Accounting for Transport Times in Planning Off-Site Shipment of Construction Materials

Publication: Journal of Construction Engineering and Management
Volume 142, Issue 1

Abstract

Off-site transportation of construction materials is planned commonly by considering the transportation costs as the dominant decision variable. Despite the significant impact of delays in the delivery of materials on the progress of projects, there is a lack of a systematic approach to estimating the off-site transport time of materials by considering the material characteristics and logistics options. This paper uses the results of a case study to highlight the importance of accounting for off-site material transport time in the planning of an industrial megaproject where small delays in activities requiring diverse materials could significantly delay the progress of the project, leading to considerable financial loss in some cases. In addition, a framework is proposed for estimating the duration of off-site transportation in industrial megaprojects by categorizing construction materials based on their supply chain structure and accounting for the effects of the transport mode, size, and weight of consignments. The results of the case study indicate that adjusting the logistics variables based on the results of a statistical analysis on transportation monitoring data collected in the earlier stages of a project may lead to a reduced delay in off-site transportation in subsequent stages.

Get full access to this article

View all available purchase options and get full access to this article.

Acknowledgments

The authors are grateful to the Research Centre for Integrated Transport Innovation (rCITI) at the University of New South Wales for their support in conducting this research. We would also like to thank Mr. Mehdi Takabi for his expert input and comments.

References

Abd El-Razek, M. E., Bassioni, H. A., and Mobarak, A. M. (2008). “Causes of delay in building construction projects in Egypt.” J. Constr. Eng. Manage., 831–841.
Ahmadian, A., Akbarnezhad, A., Rashidi, T. H., and Waller, S. T. (2014). “Importance of planning for the transport stage in procurement of construction materials.” Proc., 31th ISARC Conf., International Association for Automation & Robotics in Construction (IAARC), Bratislava, SK-Slovakia, 466–473.
Al-Momani, A. H. (2000). “Construction delay: A quantitative analysis.” Int. J. Project Manage. 18(1), 51–59.
Azambuja, M., and O’Brien, W. (2009). “Investigation of supply chain management practices in industrial projects: State of practice versus state of knowledge.” Proc., Construction Research Congress, ASCE, Reston, VA, 259–268.
Babu, A. S. (1999). “Strategies for enhancing agility of make-to-order manufacturing systems.” Int. J. Agile Manage. Syst., 1(1), 23–29.
Ceuster, G., et al. (2008). “Effects of adapting the rules on weights and dimensions of heavy commercial vehicles as established within Directive 96/53/EC.” European Commission, Belgium.
Chikan, A. (2011). “Managers’ view of a new inventory paradigm.” Int. J. Prod. Econ., 133(1), 54–59.
Christopher, M. (2000). “The agile supply chain.” Ind. Marketing Manage., 29(1), 37–44.
Davenport, T. H., and Beers, M. C. (1995). “Managing information about processes.” J. Manage. Inf. Syst., 12(1), 57–80.
Demeter, K., and Golini, R. (2014). “Inventory configurations and drivers: An international study of assembling industries.” Int. J. Prod. Econ., 157, 62–73.
Dictionary of Construction. (2013). “Long lead items.” 〈http://www.dictionaryofconstruction.com/definition/long-lead-items.html〉 (Oct. 21, 2013).
Ebrahimy, Y., Mohamed, Y., and AbouRizk, S. M. (2010). “An analytical framework for incorporating projects supply chain problems into project plan.” Proc., Construction Research Congress, ASCE, Reston, VA, 1094–1102.
Elfving, J. A., Tommelein, I. D., and Ballard, G. (2005). “Consequences of competitive bidding in project-based production.” J. Purchasing Supply Manage., 11(4), 173–181.
Fallahnejad, M. H. (2013). “Delay causes in Iran gas pipeline projects.” Int. J. Project Manage., 31(1), 136–146.
Frimpong, Y., Oluwoye, J., and Crawford, L. (2003). “Causes of delay and cost overrun in construction of ground water projects in a developing countries: Ghana as a case study.” Int. J. Project Manage., 21(5), 321–326.
Gosling, J., and Naim, M. (2009). “Engineer-to-order supply chain management: A literature review and research agenda.” Int. J. Prod. Econ., 122(2), 741–754.
Gujarati, D. (2004). Basic econometrics, part one: Single-equation regression models, 4th Ed., McGraw–Hill, New York.
Irizarry, J., Karan, E., and Jalaei, F. (2013). “Integrating BIM and GIS to improve the visual monitoring of construction supply chain management.” Autom. Constr., 31, 241–254.
Laitinen, M. (1993). “Information flows and delivery of concrete facade elements.” Confederation of Finnish Construction Industries, Helsinki, Finland.
Leesor, R. (1996). Engineer’s procurement manual for major plant equipment, Prentice Hall, Upper Saddle River, NJ.
Luskin, D. M., and Walton, C. M. (2001). “Effects of truck size and weights on highway infrastructure and operations.”, Center for Transportation Research, Univ. of Texas, Austin, TX.
O’Brien, W. J. (1998). Capacity costing approaches for construction supply-chain management, Stanford Univ., Stanford, CA.
O’Brien, W. J., Formoso, C. T., Vrijhoef, R., and London, K. A. (2008). Construction supply chain management handbook, CRC Press/Taylor & Francis Group, Boca Raton, FL.
Olhager, J. (2003). “Strategic positioning of the order penetration point.” Int. J. Prod. Econ., 85(3), 319–329.
Omar, B., and Ballal, T. (2009). “Intelligent wireless web services: Context-aware computing in construction-logistics supply chain.” Proc., 14th Int. IT Conf., International Council for Research and Innovation in Building and Construction (CIB), Delft, Netherlands, 289–308.
Rumane, A. R. (2011). Quality management in construction projects, CRC Press/Taylor and Francis Group, Boca Raton, FL, 256–259.
Ruqaishi, M., and Bashir, H. (2013). “Causes of delay in construction projects in the oil and gas industry in the Gulf Cooperation Council countries: A case study.” J. Manage. Eng., 05014017.
Said, H., and El-Rayes, K. (2011). “Optimizing material procurement and storage on construction sites.” J. Constr. Eng. Manage., 421–431.
Sambasivan, M., and Soon, Y. W. (2007). “Causes and effects of delays in Malaysian construction industry.” Int. J. Project Manage., 25(5), 517–526.
Scholman, H. S. A. (1997). “Subcontracting by main contractors.” Economic Institute for the Building Industry, Amsterdam, Netherlands.
Shakantu, W., Tookey, J. E., and Bowen, P. A. (2003). “The hidden cost of transportation of construction materials: An overview.” J. Eng. Des. Technol., 1(1), 103–118.
Tommelein, I., Ballard, G., and Kaminsky, P. (2008). “Supply chain management for lean project delivery.” 〈http://ieor.berkeley.edu/∼kaminsky/Reprints/PROOF_IT_GB_PK_08.pdf 〉 (Oct. 15, 2013).
Towill, D. R. (2009). “Construction supply chain and the time compression paradigm.” Construction supply chain management handbook, CRC Press/Taylor & Francis Group, Boca Raton, FL, 1–19.
Tserng, H. P., Yin, S. Y. L., and Li, S. (2006). “Developing a resource supply chain planning system for construction projects.” J. Constr. Eng. Manage., 393–407.
Vrijhoef, R., and Koskela, L. (1999). “Roles of supply chain management in construction.” Proc., 7th Conf. of the Int. Group for Lean Construction, Lean Construction Institute, Berkeley, CA, 133–146.
Vrijhoef, R., and Koskela, L. (2000). “The four roles of supply chain management in construction.” Eur. J. Purchasing Supply Manage., 6(3–4), 169–178.
Wegelius-Lehtonen, T. (2001). “Performance measurement in construction logistics.” Int. J. Prod. Econ., 69(1), 107–116.
Williamson, E. A., Harrison, D. K., and Jordan, M. (2004). “Information systems development within supply chain management.” Int. J. Inf. Manage., 24(5), 375–385.

