Prefabricated Construction Process Optimization Based on Rework Risk
Publication: Journal of Construction Engineering and Management
Volume 148, Issue 6
Abstract
In prefabricated construction (PC) projects, component manufacturing and site construction are implemented concurrently to improve productivity. However, concurrent PC provides feedback information on each task, and iterations and coupling tasks often exist, which causes rework at a certain probability. Therefore, it is necessary to identify and optimize coupling tasks to reduce feedback information and rework costs and time. In this paper, a PC process optimization model that includes two modules is constructed. The first module is a coupling task optimization module and is built using the design structure matrix (DSM) method with graph theory to identify and reduce coupling tasks. Then a rework risk impact optimization module is built with cost and time minimization as objectives based on a genetic algorithm (GA) according to risk communication, rework probability, and core tasks. A case study is used to verify the model and reveals an 82.24% reduction of the impacts of rework risk on costs and time. The coupling tasks that are optimized as task groups require that the corresponding stakeholders be coordinated. Core tasks should be carried out in advance to avoid greater impacts in later periods. The model extends existing process optimization methods and has value for planning and controlling PC management to enhance coordination among all stakeholders. This study provides a reference for future research on rework risk prediction.
Get full access to this article
View all available purchase options and get full access to this article.
Data Availability Statement
All data, models, and code generated or used during the study appear in the published article.
Acknowledgments
This work was supported by the National Natural Science Foundation of China (Nos. 51778335 and 51868016). The authors would also like to thank all experts interviewed for their assistance in data collection.
References
Amalin Prince, A., I. Jose, and P. Agrawal. 2012. “Concurrent design, modeling and analysis of microelectromechanical systems products—Design for ‘X’ abilities.” Micro Nanosyst. 4 (1): 56–74. https://doi.org/10.2174/1876402911204010056.
An, H. C., S. Y. Chen, and H. Huang. 2019. “Concurrent optimization of stacking sequence and stiffener layout of a composite stiffened panel.” Eng. Optim. 51 (4): 608–626. https://doi.org/10.1080/0305215X.2018.1492570.
Araújo, K., M. Andrade, R. Lima, and C. Oliveira. 2020. “Performance analysis of metropolitan bus rapid transit line via generalized stochastic petri nets.” J. Urban Plann. Dev. 146 (1): 05019019. https://doi.org/10.1061/(ASCE)UP.1943-5444.0000543.
Ashford, J. L. 1992. The management of quality in construction. London: E&F Spon.
Bourne, L. M., and P. Weaver. 2018. “The origins of schedule management: The concepts used in planning, allocating, visualizing and managing time in a project.” Front. Eng. Manage. 5 (2): 150–166. https://doi.org/10.15302/J-FEM-2018012.
Cao, X. Y., Z. D. Li, Y. M. Zhu, and Z. H. Zhang. 2015a. “A comparative study of environmental performance between prefabricated and traditional residential buildings in China.” J. Cleaner Prod. 109 (Dec): 131–143. https://doi.org/10.1016/j.jclepro.2015.04.120.
Cao, X. Y., Z. F. Li, and S. Liu. 2015b. “Study on factors that inhibit the promotion of SI housing system in China.” Energy Build. 88 (Feb): 384–394. https://doi.org/10.1016/j.enbuild.2014.11.064.
Cheng, F. F. 2009. “Research on building product design process modelling and simulation.” Doctoral thesis, Harbin Institute of Technology.
Eppinger, S. D., and T. R. Browning. 2012. Design structure matrix methods and applications. Cambridge, MA: MIT Press.
Forcada, N., M. Gangolells, and M. Casals. 2017. “Factors affecting rework costs in construction.” J. Constr. Eng. Manage. 20 (4): 445–465. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001324.
Fu, Y., M. Q. Li, and F. Z. Chen. 2012. “Impact propagation and risk assessment of requirement changes for software development projects based on design structure matrix.” Int. J. Project Manage. 30 (3): 363–373. https://doi.org/10.1016/j.ijproman.2011.08.004.
Goorden, M., J. V. Mortel-Fronczak, and M. Reniers. 2020. “Structuring multilevel discrete-event systems with dependence structure matrices.” IEEE Trans. Autom. Control 65 (4): 1625–1639. https://doi.org/10.1109/TAC.2019.2928119.
Han, R. F. 2009. Principle and application of genetic algorithms. Beijing: Weapon Industry Press.
