Technical Papers
Aug 26, 2022

New Delay-Analysis Method Using Modified Schedule and Modified Updated Schedule for Construction Projects

Publication: Journal of Construction Engineering and Management
Volume 148, Issue 11

Abstract

Being one of the most common dispute causes in construction projects, the delay is extremely important to be resolved promptly. To resolve delay-related disputes, delay analysis that is conducted to determine the amount of the delay that has occurred on a project together with its contractual responsible party is of paramount importance. Notwithstanding the numerous enhancements in the delay analysis domain, delay resolution remains one of the most challenging issues in construction projects due to various drawbacks of existing delay analysis methods. To minimize the delay-related issues in construction projects, this study, therefore, aims to develop a new delay analysis method that overcomes the drawbacks of existing delay analysis methods. The drawbacks of current methods were initially determined via an in-depth literature review and a focus group discussion (FGD) session conducted with seven experts experienced in the delay analysis domain. This step revealed that most of these methods ignore some critical features, such as consideration of critical path (CP), actual progress data, and fluctuations on CP. Moreover, most of the methods lack detailed numerical procedures and consider only the owner’s delay. Furthermore, some types of activity relationships, actual improvements, and further delays made by contractors on the planned excusable compensable delay (ECD) and excusable noncompensable delay (END) are usually ignored by these methods. Then, a new delay analysis method, namely modified schedule versus modified updated schedule (MSvsMUS), was developed. To overcome the detected drawbacks, the proposed method is designed and developed in a way that can consider various activity relationships among the critical activities, include detailed numerical equations, and compute the variations between the modified schedule (MS) including planned fragnet/s and modified updated schedule (MUS) including actualized fragnet/s periodically. This was then followed by a case study conducted to demonstrate the method’s mechanism. Finally, the developed method was evaluated and validated by conducting a second FDG session and a hypothetical case study. Results demonstrated that MSvsMUS has considerable potential to resolve delays and delay-related disputes escalated in construction projects.

Get full access to this article

View all available purchase options and get full access to this article.

Data Availability Statement

Some or all data, models, or code that support the findings of this study are available from the corresponding author upon reasonable request. Item List: (1) Questions directed to interviewees; and (2) The responses of interviewees.

Acknowledgments

This work was supported by Yildiz Technical University Scientific Research Projects Coordination Unit. Project No.: FDK-2021-4336.

