Scale and Condition Economies in Asset Preservation Cost Functions: Case Study Involving Flexible Pavement Treatments
Publication: Journal of Transportation Engineering
Volume 138, Issue 2
Abstract
Estimates of planning-level treatment costs are vital inputs for preservation project budgeting, prioritization, and programming in highway asset management. However, with the paucity of analytical research on highway asset preservation costing, agencies have resorted to the use of average costs. However, average cost values fail to adequately accommodate the influence of cost factors such as project size and asset condition at the time of the preservation treatment. In addressing this issue, this paper explores the efficacy of different mathematical specifications, including the Cobb-Douglas form and a variety of other nonlinear forms, for developing treatment cost functions. The paper shows how flexible formulations could be used to specify the response variable in order to avoid unduly restricting the models and to yield cost estimates that are more reliable compared to average costs. The paper shows how to investigate the direction and strengths of scale economies and condition economies in highway asset preservation costs using mathematical forms that allow for determining the partial derivatives of treatment cost with respect to asset dimensions and pretreatment condition. The paper demonstrates its concepts by using data on flexible pavement preservation treatments at a midwestern state highway agency.
Get full access to this article
View all available purchase options and get full access to this article.
Acknowledgments
The authors acknowledge the assistance of INDOT personnel in the data collection. The contents of this paper reflect the views of the authors, who are responsible for the facts and the accuracy of the data presented. The contents do not necessarily reflect the official views or policies of the Federal Highway Administration or the Indiana Department of Transportation, nor do the contents constitute a standard, specification, or regulation.
References
Adeli, H., and Wu, M. (1998). “Regularization neural network for construction cost estimation.” J. Constr. Eng. Manage., 124(1), 18–24.
Carnahan, V., Davis, W. J., Shahin, M. Y., Keane, P. L., and Wu, M. I. (1987). “Optimal maintenance decisions for pavement management.” J. Transp. Eng., 113(5), 554–573.
Chen, D. H., Lin, D. F., and Luo, H. L. (2003). “Effectiveness of preventative maintenance treatments using fourteen SPS-3 sites in Texas.” J. Perform. Constr. Facil., 17(3), 136–143.
Collura, J., Spring, G., and Black, K. B. (1993). “Service lives and costs of local highway maintenance decisions for pavement management.” J. Transp. Eng., 119(1).
Elhag, T. M. S., and Boussebaine, A. H. (1998). “Factors affecting cost and duration of construction projects.” EPSRC Research Rep. Phase (1), School of Architecture and Building Engineering, Univ. of Liverpool, Liverpool, UK.
Federal Highway Administration (FHWA). (2002). “HERS-ST highway economic requirements system (HERS)—State version.” U.S. Dept. of Transportation, Washington, DC.
Federal Highway Administration (FHWA). (2009). “Highway construction price trends and the consumer price index.” Office of Highway Policy Information, Washington, DC. 〈www.fhwa.dot.gov/ohim/onh00/line15.htm〉 (Mar. 20, 2009).
Feighan, K. J., Shahin, M. Y., and Sinha, K. C. (1987). “A dynamic programming approach to optimization for pavement management systems.” Proc., 2nd North American Conf. on Managing Pavements, Road and Transportation Assoc. of Canada, Toronto, Canada.
General Accounting Office (GAO). (2004). “Comparison of states’ highway construction costs.” Publication GAO-04-113R, Washington, DC.
Gkritza, K., and Labi, S. (2008). “Estimating cost discrepancies in highway contracts: A multistep econometric approach.” J. Constr. Eng. Manage., 134(12), 953–962.
Haas, R., Tighe, S. L., and Falls, L. C. (2006). “Determining return on long-life pavement investments.” Transp. Res. Rec. 1974, 10–17.
Hall, K. T., Correa, C. E., Carpenter, S. H., and Elliott, R. P. (2001). “Rehabilitation strategies for highway pavements.” NCHRP Project C1-38, National Research Council, Washington, DC.
Hartgen, D. T., and Talvitie, A. P. (1995). “Comparative performance of transportation systems: Pitfalls and prospects.”, Transportation Pub. Rep. No. 118, Charlotte Center for Interdisciplinary Transportation Studies, Univ. of North Carolina, Charlotte, NC.