Hyun, H., H. Kim, and H. Lee. 2020. “Integrated design process for modular construction projects to reduce rework.” Sustainability 12 (2): 530. https://doi.org/10.3390/su12020530.
Hyun, H., H. Lee, and J. Lee. 2019. “Design and planning process management for reducing rework in modular construction using dependency structure matrix (DSM).” J. Archit. Inst. Korea Struct. Constr. 35 (2): 29–36. https://doi.org/10.5659/JAIK_SC.2019.35.2.29.
ISO9000. 2016. Fundamentals and terminology of quality management system. Beijing: General Administration of Quality Supervision.
Jeong, K. Y., L. Wu, and J. D. Hong. 2009. “IDEF method-based simulation model design and development framework.” J. Indus. Eng. Manage. 2 (2): 337–359. https://doi.org/10.3926/jiem.2009.v2n2.p337-359.
Josephson, P. E., B. Larsson, and H. Li. 2002. “Illustrative benchmarking rework and rework costs in Swedish construction industry.” J. Manage. Eng. 18 (2): 76–83. https://doi.org/10.1061/(ASCE)0742-597X(2002)18:2(76).
Kim, K., J. Walewski, and Y. K. Cho. 2016. “Multiobjective construction schedule optimization using modified Niched Pareto genetic algorithm.” J. Manage. Eng. 32 (2): 04015038. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000374.
Lee, J., M. Park, and H. S. Lee. 2017. “Workflow dependency approach for modular building construction manufacturing process using dependency structure matrix (DSM).” J. Civ. Eng. 21 (5): 1525–1535. https://doi.org/10.1007/s12205-016-1085-1.
Li, W. L., and Y. B. Moon. 2012. “Modeling and managing engineering changes in a complex product development process.” Int. J. Adv. Manuf. Technol. 63 (9): 863–874. https://doi.org/10.1007/s00170-012-3974-x.
Li, X. D. 2018. “Research on the planning and control for construction process of the industrialised building.” Doctoral thesis, Dept. of Construction Management, Dalian Univ. of Technology.
Liu, J., Y. S. Liu, and Y. Shi. 2020. “Solving resource-constrained project scheduling problem via genetic algorithm.” J. Comput. Civ. Eng. 34 (2): 04019055. https://doi.org/10.1061/(ASCE)CP.1943-5487.0000874.
Liu, L. X. 2014. Risk management. 2nd ed. Beijing: Peking University Press.
Liu, T. L. 2016. “Research of prefabricated construction enterprise supply chain risk management.” Master’s thesis, Dept. of Industrial Engineering, Chongqing Univ.
Love, P. 2002. “Influence of project type and procurement method on rework costs in building construction projects.” J. Constr. Eng. Manage. 128 (1): 18–29. https://doi.org/10.1061/(ASCE)0733-9364(2002)128:1(18).
Love, P., and H. Li. 2000. “Quantifying the causes and costs of rework in construction.” Construct. Manage. Econ. 18 (4): 479–490. https://doi.org/10.1080/01446190050024897.
Maghsoudlou, H., B. Afshar-Nadjafi, and S. T. Akhavan Niaki. 2017. “Multi-skilled project scheduling with level-dependent rework risk; three multi-objective mechanisms based on cuckoo search.” Appl. Soft Comput. 54 (May): 46–61. https://doi.org/10.1016/j.asoc.2017.01.024.
Maheswari, J. U., and K. Varghese. 2005. “Project scheduling using dependency structure matrix.” Int. J. Project Manage. 23 (3): 223–230. https://doi.org/10.1016/j.ijproman.2004.10.001.
Mazahery, A., and M. O. Shabani. 2012. “Assistance of novel artificial intelligence in optimization of aluminum matrix nanocomposite by genetic algorithm.” Metall. Mater. Trans. A 43 (13): 5279–5285. https://doi.org/10.1007/s11661-012-1339-6.
Mei, Z., Z. X. Guo, L. C. Chen, H. F. Wang, and Y. C. Gao. 2020. “Genetic algorithm-based integrated optimization of active control systems for civil structures subjected to random seismic excitations.” Eng. Optim. 52 (10): 1700–1719. https://doi.org/10.1080/0305215X.2019.1677632.