References

Abdelhadi, Y., M. F. Dulaimi, and A. Bajracharya. 2019. “Factors influencing the selection of delay analysis methods in construction projects in UAE.” Int. J. Construct. Manage. 19 (4): 329–340. https://doi.org/10.1080/15623599.2018.1435155.
Abu Hammad, A. A., S. M. A. Ali, G. J. Sweis, and R. J. Sweis. 2010. “Statistical analysis on the cost and duration of public building projects.” J. Manage. Eng. 26 (2): 105–112. https://doi.org/10.1061/(ASCE)0742-597X(2010)26:2(105).
Adhikaril, I., S. Kim, and Y. Lee. 2006. “Selection of appropriate schedule delay analysis method: Analytical hierarchy process (AHP).” In Proc., PICMET 2006, 483–488. New York: IEEE.
Alizadeh, R., J. K. Allen, and F. Mistree. 2020a. “Managing computational complexity using surrogate models: A critical review.” Res. Eng. Des. 31 (3): 275–298. https://doi.org/10.1007/s00163-020-00336-7.
Alizadeh, R., R. Gharizadeh Beiragh, L. Soltanisehat, E. Soltanzadeh, and P. D. Lund. 2020b. “Performance evaluation of complex electricity generation systems: A dynamic network-based data envelopment analysis approach.” Energy Econ. 91 (Sep): 104894. https://doi.org/10.1016/j.eneco.2020.104894.
Alkass, S., M. Mazerolle, and F. Harris. 1996. “Construction delay analysis techniques.” Construct. Manage. Econ. 14 (5): 375–394. https://doi.org/10.1080/014461996373250.
Arcadis. 2021. Global construction disputes report. Amsterdam, Netherlands: Arcadis.
Arditi, D., and T. Pattanakitchamroon. 2006. “Selecting a delay analysis method in resolving construction claims.” Int. J. Project Manage. 24 (2): 145–155. https://doi.org/10.1016/j.ijproman.2005.08.005.
Asim, M., S. Deep, and S. A. Ahmad. 2017. “Time impact study of real estate sector construction projects post application of lean principles for delay resolutions.” Int. J. Civ. Eng. Technol. 8 (2): 89–99.
Bektas, S. 2012. Shortcomings of delay analysis practices: A case study using an integrated approach. Ankara, Turkey: Middle East Technical Univ.
Bektas, S., M. Talat Birgonul, and I. Dikmen. 2021. “Integrated probabilistic delay analysis method to estimate expected outcome of construction delay disputes.” J. Leg. Aff. Dispute Resolut. Eng. Constr. 13 (1): 04520037. https://doi.org/10.1061/(ASCE)LA.1943-4170.0000439.
Bhih, M., and T. Hegazy. 2020. “Improving concurrency assessment and resolving misconceptions about but-for delay analysis technique.” J. Leg. Aff. Dispute Resolut. Eng. Constr. 12 (2): 04520007. https://doi.org/10.1061/(ASCE)LA.1943-4170.0000378.
Bhih, M., and T. Hegazy. 2021a. “Enhanced but-for method to apportion net delays and accelerations.” J. Constr. Eng. Manage. 147 (7): 06021003. https://doi.org/10.1061/(ASCE)CO.1943-7862.0002094.
Bhih, M., and T. Hegazy. 2021b. “Enhanced daily windows delay-analysis technique.” J. Leg. Aff. Dispute Resolut. Eng. Constr. 13 (3): 04521012. https://doi.org/10.1061/(ASCE)LA.1943-4170.0000475.
Bhih, M., and T. Hegazy. 2021c. “Multiple-window modified but-for analysis of project delays and accelerations.” Int. J. Constr. Manage. (Apr): 1–15. https://doi.org/10.1080/15623599.2021.1916708.
Bilgin, G., I. Dikmen, and M. T. Birgonul. 2018. “An ontology-based approach for delay analysis in construction.” KSCE J. Civ. Eng. 22 (2): 384–398. https://doi.org/10.1007/s12205-017-0651-5.
Braimah, N., and I. Ndekugri. 2008. “Factors influencing the selection of delay analysis methodologies.” Int. J. Project Manage. 26 (8): 789–799. https://doi.org/10.1016/j.ijproman.2007.09.001.
Budayan, C., I. Dikmen, and M. T. Birgonul. 2014. “Alignment of project management with business strategy in construction: Evidence from the Turkish contractors.” J. Civ. Eng. Manage. 21 (1): 94–106. https://doi.org/10.3846/13923730.2013.802737.
