4D-BIM Dynamic Time–Space Conflict Detection and Quantification System for Building Construction Projects

Publication: Journal of Construction Engineering and Management
Volume 144, Issue 7

Abstract

Workspace in construction projects is considered a resource and a constraint that needs to be addressed in project scheduling. Without proper workspace planning, time–space conflicts frequently may occur at construction sites. In this study, a novel four-dimensional building information modeling (4D-BIM) dynamic conflict detection and quantification system was developed to identify time–space conflicts and quantify their impacts on project performance. Using the proposed approach, the conflict between different activities workspaces was identified considering the labor crew movement in the assigned workspace during different time intervals. For this purpose, four distinct execution patterns were defined, which in combination with four starting positions, led to 16 execution alternatives. The conflict’s severity was then calculated through the quantitative assessment of its effects on labor productivity. To evaluate the performance of the proposed approach, it was implemented on a building project. The time–space conflicts were detected and quantified using the proposed approach. Finally, a what-if analysis was performed to select the optimum execution scenario with the minimum number of time–space conflicts. Using the proposed approach, conflict detection can be performed more accurately, and a more precise value for conflict severity is achieved.

Get full access to this article

View all available purchase options and get full access to this article.

Data Availability Statement

Data generated or analyzed during the study are available from the corresponding author by request. Information about the Journal’s data sharing policy can be found here: http://ascelibrary.org/doi/10.1061/%28ASCE%29CO.1943-7862.0001263.