Nasirian, A., M. Arashpour, and B. Abbasi. 2019. “Optimal work assignment to multiskilled resources in prefabricated construction.” J. Constr. Eng. Manage. 145 (4): 04019011. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001627.
Osorio-Sandoval, C. A., W. Tizani, E. Pereira, and C. Koch. 2021. “Discrete-event simulation and building information modelling based animation of construction activities.” In Vol. 98 of Proc., 18th Int. Conf. on Computing in Civil and Building Engineering, ICCCBE 2020, edited by E. Toledo Santos and S. Scheer. Cham, Switzerland: Springer. https://doi.org/10.1007/978-3-030-51295-8_21.
Safapour, E., and S. Kermanshachi. 2019. “Identifying early indicators of manageable rework causes and selecting mitigating best practices for construction.” J. Manage. Eng. 35 (2): 04018060. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000669.
Satish, K. V., and N. J. Kumar. 2020. “Critical risk factors in international construction projects: An Indian perspective.” Eng. Constr. Archit. Manage. 27 (5): 1169–1190. https://doi.org/10.1108/ECAM-04-2019-0220.
Sharman, D. M., and A. A. Yassine. 2004. “Characterizing complex product architectures.” Syst. Eng. 7 (1): 35–60. https://doi.org/10.1002/sys.10056.
Shen, K. C., C. Cheng, X. D. Li, and Z. H. Zhang. 2019. “Environmental cost-benefit analysis of prefabricated public housing in Beijing.” Sustainability 11 (1): 207. https://doi.org/10.3390/su11010207.
Shen, K. C., X. D. Li, X. Y. Cao, and Z. H. Zhang. 2020. “Research on a management system for rework risk in prefabricated construction process.” [In Chinese.] J. Eng. Manage. 34 (6): 101–106. https://doi.org/10.13991/j.cnki.jem.2020.06.018.
Shen, K. C., X. D. Li, X. Y. Cao, and Z. H. Zhang. 2021. “Research on the rework risk core tasks in prefabricated construction in China.” Eng. Constr. Archit. Manage. 28 (10): 3299–3321. https://doi.org/10.1108/ECAM-07-2020-0521.
Simpeh, E. K., R. Ndihokubwayo, P. E. Love, and W. D. Thwala. 2015. “A rework probability model: A quantitative assessment of rework occurrence in construction projects.” Int. J. Constr. Manage. 15 (2): 109–116. https://doi.org/10.1080/15623599.2015.1033814.
Suh, N. P. 1997. “Design of systems.” Ann. CIRP 46 (1): 75–80. https://doi.org/10.1016/S0007-8506(07)60779-3.
Tang, D. B., X. M. Qian, and J. G. Liu. 2009. Product design and development based on DSM. Beijing: Science Press.
Unger, D., and S. Eppinger. 2011. “Improving product development process design: A method for managing information flows, risks, and iterations.” J. Eng. Des. 22 (10): 689–699. https://doi.org/10.1080/09544828.2010.524886.
Wang, Z. F. 2007. Project risk management: Theory, method and application. Beijing: China Water & Power Press.
Wang, Z. J., H. Hu, and J. Gong. 2018. “Modeling worker competence to advance precast production scheduling optimization.” J. Constr. Eng. Manage. 144 (11): 04018098. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001556.
Wu, H., W. Hsiao, C. Lin, and T. Cheng. 2011. “Application of genetic algorithm to the development of artificial intelligence module system.” In Proc., 2nd Int. Conf. on Intelligent Control and Information Processing, 290–294. New York: IEEE. https://doi.org/10.1109/ICICIP.2011.6008251.
Yang, Q., Z. L. Liu, and C. Shan. 2017. “The impact analysis and optimization of communication on rework risk between overlapped activities in R&D projects.” [In Chinese.] Syst. Eng. Theory Pract. 37 (9): 2384–2393. https://doi.org/10.12011/1000-6788(2017)09-2384-10.
Yang, Q., T. Lu, T. Yao, and Z. Bo. 2014. “The impact of uncertainty and ambiguity related to iteration and overlapping on schedule of product development projects.” Int. J. Project Manage. 32 (5): 827–837. https://doi.org/10.1016/j.ijproman.2013.10.010.
Yang, Q., C. Shan, and E. L. Tang. 2015. “Optimization of design structure matrix in complex R&D projects based on rework risk propagation and pretreatment.” [In Chinese.] Syst. Eng. Theory Pract. 35 (6): 1501–1508.
