Estimating Cumulative Damages due to Disruptions in Repetitive Construction

Publication: Journal of Construction Engineering and Management
Volume 142, Issue 11

Abstract

Disruption to continuous workflow is a major cause of cost overruns affecting many construction projects, especially for repetitive construction. The compensatory claims for damages including disruption are different from damages due to delay because of the complex characteristics of disruption per se. To estimate the cumulative damages due to disruptions, all the possible issues of damages caused by interruption of workflow should be considered. Various methods have been proposed in the literature for analyzing the impact on schedules and the damages resulting from disruptions. However, these methods have a limitation because they do not consider the ripple effect of disruptions. This paper proposes a modified method that can reasonably estimate damages caused by disruptions in construction projects, especially for repetitive construction. The proposed method includes the resource continuity and earned value analysis research methodologies to forecast the direct effect of disruptions. In addition, earned value management (EVM) is utilized to demonstrate and forecast the ripple effect of disruptions on construction activities. The original contribution of the paper is summarized as (1) application of EVM to the topic of damage calculations due to changed process sequence and (2) development of a method to assess the ripple effect as well as the direct effect of disruptions on project productivity performance.

Get full access to this article

View all available purchase options and get full access to this article.

References

Ammar, M., and Elbeltagi, E. (2001). “Algorithm for determining controlling path considering resource continuity.” J. Comput. Civ. Eng., 292–298.
Arashpour, M., and Arashpour, M. (2015). “Analysis of workflow variability and its impacts on productivity and performance in construction of multistory buildings.” J. Manage. Eng., 04015006.
Arashpour, M., Wakefield, R., Blismas, N., and Lee, E. (2014). “Analysis of disruptions caused by construction fieldwork on productivity in residential projects.” J. Constr. Eng. Manage., 04013053(12).
Batselier, J., and Vanhoucke, M. (2015). “Empirical evaluation of earned value management forecasting accuracy for time and cost.” J. Constr. Eng. Manage., 05015010(13).
Cho, K., Hong, T., and Hyun, C. (2011). “Scheduling model for repetitive construction processes for high-rise buildings.” Can. J. Civ. Eng., 38(1), 36–48.
Chou, J., Chen, H., Hou, C., and Lin, C. (2010). “Visualized EVM system for assessing project performance.” Autom. Constr., 19(5), 596–607.
Cushman, R. F., and Carpenter, D. A. (1990). Proving and pricing construction claims, Wiley, New York.
El-Rayes, K., and Moselhi, O. (1998). “Resource-driven scheduling of repetitive activities.” J. Constr. Manage. Econ., 16(4), 433–446.
Gray, C., and Larson, E. (2002). Project management, McGraw-Hill, New York.
Halligan, D. W., Demsetz, L. A., and Brown, J. D. (1994). “Action-response model and loss of productivity in construction.” J. Constr. Eng. Manage., 47–64.
Hanna, A. S. (2012). “Using the earned value management system to improve electrical project control.” J. Constr. Eng. Manage., 449–457.
Harris, R. B., and Ioannou, P. G. (1998). “Scheduling projects with repeating activities.” J. Constr. Eng. Manage., 269–278.
Heravi, G., and Eslamdoost, E. (2015). “Applying artificial neural networks for measuring and predicting construction-labor productivity.” J. Constr. Eng. Manage., 04015032.
Hyari, K., and El-Rayes, K. (2006). “Optimal planning and scheduling for repetitive construction projects.” J. Manage. Eng., 11–19.
Jones, R. M. (2001). “Lost productivity: Claims for the cumulative impact of multiple change orders.” Public Contract Law J., 31(1), 1–46.
Kang, L. S., Park, I. C., and Lee, B. H. (2001). “Optimal schedule planning for multiple, repetitive construction process.” J. Constr. Eng. Manage., 382–390.
Kauffmann, P., Keating, C., and Considine, C. (2002). “Using earned value methods to substantiate change-of-scope claims.” Eng. Manage. J., 14(1), 13–20.
Kim, B., and Kim, H. (2014). “Sensitivity of earned value schedule forecasting to s-curve patterns.”J. Constr. Eng. Manage., 04014023.
Klanac, G. P., and Nelson, E. L. (2004). “Trends in construction lost productivity claims.” J. Prof. Issues Eng. Educ. Pract., 226–236.
Lee, H., Yu, J., and Kim, S. (2004). “Impact of labor factors on workflow.” J. Constr. Eng. Manage., 918–923.
Lee, J. (2015). “Calculating cumulative inefficiency using earned value management in construction projects.” Can. J. Civ. Eng., 42(4), 222–232.
Liu, J., Shahi, A., Haas, C. T., Goodrum, P., and Caldas, C. H. (2014) “Validation methodologies and their impact in construction productivity research.” J. Constr. Eng. Manage., 04014046(10).
Narbaev, T., and De Marco, A. (2014). “Combination of growth model and earned schedule to forecast project cost at completion.” J. Constr. Eng. Manage., 04013038.
Nguyen, L. D., and Ibbs, W. (2010). “Case law and variations in cumulative impact productivity claims.” J. Constr. Eng. Manage., 826–833.
Schwartzkopf, W. (1995). Calculating lost labor productivity in construction claims, Wiley, New York.
Siu, M., and Lu, M. (2011). “Scheduling simulation-based techniques for earned value management on resource-constrained schedules under delayed scenarios.” Proc., Winter Simulation Conf., WSC Foundation, 3455–3466.
Wauters, M., and Vanhoucke, M. (2015). “Study of the stability of earned value management forecasting.” J. Constr. Eng. Manage., 04014086.
Zhang, L., Pan, C., and Zou, X. (2013). “Criticality comparison between the repetitive scheduling method and the network model.” J. Constr. Eng. Manage., 06013004.

