Optimized Approach toward Identification of Influential Cost Overrun Causes in Construction Industry

Publication: ASCE-ASME Journal of Risk and Uncertainty in Engineering Systems, Part A: Civil Engineering
Volume 9, Issue 2

Abstract

Prioritization is considered a core concept in cost overrun analysis. This study first aimed at proposing a new approach for the calculation of total risk magnitude (TRM) and, second, introduced the application of Pareto analysis in the prioritization of cost overrun causes. A case study is delineated to explain the applicability of the aforementioned approaches. Thirty-eight unique causes of cost overrun in urban-related construction projects were identified and a survey was conducted among construction professionals in Iran. The TRM for each cost overrun cause is calculated using single-attribute (SA), double-attribute (DA), and multiple-attribute (MA) approaches. Henceforth, based on calculated TRM, the causes are prioritized using the relative importance index (RII) and Pareto analysis. A comparative analysis revealed that not only could Pareto-based prioritization be effectively employed for prioritization, but also, the proposed MA approach for TRM calculation optimizes the efficiency of the most influential cause identification.

Get full access to this article

View all available purchase options and get full access to this article.

Data Availability Statement

All the data and models that support the findings of this study are available from the corresponding author upon reasonable request.

References

Abdel-Monem, M., A.-R. El-Mohr, and K. El-Dash. 2022. “Cost overrun gap analysis in construction projects: State -of-the-art.” Eng. Res. J. 51 (3): 76–97. https://doi.org/10.21608/erjsh.2022.249998.
Abusafiya, H. A. M., and S. A. M. Suliman. 2017. “Causes and effects of cost overrun on construction project in Bahrain: Part 2 (PLS-SEM path modelling).” Mod. Appl. Sci. 11 (7): 28. https://doi.org/10.5539/mas.v11n7p28.
Abusafiya, H. A. M., and S. M. A. Suliman. 2017. “Causes and effects of cost overrun on construction project in Bahrain: Part I (ranking of cost overrun factors and risk mapping).” Mod. Appl. Sci. 11 (7): 20. https://doi.org/10.5539/mas.v11n7p20.
Adam, S. U., M. N. Shamsudin, S. F. Sidique, K. A. Rahim, and A. Radam. 2013. “Attribute prioritization in choice experiment pre-design: Suggested method and application to solid waste management service improvement.” J. Energy Technol. Policy 3 (11): 291–298.
Akogbe, R. K. T. M., X. Feng, and J. Zhou. 2013. “Importance and ranking evaluation of delay factors for development construction projects in Benin.” KSCE J. Civ. Eng. 17 (6): 1213–1222. https://doi.org/10.1007/s12205-013-0446-2.
Akram, M., T. H. Ali, N. A. Memon, and S. H. Khahro. 2017. “Causal attributes of cost overrun in construction projects of Pakistan.” Int. J. Civ. Eng. Technol. 8 (6): 477–483.
Al Hosani, I. I. A., F. T. Dweiri, and U. Ojiako. 2020. “A study of cost overruns in complex multi-stakeholder road projects in the United Arab Emirates.” Int. J. Syst. Assur. Eng. Manage. 11 (6): 1250–1259. https://doi.org/10.1007/s13198-020-00979-8.
Aljohani, A. 2017. “Construction projects cost overrun: What does the literature tell us?” Int. J. Innovation Manage. Technol. 8 (2): 137–143. https://doi.org/10.18178/ijimt.2017.8.2.717.
Allahaim, F. S. A., and L. Liu. 2015. An empirical classification of cost overrun in infrastructure projects by using cluster analysis. In Proc., 4th Int. Utzon Symp. Sydney Australia: Univ. of Technology.
Amini, S., A. Rezvani, and M. Tabasi. 2021. “Identification and ranking significant factors causing cost overrun in the design and construction process of buildings using the BWM method (Case study City of Mashhad).” Urban Manage. Study 12 (44): 67–83.
Amini, S., A. Rezvani, M. Tabassi, and S. S. Malek Sadati. 2022. “Causes of cost overruns in building construction projects in Asian countries; Iran as a case study.” Eng. Constr. Archit. Manage. https://doi.org/10.1108/ECAM-05-2021-0445.
Annamalaisami, C. D., and A. Kuppuswamy. 2021. “Managing cost risks: Toward a taxonomy of cost overrun factors in building construction projects.” ASCE-ASME J. Risk Uncertainty Eng. Syst. Part A: Civ. Eng. 7 (2): 04021021. https://doi.org/10.1061/AJRUA6.0001132.
