. “Integrated project delivery: An example of relational contracting.” Lean Constr. J. 2 (1): 46–61.
Meng, X., and B. Gallagher. 2011. “The impact of incentive mechanisms on project performance.” Int. J. Project Manage. 30 (3): 352–362. https://doi.org/10.1016/j.ijproman.2011.08.006.
Molenaar, K. R., P. Jeong, and S. Washington. 2009. “Framework for measuring corporate safety culture and its impact on construction safety performance.” J. Constr. Eng. Manage. 135 (6): 488–496. https://doi.org/10.1061/(ASCE)0733-9364(2009)135:6(488).
Pinto, J. 2010. Project management: Achieving competitive advantage. London: Pearson Education.
Pinto, J., and D. Slevin. 1988. “Project success: Definitions and measurement techniques.” Project Manage. J. 19 (1): 67–73.
Pollack, J., J. Helm, and D. Adler. 2018. “What is the iron triangle, and how has it changed?” Int. J. Managing Projects Bus. 11 (2): 527–547. https://doi.org/10.1108/IJMPB-09-2017-0107.
Shr, J. F., and W. T. Chen. 2004. “Setting maximum incentive for incentive/disincentive contracts for highway projects.” J. Constr. Eng. Manage. 130 (1): 84–93. https://doi.org/10.1061/(ASCE)0733-9364(2004)130:1(84).
Sillars, D. N., and J. Riedl. 2007. Framework model for determining incentive and disincentive amounts, 11–18. Washington, DC: Transportation Research Board.
Stukhart, G. 1984. “Contractual incentives.” J. Constr. Eng. Manage. 110 (1): 34–42. https://doi.org/10.1061/(ASCE)0733-9364(1984)110:1(34).
Tang, W., M. Qiang, C. F. Duffield, D. M. Young, and Y. Lu. 2007. “Risk management in the Chinese construction industry.” J. Constr. Eng. Manage. 133 (12): 944–956. https://doi.org/10.1061/(ASCE)0733-9364(2007)133:12(944).
Teo, E. A. L., F. Y. Y. Ling, and A. F. W. Chong. 2005. “Framework for project managers to manage construction safety.” Int. J. Project Manage. 23 (4): 329–341. https://doi.org/10.1016/j.ijproman.2004.09.001.
van Wyngaard, C., J. Pretorius, and L. Pretorius. 2012. “Theory of the triple constraint—A conceptual review.” In Proc., 2012 IEEE Int. Conf. on Industrial Engineering and Engineering Management, 1991–1997. New York: IEEE.
Walker, D. H. T., K. Hampson, and R. Peters. 2002. “Project alliancing vs project partnering: A case study of the Australian National Museum Project.” Supply Chain Manage. 7 (2): 83–91. https://doi.org/10.1108/13598540210425830.
Wong, P. S. P., and S. O. Cheung. 2008. “An analysis of the relationship between learning behavior and performance improvement of contracting organizations.” Int. J. Project Manage. 26 (2): 112–123. https://doi.org/10.1016/j.ijproman.2007.04.004.

Information & Authors

Information

Published In

Go to Journal of Construction Engineering and Management
Journal of Construction Engineering and Management
Volume 149Issue 5May 2023

History

Received: Jan 11, 2022
Accepted: Dec 13, 2022
Published online: Feb 20, 2023
Published in print: May 1, 2023
Discussion open until: Jul 20, 2023

Permissions

Request permissions for this article.

ASCE Technical Topics:

Authors

Affiliations

Formerly, Graduate Student, Dept. of Civil Engineering, Indian Institute of Technology Kanpur, Kanpur, Uttar Pradesh 208016, India (corresponding author). ORCID: https://orcid.org/0000-0002-1303-3288. Email: [email protected]
Sudhir Misra
Professor, Dept. of Civil Engineering, Indian Institute of Technology Kanpur, Kanpur, Uttar Pradesh 208016, India.

Metrics & Citations

Metrics

Citations

Download citation

If you have the appropriate software installed, you can download article citation data to the citation manager of your choice. Simply select your manager software from the list below and click Download.

View Options

Get Access

Access content

Please select your options to get access

Log in/Register Log in via your institution (Shibboleth)
ASCE Members: Please log in to see member pricing

Purchase

Save for later Information on ASCE Library Cards
ASCE Library Cards let you download journal articles, proceedings papers, and available book chapters across the entire ASCE Library platform. ASCE Library Cards remain active for 24 months or until all downloads are used. Note: This content will be debited as one download at time of checkout.

Terms of Use: ASCE Library Cards are for individual, personal use only. Reselling, republishing, or forwarding the materials to libraries or reading rooms is prohibited.
ASCE Library Card (5 downloads)
$105.00
Add to cart
ASCE Library Card (20 downloads)
$280.00
Add to cart
Buy Single Article
$35.00
Add to cart

Get Access

Access content

Please select your options to get access

Log in/Register Log in via your institution (Shibboleth)
ASCE Members: Please log in to see member pricing

Purchase

Save for later Information on ASCE Library Cards
ASCE Library Cards let you download journal articles, proceedings papers, and available book chapters across the entire ASCE Library platform. ASCE Library Cards remain active for 24 months or until all downloads are used. Note: This content will be debited as one download at time of checkout.

Terms of Use: ASCE Library Cards are for individual, personal use only. Reselling, republishing, or forwarding the materials to libraries or reading rooms is prohibited.
ASCE Library Card (5 downloads)
$105.00
Add to cart
ASCE Library Card (20 downloads)
$280.00
Add to cart
Buy Single Article
$35.00
Add to cart

Media

Figures

Other

Tables

Share

Share

Copy the content Link

Share with email

Email a colleague

Share