Yu, B. G. 2010. “Research on modeling and managing of complex product development process.” Doctoral thesis, Dept. of Information Management, Hefei Univ. of Technology.
Zhang, H., W. Qiu, and H. Zhang. 2006. “An approach to measuring coupled tasks strength and sequencing of coupled tasks in new product development.” Concurrent Eng. 14 (4): 305–311. https://doi.org/10.1177/1063293X06072483.
Zhang, X. L., M. Skitmore, and Y. Peng. 2014. “Exploring the challenges to industrialized residential building in China.” Habitat Int. 41 (Jan): 176–184. https://doi.org/10.1016/j.habitatint.2013.08.005.
Zhang, Y. X., I. Flood, Q. Yang, and C. J. Kibert. 2016. “Using genetic algorithm-based dependency structure matrix for prefabrication design management.” [In Chinese.] ICCCBE 2016 (1): 1211–1218.
Information & Authors
Information
Published In
Copyright
© 2022 American Society of Civil Engineers.
History
Received: Jun 10, 2021
Accepted: Jan 18, 2022
Published online: Mar 29, 2022
Published in print: Jun 1, 2022
Discussion open until: Aug 29, 2022
Authors
Metrics & Citations
Metrics
Citations
Download citation
If you have the appropriate software installed, you can download article citation data to the citation manager of your choice. Simply select your manager software from the list below and click Download.
Cited by
- Zhen Lei, Qian Chen, Mohammed Sadiq Altaf, Ke Cao, Defining Information Requirements for Off-Site Construction Management: An Industry Case Study from Canada, Journal of Construction Engineering and Management, 10.1061/JCEMD4.COENG-15141, 150, 12, (2024).
- Helamini Sandagomika, Ankit Shringi, Saeed Reza Mohandes, Ahmed Farouk Kineber, Milad Bazli, Mehrdad Arashpour, Mixed Reality-Based Approach for Minimizing Time Uncertainty in Prefabrication, Journal of Construction Engineering and Management, 10.1061/JCEMD4.COENG-14846, 150, 11, (2024).
- Rehan Masood, Krishanu Roy, Vicente A. Gonzalez, James B. P. Lim, Ameliorating Supply Chains of Prefabricated Housebuilding: An Integrated Performance Framework, Journal of Construction Engineering and Management, 10.1061/JCEMD4.COENG-14404, 150, 6, (2024).
- Jaemin Jeong, Jaewook Jeong, Sustainability in Prefabricated Construction: Enhancing Multicriteria Analysis and Prediction Using Machine Learning, Journal of Construction Engineering and Management, 10.1061/JCEMD4.COENG-14227, 150, 8, (2024).
- Samira Rizaee, Zhen Lei, Duration Estimation of a Heavy Industrial Scaffolding Project: A Case Study, Journal of Construction Engineering and Management, 10.1061/JCEMD4.COENG-13915, 150, 4, (2024).
- Kaicheng Shen, Yimin Zhu, Jianchao Pan, Xiaodong Li, An Intelligent Decision-Making Model for the Design of Precast Slab Joints Based on Case-Based Reasoning, Journal of Construction Engineering and Management, 10.1061/JCEMD4.COENG-13032, 149, 5, (2023).
- Liuya Huang, Hang Yan, Xianqing Chen, Assessment of Rework Risk in the Construction Process of Prefabricated Buildings Based on BWM-GRA Method, ICCREM 2023, 10.1061/9780784485217.103, (1041-1050), (2023).
- Ting Wang, Jingchun Feng, Optimal Review Strategy for Concurrent Execution of Design–Construction Tasks in DB Mode, Journal of Construction Engineering and Management, 10.1061/(ASCE)CO.1943-7862.0002408, 149, 1, (2023).
- Yinghui Song, Junwu Wang, Jiequn Lu, Xiang Si, Research on collaborative scheduling of multiple projects of prefabricated building based on the niche genetic-raccoon family optimization algorithm, Alexandria Engineering Journal, 10.1016/j.aej.2022.08.054, 64, (1015-1033), (2023).
- Tianxin Li, Zhongfu Li, Long Li, Peng Jiang, Exploring the Knowledge Domain of Risk Management in Prefabricated Construction, Buildings, 10.3390/buildings12111784, 12, 11, (1784), (2022).
- See more