Asiedu, R. O., and C. Ameyaw. 2021. “A system dynamics approach to conceptualise causes of cost overrun of construction projects in developing countries.” Int. J. Build. Pathol. Adapt. 39 (5): 831–851. https://doi.org/10.1108/IJBPA-05-2020-0043.
Assaad, R., I. H. El-Adaway, and I. S. Abotaleb. 2020. “Predicting project performance in the construction industry.” J. Constr. Eng. Manage. 146 (5): 04020030. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001797.
Azhar, N., R. Farooqui, and S. Ahmed. 2008. “Cost overrun factors in construction industry of Pakistan.” In Proc., 1st Int. Conf. on Construction in Developing Countries (ICCIDCI), Advancing and Integrating Construction Education, Research & Practice, 499–508.
Balali, A., R. C. Moehler, and A. Valipour. 2022. “Ranking cost overrun factors in the mega hospital construction projects using Delphi-SWARA method: An Iranian case study.” Int. J. Construct. Manage. 22 (13): 2577–2585. https://doi.org/10.1080/15623599.2020.1811465.
Bartlett, J. E., J. W. Kotrlik, and C. C. Higgins. 2001. “Determining appropriate sample size in survey research.” Inf. Technol. Learn. Perform. J. 19 (1): 43–50.
Bekr, G. A. 2015. “Identifying factors leading to cost overrun in construction projects in Jordan.” J. Constr. Eng. Technol. Manage. 5 (3): 25–33.
Best, M., and D. Neuhauser. 2006. “Joseph Juran: Overcoming resistance to organisational change.” Qual. Saf. Health Care 15 (5): 380–382. https://doi.org/10.1136/qshc.2006.020016.
Cabuñas, J. T., and D. L. Silva. 2019. “Exploratory factor-item analytic approach for construction project cost overrun using oblique promax rotation for predictors determination.” Int. J. Innovative Technol. Exploring Eng. 8 (6): 47–54.
CBI (Central Bank of Iran). 2019. “Construction and housing and economic development in Iran CBI.” Accessed June 22, 2019. https://www.cbi.ir/simplelist/22392.aspx.
Cheng, Y. M. 2014. “An exploration into cost-influencing factors on construction projects.” Int. J. Project Manage. 32 (5): 850–860. https://doi.org/10.1016/j.ijproman.2013.10.003.
Cindrela Devi, A., and K. Ananthanarayanan. 2017. “Factors influencing cost over-run in Indian construction projects.” MATEC Web Conf. 120 (Aug): 02023. https://doi.org/10.1051/matecconf/201712002023.
Craft, R. C., and C. Leake. 2002. “The Pareto principle in organizational decision making.” Manage. Decis. 40 (8): 729–733. https://doi.org/10.1108/00251740210437699.
Dabirian, S., M. Khanzadi, and M. Abdollahi. 2020. “Investigation of the most important factors affecting cost overruns in construction projects using hybrid system dynamic and DEMATEL method.” Sharif J. Civ. Eng. 36 (3.1): 13–28. https://doi.org/10.24200/j30.2019.51915.2448.
Derakhshanalavijeh, R., and J. M. C. Teixeira. 2017. “Cost overrun in construction projects in developing countries, Gas-Oil industry of Iran as a case study.” J. Civ. Eng. Manage. 23 (1): 125–136. https://doi.org/10.3846/13923730.2014.992467.
Durdyev, S., S. Ismail, and N. A. Bakar. 2010. “Factors causing cost overruns in construction of residential projects: Case study of Turkey.” Asian J. Manage. Res. 1 (1): 3–12.
Etikan, I. 2016. “Comparison of convenience sampling and purposive sampling.” Am. J. Theor. Appl. Stat. 5 (1): 1. https://doi.org/10.11648/j.ajtas.20160501.11.
Famiyeh, S., C. T. Amoatey, E. Adaku, and C. S. Agbenohevi. 2017. “Major causes of construction time and cost overruns: A case of selected educational sector projects in Ghana.” J. Eng. Des. Technol. 15 (2): 181–198. https://doi.org/10.1108/JEDT-11-2015-0075.
França, A., and A. Haddad. 2018. “Causes of construction projects cost overrun in Brazil.” Int. J. Sustainable Constr. Eng. Technol. 9 (1): 69–83. https://doi.org/10.30880/ijscet.2018.09.01.006.
Gao, X., et al. 2004. Living with risk: A global review of disaster reduction initiatives. Geneva: United Nations Office for Diasester Risk Reduction.
Gliem, J. A., and R. R. Gliem. 2003. “Calculating, interpreting, and reporting Cronbach’s alpha reliability coefficient for Likert-type scales.” In Proc., 2003 Midwest Research to Practice Conf. in Adult, Continuing, and Community Education, 82–88. Columbus, OH: Ohio State Univ. https://doi.org/10.1109/PROC.1975.9792.