References

Akinci, B., M. Fischer, and J. Kunz. 2002a. “Automated generation of work spaces required by construction activities.” J. Constr. Eng. Manage. 128 (4): 306–315. https://doi.org/10.1061/(ASCE)0733-9364(2002)128:4(306).
Akinci, B., M. Fischer, J. Kunz, and R. Levitt. 2002b. “Representing work spaces generically in construction method models.” J. Constr. Eng. Manage. 128 (4): 296–305. https://doi.org/10.1061/(ASCE)0733-9364(2002)128:4(296).
Akinci, B., M. Fischer, R. Levitt, and R. Carlson. 2002c. “Formalization and automation of time-space conflict analysis.” J. Comput. Civ. Eng. 16 (2): 124–134. https://doi.org/10.1061/(ASCE)0887-3801(2002)16:2(124).
Chavada, R., N. Dawood, and M. Kassem. 2012. “Construction workspace management: The development and application of a novel nD planning approach and tool.” J. Inf. Technol. Constr. 17: 213–236.
Choi, B., H. Lee, M. Park, Y. Cho, and H. Kim. 2014. “Framework for work-space planning using four-dimensional BIM in construction projects.” J. Constr. Eng. Manage. 140 (9): 04014041. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000885,9(140).
Chua, D., K. Yeoh, and Y. Song. 2010. “Quantification of spatial temporal congestion in four-dimensional computer-aided design.” J. Constr. Eng. Manage. 136 (6): 641–649. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000166.
Dawood, N., and Z. Mallasi. 2006. “Construction workspace planning: Assignment and analysis utilizing 4D visualization technologies.” Comput.-Aided Civ. Infrastruct. Eng. 21 (7): 498–513. https://doi.org/10.1111/j.1467-8667.2006.00454.x.
Eastman, C., P. Teicholz, R. Sacks, and K. Liston. 2011. BIM handbook: A guide to building information modeling for owners, managers, designers, engineers and contractors. 2nd ed. Hoboken, NJ: Wiley.
Gunduz, M. 2004. “A quantitative approach for evaluation of negative impact of overmanning on electrical and mechanical projects.” Build. Environ. 39 (5): 581–587. https://doi.org/10.1016/j.buildenv.2003.11.006.
Guo, S. J. 2002. “Identification and resolution of work space conflicts in building construction.” J. Constr. Eng. Manage. 128 (4): 287–295. https://doi.org/10.1061/(ASCE)0733-9364(2002)128:4(287).
Horner, R. M. W., and B. T. Talhouni. 1995. Effects of accelerated working, delays and disruption on labour productivity. Bracknell, UK: The Chartered Institute of Building.
Kaming, P. F., P. O. Olomolaiye, G. D. Holt, and F. C. Harris. 1997. “Factors influencing craftsmen’s productivity in Indonesia.” Int. J. Project Manage. 15 (1): 21–30. https://doi.org/10.1016/S0263-7863(96)00019-1.
Kassem, M., N. Dawood, and R. Chavada. 2015. “Construction workspace management within an Industry Foundation Class-compliant 4D tool.” Autom. Constr. 52: 42–58. https://doi.org/10.1016/j.autcon.2015.02.008.
Koo, B., and M. Fischer. 2000. “Feasibility study of 4D CAD in commercial construction.” J. Constr. Eng. Manage. 126 (4): 251–260. https://doi.org/10.1061/(ASCE)0733-9364(2000)126:4(251).
Ma, Z., Q. Shen, and J. Zhang. 2005. “Application of 4D for dynamic site layout and management of construction projects.” Autom. Constr. 14 (3): 369–381. https://doi.org/10.1016/j.autcon.2004.08.011.
Mallasi, Z. 2006. “Dynamic quantification and analysis of the construction workspace congestion utilising 4D visualisation.” Autom. Constr. 15 (5): 640–655. https://doi.org/10.1016/j.autcon.2005.08.005.
Mallasi, Z., and N. Dawood. 2001. “Assessing space criticality in sequencing and identifying execution patterns for construction activities using VR visualisations.” In Proc., ARCOM Doctoral Research Workshop: Simulation and Modelling in Construction, 22–27. Edinburgh, Scotland: Edinburgh Univ.
McKinney, K., and M. Fischer. 1998. “Generating, evaluating and visualizing construction schedules with CAD tools.” Autom. Constr. 7 (6): 433–447. https://doi.org/10.1016/S0926-5805(98)00053-3.
Moon, H., N. Dawood, and L. Kang. 2014a. “Development of workspace conflict visualization system using 4D object of work schedule.” Adv. Eng. Inf. 28 (1): 50–65. https://doi.org/10.1016/j.aei.2013.12.001.
Moon, H., H. Kim, C. Kim, and L. Kang. 2014b. “Development of a schedule-workspace interference management system simultaneously considering the overlap level of parallel schedules and workspaces.” Autom. Constr. 39 (1): 93–105. https://doi.org/10.1016/j.autcon.2013.06.001.
Project Management Institute. 2013. A guide to the project management body of knowledge (PMBOK® guide). 5th ed. Newtown Square, PA: Project Management Institute.
Riley, D. R., and V. E. Sanvido. 1995. “Patterns of construction-space use in multistory buildings.” J. Constr. Eng. Manage. 121 (4): 464–473. https://doi.org/10.1061/(ASCE)0733-9364(1995)121:4(464).
Riley, D. R., and V. E. Sanvido. 1997. “Space planning method for multistory building construction.” J. Constr. Eng. Manage. 123 (2): 171–180. https://doi.org/10.1061/(ASCE)0733-9364(1997)123:2(171).
Sanders, S. R., and H. R. Thomas. 1991. “Factors affecting masonry-labor productivity.” J. Constr. Eng. Manage. 117 (4): 626–644. https://doi.org/10.1061/(ASCE)0733-9364(1991)117:4(626).
Smith, D. M. 1987. “An investigation of the space constraint problem in construction planning.” Blacksburg, VA: Virginia Polytechnic Institute and State Univ.
Su, X., and H. Cai. 2014. “Life cycle approach to construction workspace modeling and planning.” J. Constr. Eng. Manage. 7 (7): 04014019. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000855.
Thabet, W. Y., and Y. J. Beliveau. 1994. “Modeling work space to schedule repetitive floors in multistory building.” J. Constr. Eng. Manage. 120 (1): 96–116. https://doi.org/10.1061/(ASCE)0733-9364(1994)120:1(96).
Thomas, H. R., and D. R. Riley. 2006. “Fundamental principles for avoiding congested work areas: A case study.” Pract. Period. Struct. Des. Constr. 11 (4): 197–205. https://doi.org/10.1061/(ASCE)1084-0680(2006)11:4(197).
Thomas, H. R., Jr., and G. R. Smith. 1990. Loss of construction labor productivity due to inefficiencies and disruptions: The weight of expert opinion. State College, PA: Pennsylvania State Univ.
Tommelein, I. D., R. J. Dzeng, and P. P. Zouein. 1993. “Exchanging layout and schedule data in a real-time distributed environment.” In Proc., 5th Int. Conf. on Computing in Civil and Building Engineering, 947–954. Reston, VA: ASCE.
Wang, H. J., J. P. Zhang, K. W. Chau, and M. Anson. 2004. “4D dynamic management for construction planning and resource utilization.” Autom. Constr. 13 (5): 575–589. https://doi.org/10.1016/j.autcon.2004.04.003.
Winch, G., and S. North. 2006. “Critical space analysis.” J. Constr. Eng. Manage. 132 (5): 473–481. https://doi.org/10.1061/(ASCE)0733-9364(2006)132:5(473).
Wu, I., and Y. Chiu. 2010. “4D workspace conflict detection and analysis system.” In Proc., 10th Int. Conf. on Construction Applications of Virtual Reality. Middlesbrough, UK: Teesside Univ.