Budayan, C., O. Okudan, and I. Dikmen. 2020. “Identification and prioritization of stage-level KPIs for BOT projects—Evidence from Turkey.” Int. J. Managing Projects Bus. 13 (6): 1311–1337. https://doi.org/10.1108/IJMPB-11-2019-0286.
Cakmak, E., and P. I. Cakmak. 2014. “An analysis of causes of disputes in the construction industry using analytical network process.” Procedia-Soc. Behav. Sci. 109 (Jan): 183–187. https://doi.org/10.1016/j.sbspro.2013.12.441.
Callahan, M. T., D. G. Quackenbush, and J. E. Rowings. 1992. Construction project scheduling. New York: McGraw-Hill.
Çevikbaş, M., and Z. Işık. 2021. “An overarching review on delay analyses in construction projects.” Buildings 11 (3): 109. https://doi.org/10.3390/buildings11030109.
Çevikbaş, M., and A. Köksal. 2018. “An investigation of litigation process in construction industry in Turkey.” Teknik Dergi 29 (6): 8715–8729.
Chan, I. Y. S., M. Leung, and S. S. W. Yu. 2012. “Managing the stress of Hong Kong expatriate construction professionals in Mainland China: Focus group study exploring individual coping strategies and organizational support.” J. Constr. Eng. Manage. 138 (10): 1150–1160. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000533.
Dainty, A. R. J., M. I. Cheng, and D. R. Moore. 2003. “Redefining performance measures for construction project managers: An empirical evaluation.” Construct. Manage. Econ. 21 (2): 209–218. https://doi.org/10.1080/0144619032000049737.
de la Garza, J. M., A. Prateapusanond, and N. Ambani. 2007. “Preallocation of total float in the application of a critical path method based construction contract.” J. Constr. Eng. Manage. 133 (11): 836–845. https://doi.org/10.1061/(ASCE)0733-9364(2007)133:11(836).
Dikmen, I., A. Qazi, H. Erol, and M. T. Birgonul. 2020. “Meta-modeling of complexity-uncertainty-performance triad in construction projects.” Eng. Manage. J. 33 (1): 1–15. https://doi.org/10.1080/10429247.2020.1772698.
Ekanayake, E. M. K., and B. A. K. S. Perera. 2016. “Appropriate delay analysis techniques to analyse delays in road construction projects in Sri Lanka.” Built Environ. Project Asset Manage. 6 (5): 521–534. https://doi.org/10.1108/BEPAM-08-2015-0039.
Eken, G., G. Bilgin, I. Dikmen, and M. T. Birgonul. 2020. “A lessons-learned tool for organizational learning in construction.” Autom. Constr. 110 (Sep): 102977. https://doi.org/10.1016/j.autcon.2019.102977.
Farrow, T. 2007. “Developments in the analysis of extensions of time.” J. Prof. Issues Eng. Educ. Pract. 133 (3): 218–228. https://doi.org/10.1061/(ASCE)1052-3928(2007)133:3(218).
Gothand, K. D. 2003. “Schedule delay analysis: Modified windows approach.” Cost Eng. 45 (9): 18–23.
Guida, P. L., and G. Sacco. 2019. “A method for project schedule delay analysis.” Comput. Ind. Eng. 128 (Feb): 346–357. https://doi.org/10.1016/j.cie.2018.12.046.
Harris, R. A., and S. Scott. 2001. “UK practice in dealing with claims for delay.” Eng. Constr. Archit. Manage. 8 (5–6): 317–324. https://doi.org/10.1108/eb021192.
Hasan, A., A. Elmualim, R. Rameezdeen, B. Baroudi, and A. Marshall. 2018. “An exploratory study on the impact of mobile ICT on productivity in construction projects.” Built Environ. Project Asset Manage. 8 (3): 320–332. https://doi.org/10.1108/BEPAM-10-2017-0080.
Hashem M. Mehany, M. S., and N. Grigg. 2016. “Delay claims in road construction: Best practices for a standard delay claims management system.” J. Leg. Aff. Dispute Resolut. Eng. Constr. 8 (3): 02516001. https://doi.org/10.1061/(ASCE)LA.1943-4170.0000186.
Hegazy, T., E. Elbeltagi, and K. Zhang. 2005. “Keeping better site records using intelligent bar charts.” J. Constr. Eng. Manage. 131 (5): 513–521. https://doi.org/10.1061/(ASCE)0733-9364(2005)131:5(513).
Hegazy, T., and W. Menesi. 2008. “Delay analysis under multiple baseline updates.” J. Constr. Eng. Manage. 134 (8): 575–582. https://doi.org/10.1061/(ASCE)0733-9364(2008)134:8(575).
