Cost Impacts of Change Orders due to Unforeseen Existing Conditions in Building Renovation Projects
Publication: Journal of Construction Engineering and Management
Volume 146, Issue 8
Abstract
A renovation project generally requires time, money, or costly equipment to examine the existing conditions of a structure. When unforeseen existing conditions are not properly examined, unexpected costs and/or schedule impacts can adversely affect the successful completion of a renovation project. This paper examines whether the cost impact of change orders due to unforeseen existing conditions is significant compared with the cost impacts of all other change orders, and quantifies the impact on the total project costs and the construction trade. Statistical analyses such as -test and ANOVA were conducted, using information on 517 change orders obtained from 27 building renovation projects. The results show that change orders due to unforeseen existing conditions have significant impacts compared with change orders caused by other reasons, and that the calculated mean cost is higher for change orders stemming from unforeseen existing conditions. The results also show that the concrete trade is most impacted by change orders from unforeseen existing conditions, while the trade with the highest cost impact is heating, ventilating, and air conditioning. This paper investigates the effect of unforeseen existing conditions on the costs associated with change orders. The paper also identifies those construction trades that are more impacted than others and, therefore, require special attention. This knowledge is essential for identifying areas of possible cost overruns and minimizing overruns in building renovation projects.
Get full access to this article
View all available purchase options and get full access to this article.
Data Availability Statement
Some or all data, models, or code generated or used during the study are available from the corresponding author by request. The items include the change order data and statistical analysis outputs.
Acknowledgments
The writers thank three anonymous reviewers for their critical and helpful comments and suggestions that improved the quality of this paper.
References
Abdul-Rahman, H., C. Wang, and J. B. H. Yap. 2015. “Impacts of design changes on construction project performance: Insights from a literature review.” In Proc., 14th Management in Construction Researchers’ Association (MiCRA 2015) Annual Conf. and General Meeting. Kuala Lumpur, Malaysia: International Islamic Univ. Malaysia.
Alnuaimi, A. S., R. A. Taha, M. A. Mohsin, and A. S. Al-Harthi. 2010. “Causes, effects, benefits, and remedies of change orders on public construction projects in Oman.” J. Constr. Eng. Manage. 136 (5): 615–622. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000154.
Anastasopoulos, P. C., S. Labi, A. Bhargava, C. Bordat, and F. L. Mannering. 2010. “Frequency of change orders in highway construction using alternate count-data modeling methods.” J. Constr. Eng. Manage. 136 (8): 886–893. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000198.
Baccarini, D. 1999. “The logical framework method for defining project success.” Project Manage. J. 30 (4): 25–32. https://doi.org/10.1177/875697289903000405.
Bordat, C., B. G. McCullouch, S. Labi, and K. C. Sinha. 2004. An analysis of cost overruns and time delays of INDOT projects. West Lafayette, Indiana: Joint Transportation Research Program, Indiana Department of Transportation and Purdue University.
Cattano, C. 2010. “Identifying barriers to address during the delivery of sustainable building renovation projects.” M.S. thesis, Dept. of Civil Engineering, Clemson Univ.
Civitello, A. M. 2002. Contractor’s guide to change orders. Cincinnati: BNI Publications.
CSI (Construction Specification Institute). 2016. “MasterFormat.” Accessed July 10, 2019. https://www.csiresources.org/standards/masterformat.
Finke, M. R. 1998. “A better way to estimate and mitigate disruption.” J. Constr. Eng. Manage. 124 (6): 490–497. https://doi.org/10.1061/(ASCE)0733-9364(1998)124:6(490).
Gibson, G. E., Q. Cui, S. Howard, and K. T. Irons. 2010. “Front end planning for renovation projects.” In Proc., Construction Research Conf. Reston, VA: ASCE. https://doi.org/10.1061/41109(373)113.
Gokulkarthi, M., and K. S. Gowrishankar. 2015. “A study on impacts of change orders in construction projects.” Int. J. Sci. Eng. Res. 3 (4): 3221.
Hanna, A. S., R. Camlic, P. A. Peterson, and E. V. Nordheim. 2002. “Quantitative definition of projects impacted by change orders.” J. Constr. Eng. Manage. 128 (1). https://doi.org/10.1061/(ASCE)0733-9364(2002)128:1(57).
Hanna, A. S., and K. A. Iskandar. 2017. “Quantifying and modeling the cumulative impact of change orders.” J. Constr. Eng. Manage. 143 (10): 04017076. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001385.
Hanna, A. S., and J. Swanson. 2007. “Risk allocation by law—Cumulative impact of change orders.” J. Prof. Issues Eng. Educ. Pract. 133 (1): 60–66. https://doi.org/10.1061/(ASCE)1052-3928(2007)133:1(60).