Information & Authors

Information

Published In

Go to Journal of Construction Engineering and Management
Journal of Construction Engineering and Management
Volume 144Issue 7July 2018

History

Received: Aug 15, 2017
Accepted: Dec 18, 2017
Published online: Apr 30, 2018
Published in print: Jul 1, 2018
Discussion open until: Sep 30, 2018

Permissions

Request permissions for this article.

Authors

Affiliations

Ali Mirzaei [email protected]
Dept. of Project and Construction Management, Faculty of Architecture, College of Fine Arts, Univ. of Tehran, P.O. BOX 14395-515, 16 Azar St., Enghelab Square, 1417466191 Tehran, Iran. Email: [email protected]
Farnad Nasirzadeh [email protected]
Senior Lecturer, School of Architecture and Built Environment, Deakin Univ., Geelong, VIC 3220, Australia. Email: [email protected]
Majid Parchami Jalal [email protected]
Assistant Professor, Dept. of Project and Construction Management, Faculty of Architecture, College of Fine Arts, Univ. of Tehran, P.O. BOX 14395-515, 16 Azar St., Enghelab Square, 1417466191 Tehran, Iran (corresponding author). Email: [email protected]
Yasin Zamani [email protected]
Ph.D. Candidate, Dept. of Artificial Intelligence, Faculty of Computer Engineering, Sharif Univ., P.O. Box: 11155-9517, Azadi Ave., 1458889694 Tehran, Iran. Email: [email protected]

Metrics & Citations

Metrics

Citations

Download citation

If you have the appropriate software installed, you can download article citation data to the citation manager of your choice. Simply select your manager software from the list below and click Download.

Cited by

View Options

Get Access

Access content

Please select your options to get access

Log in/Register Log in via your institution (Shibboleth)
ASCE Members: Please log in to see member pricing

Purchase

Save for later Information on ASCE Library Cards
ASCE Library Cards let you download journal articles, proceedings papers, and available book chapters across the entire ASCE Library platform. ASCE Library Cards remain active for 24 months or until all downloads are used. Note: This content will be debited as one download at time of checkout.

Terms of Use: ASCE Library Cards are for individual, personal use only. Reselling, republishing, or forwarding the materials to libraries or reading rooms is prohibited.
ASCE Library Card (5 downloads)
$105.00
Add to cart
ASCE Library Card (20 downloads)
$280.00
Add to cart
Buy Single Article
$35.00
Add to cart

Get Access

Access content

Please select your options to get access

Log in/Register Log in via your institution (Shibboleth)
ASCE Members: Please log in to see member pricing

Purchase

Save for later Information on ASCE Library Cards
ASCE Library Cards let you download journal articles, proceedings papers, and available book chapters across the entire ASCE Library platform. ASCE Library Cards remain active for 24 months or until all downloads are used. Note: This content will be debited as one download at time of checkout.

Terms of Use: ASCE Library Cards are for individual, personal use only. Reselling, republishing, or forwarding the materials to libraries or reading rooms is prohibited.
ASCE Library Card (5 downloads)
$105.00
Add to cart
ASCE Library Card (20 downloads)
$280.00
Add to cart
Buy Single Article
$35.00
Add to cart

Media

Figures

Other

Tables

Share

Share

Copy the content Link

Share with email

Email a colleague

Share