Gunduz, M., and O. L. Maki. 2018. “Assessing the risk perception of cost overrun through importance rating.” Technol. Econ. Dev. Economy 24 (5): 1829–1844. https://doi.org/10.3846/20294913.2017.1321053.
Harvey, H. B., and S. T. Sotardi. 2018. “The Pareto principle.” J. Am. College Radiol. 15 (6): 931. https://doi.org/10.1016/j.jacr.2018.02.026.
Herrera, R. F., O. Sánchez, K. Castañeda, and H. Porras. 2020. “Cost overrun causative factors in road infrastructure projects: A frequency and importance analysis.” Appl. Sci. (Switzerland) 10 (16): 5506. https://doi.org/10.3390/app10165506.
Hopkins, M., P. Close, D. Hillson, and S. Ward. 2008. Prioritising project risks a short guide to useful techniques. Princes Risborough, Buckinghamshire: Association for Project Management.
Hossen, M. M., S. Kang, and J. Kim. 2015. “Construction schedule delay risk assessment by using combined AHP-RII methodology for an international NPP project.” Nuclear Eng. Technol. 47 (3): 362–379. https://doi.org/10.1016/j.net.2014.12.019.
Jackson, S. 2002. “Project cost overruns and risk management.” In Proc., Association of Researchers in Construction Management 18th Annual ARCOM Conf., 1–10. England: Univ. of Reading.
Johnson, R. M., and R. I. I. Babu. 2020. “Time and cost overruns in the UAE construction industry: A critical analysis.” Int. J. Construct. Manage. 20 (5): 402–411. https://doi.org/10.1080/15623599.2018.1484864.
Kapur Shah, R. 2016. “An exploration of causes for delay and cost overrun in construction projects: A case study of Australia, Malaysia & Ghana.” J. Adv. Coll. Eng. Manage. 2 (1): 41–55. https://doi.org/10.3126/jacem.v2i0.16097.
Kassem, M. A., M. A. Khoiry, and N. Hamzah. 2020. “Using relative importance index method for developing risk map in oil and gas construction projects.” J. Kejuruteraan 32 (3): 441–453. https://doi.org/10.17576/jkukm-2020-32(3)-09.
Kim, S.-Y., K. N. Tuan, J. D. Lee, H. Pham, and V. T. Luu. 2018. “Cost overrun factor analysis for hospital projects in Vietnam.” KSCE J. Civ. Eng. 22 (1): 1–11. https://doi.org/10.1007/s12205-017-0947-5.
Larsen, J. K., G. Q. Shen, S. M. Lindhard, and T. D. Brunoe. 2016. “Factors affecting schedule delay, cost overrun, and quality level in public construction projects.” J. Manage. Eng. 32 (1): 04015032. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000391.
Latif, Q. B. A. I., R. K. M. Gopang, and I. A. Rahman. 2020. “Substantial factors of construction management causes budget overrun in construction industry of Oman.” Int. J. Sustainable Constr. Eng. Technol. 11 (2): 196–203. https://doi.org/10.30880/ijscet.2020.11.02.024.
Lavrakas, P. J. 2008. Encyclopedia of survey research methods. 1st ed. Thousand Oaks, CA: SAGE.
Le-Hoai, L., Y. D. Lee, and J. Y. Lee. 2008. “Delay and cost overruns in Vietnam large construction projects: A comparison with other selected countries.” KSCE J. Civ. Eng. 12 (6): 367–377. https://doi.org/10.1007/s12205-008-0367-7.
Machin, D., M. J. Campbell, S. B. Tan, and S. H. Tan. 2018. Sample sizes for clinical, laboratory and epidemiology studies. 4th ed. New York: John Wiley & Sons.
Mahamid, I. 2016. “Micro and macro level of dispute causes in residential building projects: Studies of Saudi Arabia.” J. King Saud Univ. Eng. Sci. 28 (1): 12–20. https://doi.org/10.1016/j.jksues.2014.03.002.
Mahamid, I., and N. Dmaidi. 2013. “Risks leading to cost overrun in building construction from consultants’ perspective.” Organ. Technol. Manage. Constr. 5 (2): 860–873. https://doi.org/10.5592/otmcj.2013.2.5.
Matin, D. M. 2016. “Identifying the effective factors for cost overrun and time delay in water construction projects.” Eng. Technol. Appl. Sci. Res. 6 (4): 1062–1066. https://doi.org/10.48084/etasr.706.
Memon, A. H., I. Abdul Rahman, and A. A. Abdul Aziz. 2012. “The cause factors of large project’s cost overrun: A survey in the southern part of Peninsular Malaysia.” Int. J. Real Estate Stud. 7 (2): 1–15.
Memon, A. H., and I. A. Rahman. 2013. “Analysis of cost overrun factors for small scale construction projects in Malaysia using PLS-SEM method.” Mod. Appl. Sci. 7 (8): 78–88. https://doi.org/10.5539/mas.v7n8p78.