Hegazy, T., and K. Zhang. 2005. “Daily windows delay analysis.” J. Constr. Eng. Manage. 131 (5): 505–512. https://doi.org/10.1061/(ASCE)0733-9364(2005)131:5(505).
Ibbs, W., L. D. Nguyen, and L. Simonian. 2011. “Concurrent delays and apportionment of damages.” J. Constr. Eng. Manage. 137 (2): 119–126. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000259.
Jia, L., R. Alizadeh, J. Hao, G. Wang, J. K. Allen, and F. Mistree. 2020. “A rule-based method for automated surrogate model selection.” Adv. Eng. Inf. 45 (Aug): 101123. https://doi.org/10.1016/j.aei.2020.101123.
Kao, C. K., and B. J. Yang. 2009. “Comparison of windows-based delay analysis methods.” Int. J. Project Manage. 27 (4): 408–418. https://doi.org/10.1016/j.ijproman.2008.05.016.
Kim, Y., K. Kim, and D. Shin. 2005. “Delay analysis method using delay section.” J. Constr. Eng. Manage. 131 (11): 1155–1164. https://doi.org/10.1061/(ASCE)0733-9364(2005)131:11(1155).
Koulinas, G. K., A. S. Xanthopoulos, T. T. Tsilipiras, and D. E. Koulouriotis. 2020. “Schedule delay risk analysis in construction projects with a simulation-based expert system.” Buildings 10 (8): 134. https://doi.org/10.3390/buildings10080134.
Lee, J.-S. 2007. “Delay analysis using linear schedule in construction.” AACE Int. Trans. 404: 1–6.
Maidi, M. N. 2020. Lean construction and delay analysis input in delay mitigation. Berlin: HTW Berlin.
Marey, M., N. Amer, A. E. Amer, M. E. M. Marey, and A. Ehab. 2020. “Analysis of delay causes using BIM.” EasyChair. Accessed December 25, 2020. https://easychair.org/publications/preprint_open/C5HW.
Marques, R. C. 2018. “Is arbitration the right way to settle conflicts in PPP arrangements?” J. Manage. Eng. 34 (1): 05017007. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000564.
Mbabazi, A., T. Hegazy, and F. Saccomanno. 2005. “Modified but-for method for delay analysis.” J. Constr. Eng. Manage. 131 (10): 1142–1144. https://doi.org/10.1061/(ASCE)0733-9364(2005)131:10(1142).
McGeehin, P. A., and J. I. Spangler III. 2021. “Coronavirus delay and disruption claims.” Constr. Lawyer 41 (2): 18–25.
Mills, A. 2001. “A systematic approach to risk management for construction.” Struct. Surv. 19 (5): 245–252. https://doi.org/10.1108/02630800110412615.
Munvar, C., D. G. Mengistu, and G. Mahesh. 2020. “Concurrent delay analysis: Methods, case law, and expert perception.” J. Leg. Aff. Dispute Resolut. Eng. Constr. 12 (1): 04519035. https://doi.org/10.1061/(ASCE)LA.1943-4170.0000343.
Ndekugri, I., N. Braimah, and R. Gameson. 2008. “Delay analysis within construction contracting organizations.” J. Constr. Eng. Manage. 134 (9): 692–700. https://doi.org/10.1061/(ASCE)0733-9364(2008)134:9(692).
Ng, S. T., M. Skitmore, M. Z. M. Deng, and A. Nadeem. 2004. “Improving existing delay analysis techniques for the establishment of delay liabilities.” Constr. Innovation 4 (1): 3–17. https://doi.org/10.1108/14714170410814971.
Nguyen, L. D., and W. Ibbs. 2008. “FLORA: New forensic schedule analysis technique.” J. Constr. Eng. Manage. 134 (7): 483–491. https://doi.org/10.1061/(ASCE)0733-9364(2008)134:7(483).
Nyumba, T. O., K. Wilson, C. J. Derrick, and N. Mukherjee. 2018. “The use of focus group discussion methodology: Insights from two decades of application in conservation.” Methods Ecol. Evol. 9 (1): 20–32. https://doi.org/10.1111/2041-210X.12860.
Okudan, O., C. Budayan, and I. Dikmen. 2021. “A knowledge-based risk management tool for construction projects using case-based reasoning.” Expert Syst. Appl. 173 (Jul): 114776. https://doi.org/10.1016/j.eswa.2021.114776.
Onofrio, M. F. D., and K. P. Hoshino. 2010. “AACE recommended practice for forensic schedule analysis.” In Proc., 2010 Annual Meeting The Age of Turbulence: Managing Money Issues in Construction. Austin, TX: Hilton Austin.
Perera, N., and M. Sutrisna. 2010. “The use of analytic hierarchy process (AHP) in the analysis of delay claims in construction projects in the UAE.” Built Hum. Environ. Rev. 3 (1): 29–48.
