Leveling Process of Annual Budgetary Requirements for Pavement Preservation

Publication: Journal of Infrastructure Systems
Volume 20, Issue 1

Abstract

This paper presents a model for leveling annual budgetary requirements (ABRs) for pavement preservation programs over a multiyear analysis period. Given the information such as the candidate pavement preservation projects, associated costs, application years, and time floats to be shifted, the presented leveling process adjusts the application years of the projects to minimize the variance among ABRs. The minimum moment method is modified considering the dummy period that is to shift preservation projects within their time floats and additional constraints for the leveling process. To validate the leveling model, this study uses Indiana Department of Transportation (INDOT) pavement preservation projects as a case study that consists of a total of 193 projects over a three-year analysis period between 2010 and 2012. As a result of the case study, the leveling process provides relatively consistent ABRs over the three-year analysis period for INDOT. Therefore, the major contributions of this research will assist public agencies in: (1) identifying the consistent budgetary requirements to be dedicated to the pavement preservation program, and (2) establishing a long-term budgetary goal to include all needs of the pavement preservation program at the network level.

Get full access to this article

View all available purchase options and get full access to this article.

Acknowledgments

This research was funded by the Joint Transportation Research Program (JTRP) and the Indiana Department of Transportation (INDOT). The authors would like to thank the Study Advisory Committee for their valuable assistance and technical guidance in the course of performing this research. Part of the research presented in this paper is based on work supported by JTRP/INDOT. Any opinions, findings, and conclusions or recommendations expressed in this material are those of the authors and do not necessarily reflect the views of JTRP/INDOT.

References

AASHTO. (2001). “Pavement management guide: Executive summary report.” Washington, DC.
Christodoulou, S. E., Ellinas, G., and Michaelidou-Kamenou, A. (2010). “Minimum moment method for resource leveling using entropy maximization.” J. Constr. Eng. Manage., 518–527.
Code of Federal Regulations. “Development and content of the statewide transportation improvement program (STIP).” 〈http://www.gpo.gov/fdsys/pkg/CFR-2011-title23-vol1/xml/CFR-2011-title23-vol1-sec450-216.xml〉.
Commonwealth of Massachusetts. (2007). FY 2008–2012 five-year capital investment plan, Boston, MA.
Easa, S. M. (1989). “Resource leveling in construction by optimization.” J. Constr. Eng. Manage., 302–316.
Federal Highway Administration (FHWA). (2005). “Pavement preservation definitions.” 〈http://www.fhwa.dot.gov/pavement/preservation/091205.cfm〉 (Jul. 5, 2011).
Georgy, M. E. (2008). “Evolutionary resource scheduler for linear projects.” Autom. Construct., 17(5), 573–583.
Harris, R. B. (1978). Precedence and arrow networking techniques for construction, John Wiley and Sons, New York.
Harris, R. B. (1990). “Packing method for resource leveling (PACK).” J. Constr. Eng. Manage., 331–350.
Hegazy, T. (1999). “Optimization of resource allocation and leveling using genetic algorithms.” J. Constr. Eng. Manage., 167–175.
Hiyassat, M. A. S. (2001). “Applying modified minimum moment method to multiple resource leveling.” J. Constr. Eng. Manage., 192–198.
Indiana Department of Transportation (INDOT). (2010). Statewide transportation improvement program: FY 2010-2013, Indianapolis.
Kartam, N., and Tongthong, T. (1998). “An artificial neural network for resource leveling problems.” Artificial Intel. Eng. Design, Analysis Manuf., 12(3), 273–287.
Leu, S. S., Yang, C. H., and Huang, J. C. (2000). “Resource leveling in construction by genetic algorithm-based optimization and its decision support system application.” Autom. Construct., 10(1), 27–41.
Martinez, J., and Ioannou, P. (1993). “Resource leveling based on the modified minimum moment heuristic.” Proc., 5th Int. Conf. on Civil and Building Eng., ASCE, Reston, VA, 287–294.
Michigan Department of Transportation (MDOT). (2009). Project scoping manual, Lansing, MI.
Moder, J. J., Phillips, C. R., and Davis, E. W. (1983). Project management with CPM, PERT and project diagram, Van Nostrand Reinhold, New York.
National Advisory Council on State, and Local Budgeting (NACSLB). (1998). Recommended budget practices: A framework for improved state and local government budgeting, Chicago.
New Jersey Department of Transportation (NJDOT). (2008). “FY 2009 – 2018 Statewide Transportation Improvement Program.” 〈http://www.state.nj.us/transportation/capital/stip0918/〉 (Sep. 7, 2011).
New York State Department of Transportation (NYSDOT). (2009). Capital program proposal: 2010–2015, Albany, NY.
Ohio Department of Transportation (ODOT). (2001). Pavement preventive maintenance program guideline, Columbus, OH.
Ohio Department of Transportation (ODOT). (2006). Pavement condition rating system, Columbus, OH.
Ping, O. G., Nantung, T., and Sinha, K. C. (2010). “Indiana pavement preservation program.”, Joint Transportation Research Program, Indiana Dept. of Transportation and Purdue Univ., West Lafayette, IN.
Savin, D., Alkass, S., and Fazio, P. (1997). “A procedure for calculating the weight-matrix of a neuronal network for resource leveling.” Adv. Eng. Softw., 28(5), 277–283.
Sayers, M. W., and Karamihas, S. M. (1998). The little book of profiling: Basic information about measuring and interpreting road profile, UMTRI, Ann Arbor, MI.
Shah, H. K., Yoon, Y., Hastak, M., and Lee, J. (2011). “Benefits and assessment of annual budget requirements for pavement preservation.”, Joint Transportation Research Program, Indiana Dept. of Transportation and Purdue Univ., West Lafayette, IN.
Takamoto, M., Yamada, N., Kobayashi, Y., Nonaka, H., and Okoshi, S. (1995). “Zero-one quadratic programming algorithm for resource leveling of manufacturing process schedules.” Syst. Comput. Jpn., 26(10), 68–76.
Titus-Glover, L., Fang, C., Alan, M., O’Toole, K., and Darter, M. I. (2010). Pavement health track (PHT), remaining service life (RSL), forecasting models, technical information, FHWA, Washington, D.C.
Woodworth, B. M., and Willie, C. J. (1975). “A heuristic algorithm for resource leveling in multi-project, multi-resource scheduling.” Decis. Sci., 6(3), 525–540.