Hegazy, T., and Ayed, A. (1998). “Neural network model for parametric cost estimation of highway projects.” J. Constr. Eng. Manage., 124(3), 210–218.
Indiana Dept. of Transportation (INDOT). (2003). “Construction contracts information.” 〈http://www.in.gov/dot/div/contracts/letting/oldletting.html〉.
Jahren, C., and Ashe, A. (1990). “Predictors of cost-overrun rates.” J. Constr. Eng. Manage., 116(3), 548–551.
Kim, G.-H., An, S.-H., and Kang, K.-I. (2004). “Comparison of construction cost estimating models based on regression analysis.” Neural Networks, and Case-Based Reasoning. Build. Environ., 39(10), 1235–1242.
Koehn, E., Young, R., Kuchar, J., and Seling, F. (1978). “Cost of delays in construction.” J. Constr. Div., 104(3), 323–331.
Labi, S., and Sinha, K. C. (2003). “The effectiveness of maintenance and its impact on capital expenditures.” Pub. No. FHWA/IN/JTRP-2002/27, Joint Transportation Research Program, Indiana Dept. of Transportation and Purdue Univ., W. Lafayette, IN.
Li, N., Huot, M., and Haas, R. (1997). “Cost-effectiveness-based priority programming of standardized pavement maintenance.” Transp. Res. Rec. 1592, Transportation Research Board, Washington, DC, 8–16.
McCarthy, P. S. (2001). Transportation economics—Theory and practice: A case study approach, Blackwell Publishers, Malden, MA.
Morian, D. A., Coleman, L., Frith, D. J., Stoffels, S. M., and Dawood, D. (2003). “Pennsylvania SPS-6 performance at 10 years: Evaluation of concrete pavement rehabilitation strategies.” Transp. Res. Rec. 1823, Transportation Research Board, Washington, DC, 28–38.
PASW Statistics 18 [Computer software]. SPSS Inc., Chicago, IL. 〈http://www.spss.com/software/statistics/statistics-base〉 (Jan., 20, 2009).
Pearce, A. R., Gregory, Rita A., and Williams, L. (1999). “Range estimating for risk management using artificial neural networks.” J. Param. Est., 14(1), 88–93.
Ramaswamy, R., and Ben-Akiva, M. (1990). “Estimation of highway pavement deterioration from in-service pavement data.” Transp. Res. Rec. 1272, Transportation Research Board, Washington, DC, 96–106.
SAS OnlineDoc 9.1.3 [Computer software]. SAS Institute, Inc., Cary, NY. 〈http://support.sas.com/onlinedoc/913/docMainpage.jsp〉 (Jun. 1, 2009).
Sinha, K. C., and Labi, S. (2007). Transportation decision making—Principles of project evaluation and programming, Wiley, Hoboken, NJ.
Sodikov, J. (2005). “Cost estimation of highway projects in developing countries: Artificial neural network approach.” J. Eastern Asia Society Transp. Studies, 6, 1036–1047.
Sprague, C. J. (2006). “Study of the cost-effectiveness of various flexible pavement maintenance treatments.” Transp. Research Circular E-C098, Transportation Research Board, Washington, DC, 45–53.
Stevens, J. D. (1995). “Cost estimating and forecasting for highway work in Kentucky.” Pub. KTC 95-12, Kentucky Transportation Center, Univ. of Kentucky, Lexington, KY.
Washington State Dept. of Transportation (WSDOT). (2002). “Highway construction cost comparison survey.” Final Rep., Olympia, WA.
Wilmot, C. G., and Cheng, G. (2003). “Estimating future highway construction costs.” J. Constr. Eng. Manage., 129(3), 272–279.
Information & Authors
Information
Published In
Copyright
© 2012 American Society of Civil Engineers.
History
Received: Sep 16, 2010
Accepted: Jun 29, 2011
Published online: Jul 1, 2011
Published in print: Feb 1, 2012
Authors
Metrics & Citations
Metrics
Citations
Download citation
If you have the appropriate software installed, you can download article citation data to the citation manager of your choice. Simply select your manager software from the list below and click Download.