Information & Authors

Information

Published In

Go to Journal of Construction Engineering and Management
Journal of Construction Engineering and Management
Volume 142Issue 11November 2016

History

Received: Aug 13, 2015
Accepted: Mar 28, 2016
Published online: Jun 3, 2016
Published in print: Nov 1, 2016
Discussion open until: Nov 3, 2016

Permissions

Request permissions for this article.

Authors

Affiliations

Jae-Seob Lee [email protected]
Professor, Division of Architectural Engineering, Dongguk Univ.-Seoul, 30, Pildong-ro 1 gil, Jung-gu, Seoul 100-715, Korea. E-mail: [email protected]

Metrics & Citations

Metrics

Citations

Download citation

If you have the appropriate software installed, you can download article citation data to the citation manager of your choice. Simply select your manager software from the list below and click Download.

Cited by

View Options

Get Access

Access content

Please select your options to get access

Log in/Register Log in via your institution (Shibboleth)
ASCE Members: Please log in to see member pricing

Purchase

Save for later Information on ASCE Library Cards
ASCE Library Cards let you download journal articles, proceedings papers, and available book chapters across the entire ASCE Library platform. ASCE Library Cards remain active for 24 months or until all downloads are used. Note: This content will be debited as one download at time of checkout.

Terms of Use: ASCE Library Cards are for individual, personal use only. Reselling, republishing, or forwarding the materials to libraries or reading rooms is prohibited.
ASCE Library Card (5 downloads)
$105.00
Add to cart
ASCE Library Card (20 downloads)
$280.00
Add to cart
Buy Single Article
$35.00
Add to cart

Get Access

Access content

Please select your options to get access

Log in/Register Log in via your institution (Shibboleth)
ASCE Members: Please log in to see member pricing

Purchase

Save for later Information on ASCE Library Cards
ASCE Library Cards let you download journal articles, proceedings papers, and available book chapters across the entire ASCE Library platform. ASCE Library Cards remain active for 24 months or until all downloads are used. Note: This content will be debited as one download at time of checkout.

Terms of Use: ASCE Library Cards are for individual, personal use only. Reselling, republishing, or forwarding the materials to libraries or reading rooms is prohibited.
ASCE Library Card (5 downloads)
$105.00
Add to cart
ASCE Library Card (20 downloads)
$280.00
Add to cart
Buy Single Article
$35.00
Add to cart

Media

Figures

Other

Tables

Share

Share

Copy the content Link

Share with email

Email a colleague

Share