Hao, Q., W. Shen, J. Neelamkavil, and R. Thomas. 2008. “Change management in construction projects.” In Proc., CIB W78 2008 Int. Conf. on Information Technology in Construction. Santiago, Chile: Universidad de Talca.
Hsieh, T. Y., S. T. Lu, and C. H. Wu. 2004. “Statistical analysis of causes for change orders in metropolitan public works.” Int. J. Project Manage. 22 (8): 679–686. https://doi.org/10.1016/j.ijproman.2004.03.005.
Hwang, B.-G., and L. K. Low. 2012. “Construction project change management in Singapore: Status, importance and impact.” Int. J. Project Manage. 30 (7): 817–826. https://doi.org/10.1016/j.ijproman.2011.11.001.
Isaac, S., and R. Navon. 2008. “Feasibility study of an automated tool for identifying the implications of changes in construction projects.” J. Constr. Eng. Manage. 134 (2): 139–145. https://doi.org/10.1061/(ASCE)0733-9364(2008)134:2(139).
Khanzadi, M., F. Nasirzadeh, and M. S. Dashti. 2018. “Fuzzy cognitive map approach to analyze causes of change orders in construction projects.” J. Constr. Eng. Manage. 144 (2): 04017111. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001430.
Kolsoff, K. 2019. “Unforeseen conditions and hidden costs of construction projects. Educational Community for Homeowners.” Accessed February 15, 2019. https://www.echo-ca.org/article/unforeseen-conditions-and-hidden-costs-construction-projects.
Levine, D. M. 2001. Applied statistics for engineers and scientists. Upper Saddle River, NJ: Prentice Hall.
McGraw-Hill Construction. 2009. Green building retrofit and renovation. Bedford, MA: McGraw-Hill Construction.
McKim, R., T. Hegazy, and M. Attalla. 2000. “Project performance control in reconstruction projects.” J. Constr. Eng. Manage. 126 (2): 137–141. https://doi.org/10.1061/(ASCE)0733-9364(2000)126:2(137).
Mitropoulos, P., and G. A. Howell. 2002. “Renovation projects: Design process problems and improvement mechanisms.” J. Manage. Eng. 18 (4): 179–185. https://doi.org/10.1061/(ASCE)0742-597X(2002)18:4(179).
Moselhi, O., C. Leonard, and P. Fazio. 1991. “Impact of change orders on construction productivity.” Can. J. Civ. Eng. 18 (3): 484–492. https://doi.org/10.1139/l91-059.
Nourse, J. 2017. “How to minimize change orders on your commercial construction project.” Accessed December 15, 2019. http://manourse.com/how-to-minimize-change-orders-on-your-commercial-construction-project/.
O’Brien, J. J. 1998. Construction change orders: Impact, avoidance, documentation. New York: McGraw-Hill.
Olsen, D., R. Killingsworth, and P. Brandon. 2012. “Change order causation: Who is the guilty part?” In Vol. 1 of Proc., 48th ASC Annual Int. Conf., 1–9. Windsor, CO: Associated Schools of Construction. http://ascpro.ascweb.org/chair/paper/CPGT166002012.pdf.
PMI (Project Management Institute). 2013. A guide to the project management body of knowledge (PMBOK). Newtown Square, PA: PMI.
Ramons-Maldonado, D., A. Gonzales-Quevedo, and O. Molina-Bas. 2016. “Study of change orders in design-build-maintain projects of the XXI Century Schools in Puerto Rico.” In Proc., Construction Research Congress 2016. Reston, VA: ASCE. https://doi.org/10.1061/9780784479827.059.
Serag, E., A. Oloufa, L. Malone, and E. Radwan. 2010. “Model for quantifying the impact of change orders on project cost for U.S. roadwork construction.” J. Constr. Eng. Manage. 136 (9): 1015–1027. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000206.
Shrestha, P. P., and H. Zeleke. 2018. “Effect of change orders on cost and schedule overruns of school building renovation projects.” J. Leg. Aff. Dispute Resolut. Eng. Constr. 10 (4): 04518018. https://doi.org/10.1061/(ASCE)LA.1943-4170.0000271.
Taylor, T. R. B., M. Uddin, P. M. Goodrum, and A. McCoy. 2012. “Change orders and lessons learned: Knowledge from statistical analyses of engineering change orders on Kentucky highway projects.” J. Constr. Eng. Manage. 138 (12): 1360–1369. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000550.
Information & Authors
Information
Published In
Copyright
©2020 American Society of Civil Engineers.
History
Received: Jul 21, 2019
Accepted: Mar 16, 2020
Published online: Jun 11, 2020
Published in print: Aug 1, 2020
Discussion open until: Nov 11, 2020
Authors
Metrics & Citations
Metrics
Citations
Download citation
If you have the appropriate software installed, you can download article citation data to the citation manager of your choice. Simply select your manager software from the list below and click Download.