Rooholelm, V., and A. Sheikh Aboumasoudi. 2020a. “Designing pattern for project delay analysis with several periods extension of time, continuous and discrete (Pr-to-Pr).” Comput. Ind. Eng. 146 (Aug): 106576. https://doi.org/10.1016/j.cie.2020.106576.
Rooholelm, V., and A. Sheikh Aboumasoudi. 2020b. “Share determination of stakeholder delays, based on targeted delay analysis of projects, with incursive and defensive (In-De) approach.” Int. J. Managing Projects Bus. 13 (6): 1219–1261. https://doi.org/10.1108/IJMPB-08-2019-0196.
Sakka, Z. I., and S. M. El-Sayegh. 2007. “Float consumption impact on cost and schedule in the construction industry.” J. Constr. Eng. Manage. 133 (2): 124–130. https://doi.org/10.1061/(ASCE)0733-9364(2007)133:2(124).
Salim, W. N., and C. M. Sujana. 2020. “Project delay analysis of highrise building project in Jakarta.” IOP Conf. Ser.: Earth Environ. Sci. 426 (1): 012051. https://doi.org/10.1088/1755-1315/426/1/012051.
Sambasivan, M., T. J. Deepak, A. N. Salim, and V. Ponniah. 2017. “Analysis of delays in Tanzanian construction industry transaction cost economics (TCE) and structural equation modeling (SEM) approach.” Eng. Constr. Archit. Manage. 24 (2): 308–325. https://doi.org/10.1108/ECAM-09-2015-0145.
SCW (Society of Construction Law). 2017. The society of construction law delay and disruption protocol. Leicestershire, UK: SCW.
Stumpf, G. R. 2000. “Schedule delay analysis.” Cost Eng. (Morgantown, West Virginia) 42 (7): 32–43.
Sweet, J. 1977. Legal aspects of architecture, engineering and the construction process. St. Paul, MN: West Publishing.
Tardif, L. M. 1988. “Delay analysis using the ‘snapshot’ technique.” PMI Network 2 (4): 17–36.
Trauner, T. J., W. A. Manginelli, J. S. Lowe, M. F. Nagata, and B. J. Furniss. 2009. “Types of construction delays.” In Construction delays, 25–36. Amsterdam, Netherlands: Elsevier.
Türkakın, O. H., E. Manisalı, and D. Arditi. 2020. “Delay analysis in construction projects with no updated work schedules.” Eng. Constr. Archit. Manage. 27 (10): 2893–2909. https://doi.org/10.1108/ECAM-09-2019-0470.
Udeaja, C. E., J. M. Kamara, P. M. Carrillo, C. J. Anumba, N. Bouchlaghem, and H. C. Tan. 2008. “A web-based prototype for live capture and reuse of construction project knowledge.” Autom. Constr. 17 (7): 839–851. https://doi.org/10.1016/j.autcon.2008.02.009.
Vasilyeva-lyulina, A., M. Onishi, and K. Kobayashi. 2015. “Delay analysis methods for construction projects: Mathematical modeling.” Int. J. Transp. 3 (1): 27–36. https://doi.org/10.14257/ijt.2015.3.1.03.
Yang, J. B., and C. K. Kao. 2012. “Critical path effect based delay analysis method for construction projects.” Int. J. Project Manage. 30 (3): 385–397. https://doi.org/10.1016/j.ijproman.2011.06.003.
Yang, J. B., and Y. L. Teng. 2017. “Theoretical development of stochastic delay analysis and forecast method.” J. Chin. Inst. Eng. 40 (5): 391–400. https://doi.org/10.1080/02533839.2017.1336115.
Yang, J. B., and M. K. Tsai. 2011. “Computerizing ICBF method for schedule delay analysis.” J. Constr. Eng. Manage. 137 (8): 583–591. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000338.
Yang, J.-B., and P.-C. Yin. 2009. “Isolated collapsed but-for delay analysis methodology.” J. Constr. Eng. Manage. 135 (7): 570–578. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000016.
Yousefi, E. 2017. “An integrated expert model for delay management in construction projects.” J. Constr. Eng. Project Manage. 7 (3): 1–14. https://doi.org/10.6106/JCEPM.2017.9.29.001.
Zarei, B., H. Sharifi, and Y. Chaghouee. 2018. “Delay causes analysis in complex construction projects: A semantic network analysis approach.” Prod. Plann. Control 29 (1): 29–40. https://doi.org/10.1080/09537287.2017.1376257.