Memon, A. H., I. A. Rahman, and A. A. A. Azis. 2011. “Preliminary study on causative factors leading to construction cost overrun.” Int. J. Sustainable Constr. Eng. Technol. 2 (1): 57–71.
Nasir, A. R., H. F. Gabriel, and R. M. Choudhry. 2011. “Cost and time overruns in highway projects of Pakistan.” In Proc., 6th Int. Conf. on Construction in the 21st Century Construction Challenges in the New Decade, 69–76. Selangor, Malaysia: Faculty of architecture, planning and surveying Universiri Teknoloji MARA.
Nasser, H., and M. Al. 2020. “An investigation the causes of projects delay and cost overrun for construction industry in oman and their impact on realization of Oman Vision 2040.” Int. J. Econ. Commerce Manage. VIII (11): 125.
Neeraj Jha, K., and W. Koshe. 2016. “Investigating causes of construction delay in Ethiopian construction industries.” J. Civ. Constr. Environ. Eng. 1 (1): 18–29. https://doi.org/10.11648/j.jccee.20160101.13.
Nega, F. 2008. “Causes and effects of cost overrun on public building construction projects in Ethiopia.” Unpublished doctoral dissertation, Addis Ababa Univ.
Olawale, Y. A., and M. Sun. 2010. “Cost and time control of construction projects: Inhibiting factors and mitigating measures in practice.” Construct. Manage. Econ. 28 (5): 509–526. https://doi.org/10.1080/01446191003674519.
Pham, H., T. Van Luu, S. Y. Kim, and D. T. Vien. 2020. “Assessing the impact of cost overrun causes in transmission lines construction projects.” KSCE J. Civ. Eng. 24 (4): 1029–1036. https://doi.org/10.1007/s12205-020-1391-5.
PMI (Project Management Institute). 2017. Vol. 6 of PMBOK Guide Sixth Edition (PMI, 2017). Newtown Square, PA: PMI.
Rachid, Z., B. Toufik, and B. Mohammed. 2019. “Causes of schedule delays in construction projects in Algeria.” Int. J. Construct. Manage. 19 (5): 371–381. https://doi.org/10.1080/15623599.2018.1435234.
Rahman, I. A., A. H. Memon, and A. T. A. Karim. 2013a. “Relationship between factors of construction resources affecting project cost.” Mod. Appl. Sci. 7 (1): 67–75. https://doi.org/10.5539/mas.v7n1p67.
Rahman, I. A., A. H. Memon, and A. T. A. Karim. 2013b. “Significant factors causing cost overruns in large construction projects in Malaysia.” J. Appl. Sci. 13 (2): 286–293. https://doi.org/10.3923/jas.2013.286.293.
Ramabhadran, M. 2018. “An investigation into cost overrun in construction projects in United Arab Emirates.” Int. J. Constr. Eng. Manage. 7 (1): 1–21. https://doi.org/10.5923/j.ijcem.20180701.01.
Ramanathan, C., N. S. Potty, and A. B. Idrus. 2012. “Analysis of time and cost overrun in Malaysian construction.” In Vol. 452–453 of Advanced materials research, 1002–1008. Wollerau, Switzerland: Trans Tech Publication.
Regmi, P. R., E. Waithaka, A. Paudyal, P. Simkhada, and E. van Teijlingen. 2016. “Guide to the design and application of online questionnaire surveys.” Nepal J. Epidemiol. 6 (4): 640. https://doi.org/10.3126/nje.v6i4.17258.
Samarghandi, H., S. M. M. Tabatabaei, P. Taabayan, A. M. Hashemi, and K. Willoughby. 2016. “Studying the reasons for delay and cost overrun in construction projects: The case of Iran.” J. Constr. Dev. Countries 21 (1): 51–84. https://doi.org/10.21315/jcdc2016.21.1.4.
Sayed, M., M. Abdel-Hamid, and K. El-Dash. 2020. “Improving cost estimation in construction projects.” Int. J. Construct. Manage. (Dec): 1–20. https://doi.org/10.1080/15623599.2020.1853657.
Shoar, S., T. W. Yiu, S. Payan, and M. Parchamijalal. 2022. “Modeling cost overrun in building construction projects using the interpretive structural modeling approach: A developing country perspective.” Eng. Constr. Archit. Manage. https://doi.org/10.1108/ECAM-08-2021-0732.
Tejale, D. S., S. D. Khandekar, and J. R. Patil. 2015. “Analysis of construction project cost overrun by statistical method.” Int. J. Adv. Res. Comput. Sci. Manage. Stud. 3 (5): 349–355.
Ubani, E. C., K. A. Okorocha, and S. C. Emeribe. 2013. “Analysis of factors influencing time and cost overruns on construction projects in South Eastern Nigeria.” Int. J. Manage. Sci. Bus. Res. 2 (2): 73–84.
Urbanucci, L., and D. Testi. 2018. “Optimal integrated sizing and operation of a CHP system with Monte Carlo risk analysis for long-term uncertainty in energy demands.” Energy Convers. Manage. 157 (Feb): 307–316. https://doi.org/10.1016/j.enconman.2017.12.008.