Information & Authors

Information

Published In

Go to Journal of Construction Engineering and Management
Journal of Construction Engineering and Management
Volume 142Issue 1January 2016

History

Received: Nov 27, 2014
Accepted: May 12, 2015
Published online: Jul 3, 2015
Discussion open until: Dec 3, 2015
Published in print: Jan 1, 2016

Permissions

Request permissions for this article.

Authors

Affiliations

F. F. Alireza Ahmadian [email protected]
Ph.D. Candidate, School of Civil and Environmental Engineering, Univ. of New South Wales, Sydney, NSW 2052, Australia (corresponding author). E-mail: [email protected]
Ali Akbarnezhad [email protected]
Lecturer, School of Civil and Environmental Engineering, Univ. of New South Wales, Sydney, NSW 2052, Australia. E-mail: [email protected]
Taha H. Rashidi [email protected]
Lecturer, School of Civil and Environmental Engineering, Univ. of New South Wales, Sydney, NSW 2052, Australia. E-mail: [email protected]
S. Travis Waller, A.M.ASCE [email protected]
Professor and Director of the Research Centre for Integrated Transport Innovation, School of Civil and Environmental Engineering, Univ. of New South Wales, Sydney, NSW 2052, Australia. E-mail: [email protected]

Metrics & Citations

Metrics

Citations

Download citation

If you have the appropriate software installed, you can download article citation data to the citation manager of your choice. Simply select your manager software from the list below and click Download.

Cited by

View Options

Get Access

Access content

Please select your options to get access

Log in/Register Log in via your institution (Shibboleth)
ASCE Members: Please log in to see member pricing

Purchase

Save for later Information on ASCE Library Cards
ASCE Library Cards let you download journal articles, proceedings papers, and available book chapters across the entire ASCE Library platform. ASCE Library Cards remain active for 24 months or until all downloads are used. Note: This content will be debited as one download at time of checkout.

Terms of Use: ASCE Library Cards are for individual, personal use only. Reselling, republishing, or forwarding the materials to libraries or reading rooms is prohibited.
ASCE Library Card (5 downloads)
$105.00
Add to cart
ASCE Library Card (20 downloads)
$280.00
Add to cart
Buy Single Article
$35.00
Add to cart

Get Access

Access content

Please select your options to get access

Log in/Register Log in via your institution (Shibboleth)
ASCE Members: Please log in to see member pricing

Purchase

Save for later Information on ASCE Library Cards
ASCE Library Cards let you download journal articles, proceedings papers, and available book chapters across the entire ASCE Library platform. ASCE Library Cards remain active for 24 months or until all downloads are used. Note: This content will be debited as one download at time of checkout.

Terms of Use: ASCE Library Cards are for individual, personal use only. Reselling, republishing, or forwarding the materials to libraries or reading rooms is prohibited.
ASCE Library Card (5 downloads)
$105.00
Add to cart
ASCE Library Card (20 downloads)
$280.00
Add to cart
Buy Single Article
$35.00
Add to cart

Media

Figures

Other

Tables

Share

Share

Copy the content Link

Share with email

Email a colleague

Share