Information & Authors

Information

Published In

Go to Journal of Construction Engineering and Management
Journal of Construction Engineering and Management
Volume 148Issue 11November 2022

History

Received: Dec 23, 2021
Accepted: Jun 17, 2022
Published online: Aug 26, 2022
Published in print: Nov 1, 2022
Discussion open until: Jan 26, 2023

Permissions

Request permissions for this article.

ASCE Technical Topics:

Authors

Affiliations

Murat Çevikbaş [email protected]
Research Assistant, Dept. of Civil Engineering, Faculty of Technology, Isparta Univ. of Applied Sciences, Isparta 32200, Turkey. Email: [email protected]
Research Assistant, Dept. of Civil Engineering, Yildiz Technical Univ., Davutpaşa Caddesi, Istanbul 34220, Turkey. ORCID: https://orcid.org/0000-0001-7816-2761. Email: [email protected]
Associate Professor, Dept. of Civil Engineering, Yildiz Technical Univ., Davutpaşa Caddesi, Istanbul 34220, Turkey (corresponding author). ORCID: https://orcid.org/0000-0002-7849-8633. Email: [email protected]

Metrics & Citations

Metrics

Citations

Download citation

If you have the appropriate software installed, you can download article citation data to the citation manager of your choice. Simply select your manager software from the list below and click Download.

Cited by

  • Identification of Dispute Sources in the Construction Industry via Court Files, Turkish Journal of Civil Engineering, 10.18400/tjce.1224425, (2023).

View Options

Get Access

Access content

Please select your options to get access

Log in/Register Log in via your institution (Shibboleth)
ASCE Members: Please log in to see member pricing

Purchase

Save for later Information on ASCE Library Cards
ASCE Library Cards let you download journal articles, proceedings papers, and available book chapters across the entire ASCE Library platform. ASCE Library Cards remain active for 24 months or until all downloads are used. Note: This content will be debited as one download at time of checkout.

Terms of Use: ASCE Library Cards are for individual, personal use only. Reselling, republishing, or forwarding the materials to libraries or reading rooms is prohibited.
ASCE Library Card (5 downloads)
$105.00
Add to cart
ASCE Library Card (20 downloads)
$280.00
Add to cart
Buy Single Article
$35.00
Add to cart

Get Access

Access content

Please select your options to get access

Log in/Register Log in via your institution (Shibboleth)
ASCE Members: Please log in to see member pricing

Purchase

Save for later Information on ASCE Library Cards
ASCE Library Cards let you download journal articles, proceedings papers, and available book chapters across the entire ASCE Library platform. ASCE Library Cards remain active for 24 months or until all downloads are used. Note: This content will be debited as one download at time of checkout.

Terms of Use: ASCE Library Cards are for individual, personal use only. Reselling, republishing, or forwarding the materials to libraries or reading rooms is prohibited.
ASCE Library Card (5 downloads)
$105.00
Add to cart
ASCE Library Card (20 downloads)
$280.00
Add to cart
Buy Single Article
$35.00
Add to cart

Media

Figures

Other

Tables

Share

Share

Copy the content Link

Share with email

Email a colleague

Share