Information & Authors

Information

Published In

Go to ASCE-ASME Journal of Risk and Uncertainty in Engineering Systems, Part A: Civil Engineering
ASCE-ASME Journal of Risk and Uncertainty in Engineering Systems, Part A: Civil Engineering
Volume 9Issue 2June 2023

History

Received: Aug 23, 2022
Accepted: Oct 19, 2022
Published online: Jan 14, 2023
Published in print: Jun 1, 2023
Discussion open until: Jun 14, 2023

Permissions

Request permissions for this article.

Authors

Affiliations

Ph.D. Candidate, Dept. of Civil Engineering, Eastern Mediterranean Univ., North Cyprus via Mersin 10, Famagusta 99628, Turkey (corresponding author). ORCID: https://orcid.org/0000-0003-4403-036X. Email: [email protected]
Tolga Celik, Ph.D. [email protected]
Associate Professor, Dept. of Civil Engineering, Eastern Mediterranean Univ., North Cyprus via Mersin 10, Famagusta 99628, Turkey. Email: [email protected]

Metrics & Citations

Metrics

Citations

Download citation

If you have the appropriate software installed, you can download article citation data to the citation manager of your choice. Simply select your manager software from the list below and click Download.

Cited by

  • Navigating the Ethical Discourse in Construction: A State-of-the-Art Review of Relevant Literature, Journal of Construction Engineering and Management, 10.1061/JCEMD4.COENG-13880, 150, 3, (2024).
  • Comparative analysis between different risk score calculation approaches, Engineering, Construction and Architectural Management, 10.1108/ECAM-11-2022-1097, (2023).

View Options

Get Access

Access content

Please select your options to get access

Log in/Register Log in via your institution (Shibboleth)
ASCE Members: Please log in to see member pricing

Purchase

Save for later Information on ASCE Library Cards
ASCE Library Cards let you download journal articles, proceedings papers, and available book chapters across the entire ASCE Library platform. ASCE Library Cards remain active for 24 months or until all downloads are used. Note: This content will be debited as one download at time of checkout.

Terms of Use: ASCE Library Cards are for individual, personal use only. Reselling, republishing, or forwarding the materials to libraries or reading rooms is prohibited.
ASCE Library Card (5 downloads)
$105.00
Add to cart
ASCE Library Card (20 downloads)
$280.00
Add to cart
Buy Single Article
$35.00
Add to cart

Get Access

Access content

Please select your options to get access

Log in/Register Log in via your institution (Shibboleth)
ASCE Members: Please log in to see member pricing

Purchase

Save for later Information on ASCE Library Cards
ASCE Library Cards let you download journal articles, proceedings papers, and available book chapters across the entire ASCE Library platform. ASCE Library Cards remain active for 24 months or until all downloads are used. Note: This content will be debited as one download at time of checkout.

Terms of Use: ASCE Library Cards are for individual, personal use only. Reselling, republishing, or forwarding the materials to libraries or reading rooms is prohibited.
ASCE Library Card (5 downloads)
$105.00
Add to cart
ASCE Library Card (20 downloads)
$280.00
Add to cart
Buy Single Article
$35.00
Add to cart

Media

Figures

Other

Tables

Share

Share

Copy the content Link

Share with email

Email a colleague

Share