Information & Authors

Information

Published In

Go to Journal of Infrastructure Systems
Journal of Infrastructure Systems
Volume 20Issue 1March 2014

History

Received: Oct 24, 2011
Accepted: Nov 30, 2012
Published online: Dec 3, 2012
Published in print: Mar 1, 2014
Discussion open until: May 12, 2014

Permissions

Request permissions for this article.

Authors

Affiliations

Yoojung Yoon
Doctoral Candidate and Graduate Research Assistant, Construction Engineering and Management, School of Civil Engineering, Purdue Univ., West Lafayette, IN 47907.
Hiral Shah
Former Master’s Student, Construction Engineering and Management, School of Civil Engineering, Purdue Univ., West Lafayette, IN 47907.
Makarand Hastak3
P.E.
M.ASCE
Jusang Lee
Research Engineer, Office of Research and Development, Indiana Dept. of Transportation, West Lafayette, IN 47906.

Metrics & Citations

Metrics

Citations

Download citation

If you have the appropriate software installed, you can download article citation data to the citation manager of your choice. Simply select your manager software from the list below and click Download.

Cited by

View Options

Get Access

Access content

Please select your options to get access

Log in/Register Log in via your institution (Shibboleth)
ASCE Members: Please log in to see member pricing

Purchase

Save for later Information on ASCE Library Cards
ASCE Library Cards let you download journal articles, proceedings papers, and available book chapters across the entire ASCE Library platform. ASCE Library Cards remain active for 24 months or until all downloads are used. Note: This content will be debited as one download at time of checkout.

Terms of Use: ASCE Library Cards are for individual, personal use only. Reselling, republishing, or forwarding the materials to libraries or reading rooms is prohibited.
ASCE Library Card (5 downloads)
$105.00
Add to cart
ASCE Library Card (20 downloads)
$280.00
Add to cart
Buy Single Article
$35.00
Add to cart

Get Access

Access content

Please select your options to get access

Log in/Register Log in via your institution (Shibboleth)
ASCE Members: Please log in to see member pricing

Purchase

Save for later Information on ASCE Library Cards
ASCE Library Cards let you download journal articles, proceedings papers, and available book chapters across the entire ASCE Library platform. ASCE Library Cards remain active for 24 months or until all downloads are used. Note: This content will be debited as one download at time of checkout.

Terms of Use: ASCE Library Cards are for individual, personal use only. Reselling, republishing, or forwarding the materials to libraries or reading rooms is prohibited.
ASCE Library Card (5 downloads)
$105.00
Add to cart
ASCE Library Card (20 downloads)
$280.00
Add to cart
Buy Single Article
$35.00
Add to cart

Media

Figures

Other

Tables

Share

Share

Copy the content Link

Share with email

Email a colleague

Share