Transaction-Cost Approach to the Comparative Analysis of User-Pay and Government-Pay Public-Private Partnership Systems
Publication: Journal of Construction Engineering and Management
Volume 140, Issue 9
Abstract
Government-pay and user-pay public-private partnership (P3) systems have been employed as the main conduits for channelling private capital to finance the provision of public services throughout the world. In efficiency terms, they are suited to different types of projects. This paper develops a model to illuminate the condition under which one route would perform better than the other. If both of them are instituted into law, governance alignment should emerge in the long run. However, in Taiwan government-pay P3 systems are not a lawful route, forcing the government to employ user-pay P3 systems regardless of project types. This gives researchers an unusual opportunity to examine what would happen as a result of an inappropriate choice of P3 models. This paper makes a theoretical innovation in the identification of a conflict of interest indicator as an attribute for differentiating the relative efficacy of two types of P3 systems. This result sheds light on the way value for money assessment should be conducted for user-pay P3 projects.
Get full access to this article
View all available purchase options and get full access to this article.
Acknowledgments
The authors would like to thank the National Science Council, Taiwan, R.O.C., for partially funding this research under Contract No. NSC100-2628-E-324-003-MY3.
References
Arrow, K. J. (1969). “The organization of economic activity: issues pertinent to the choice of market versus nonmarket allocation.” Analysis and evaluation of public expenditure: The PPB system, U.S. Government Printing Office, Washington, DC, 59–73.
Bennett, J., and Iossa, E. (2006). “Building and managing facilities for public services.” J. Publ. Econ., 90(10–11), 2143–2160.
Bing, L., Akintoye, A., Edwards, P. J., and Hardcastle, C. (2005). “The allocation of risk in PPP/PFI construction projects in the UK.” Int. J. Project Manage., 23(1), 25–35.
Bridge, A. J., and Tisdell, C. (2004). “The determinants of the vertical boundaries of the construction firm.” Constr. Manage. Econ., 22(8), 807–825.
Chang, C. Y. (2006). “The determinants of the vertical boundaries of the construction firm: comment.” Constr. Manage. Econ., 24(3), 229–232.
Chang, C. Y. (2013a). “A critical review of the application of TCE in the interpretation of risk allocation in PPP contracts.” Constr. Manage. Econ., 31(2), 99–103.
Chang, C. Y. (2013b). “Understanding the hold-up problem in the management of megaprojects: The case of the channel tunnel rail link project.” Int. J. Project Manage., 31(4), 628–637.
Chang, C. Y., and Ive, G. (2007a). “Reversal of bargaining power in construction projects: meaning, existence and implications.” Constr. Manage. Econ., 25(8), 845–855.
Chang, C. Y., and Ive, G. (2007b). “The hold-up problem in the management of construction projects: A case study of the channel tunnel.” Int. J. Project Manage., 25(4), 394–404.
Engel, E., Fischer, R., and Galetovic, A. (2010). “The economics of infrastructure finance: Public-private partnerships versus public provision.” EIB Papers, 15(1), 40–69.
Gibbons, R. (2005). “Four formal (izable) theories of the firm?” J. Econ. Behav. Organiz., 58(2), 200–245.
Guasch, J. L., Laffont, J. J., and Straub, S. (2006). “Renegotiation of concession contracts: A theoretical approach.” Rev. Ind. Organiz., 29(1–2), 55–73.
Guasch, J. L., Laffont, J. J., and Straub, S. (2008). “Renegotiation of concession contracts in Latin America: Evidence from the water and transport sectors.” Int. J. Ind. Organiz., 26(2), 421–442.
Hart, O. (2003). “Incomplete contracts and public ownership: Remarks, and an application to public-private partnerships.” Econ. J., 113(486), C69–C76.
Hart, O., Shleifer, A., and Vishny, R. W. (1997). “The proper scope of government: Theory and an application to prisons.” Q. J. Econ., 112(4), 1119–1158.
HM Treasury. (2006). Value for money assessment guidance, Her Majesty’s Stationery Office (HMSO), London.
HM Treasury. (2012). A new approach to public private partnerships, Her Majesty’s Stationery Office (HMSO), London.
Iossa, E., and Martimort, D. (2008). The simple micro-economics of public-private partnerships, Univ. of Bristol, Bristol, U.K.
Iossa, E., and Martimort, D. (2012). “Risk allocation and the costs and benefits of public-private partnerships.” RAND J. Econ., 43(3), 442–474.
Ive, G., and Chang, C. Y. (2007). “The principle of inconsistent trinity in the selection of procurement systems.” Constr. Manage. Econ., 25(7), 677–690.
Jin, X. H. (2010). “Determinants of efficient risk allocation in privately financed public infrastructure projects in Australia.” J. Constr. Eng. Manage., 138–150.
Jin, X. H., and Doloi, H. (2008). “Interpreting risk allocation mechanism in public–private partnership projects: An empirical study in a transaction cost economics perspective.” Constr. Manage. Econ., 26(7), 707–721.
Jin, X. H., and Zhang, G. (2011). “Modelling optimal risk allocation in PPP projects using artificial neural networks.” Int. J. Project Manage., 29(5), 591–603.
Klein, B., Crawford, R. G., and Alchian, A. A. (1978). “Vertical integration, appropriable rents, and the competitive contracting process.” J. Law Econ., 21(2), 297–326.
Legislative Yuan. (2009). Proc., Yuan of Legislation, Vol. 99, Yuan of Legislation, Taipei, Taiwan, 312–315.
Legislative Yuan. (2012a)., Taipei, Taiwan.
Legislative Yuan. (2012b). The Legislative Yuan Gazette, Vol. 101, Taipei, Taiwan, 342–345.
Li, H., Arditi, D., and Wang, Z. (2012). “Transaction-related issues and construction project performance.” Constr. Manage. Econ., 30(2), 151–164.
Martimort, D., and Pouyet, J. (2008). “To build or not to build: Normative and positive theories of public-private partnerships.” Int. J. Ind. Organiz., 26(2), 393–411.
Milgrom, P. R., and Roberts, J. (1992). Economics, organization and management, Prentice-Hall International, New Jersey.
Reve, T., and Levitt, R. E. (1984). “Organization and governance in construction.” Int. J. Project Manage., 2(1), 17–25.
Turner, J. R. (2004). “Farsighted project contract management: incomplete in its entirety.” Constr. Manage. Econ., 22(1), 75–83.
Williamson, O. E. (1985). The economic institutions of capitalism, The Free Press, New York.
Williamson, O. E. (1991). “Comparative economic organization: The analysis of discrete structural alternatives.” Administrative Sci. Q., 36(2), 269–296.
Williamson, O. E. (1996). The mechanisms of governance, Oxford University Press, New York.
Winch, G. (1989). “The construction firm and the construction project: a transaction cost approach.” Constr. Manage. Econ., 7(4), 331–345.
Winch, G. M. (2001). “Governing the project process: A conceptual framework.” Constr. Manage. Econ., 19(8), 799–808.
Information & Authors
Information
Published In
Copyright
© 2014 American Society of Civil Engineers.
History
Received: Oct 17, 2013
Accepted: Apr 17, 2014
Published online: Jul 8, 2014
Published in print: Sep 1, 2014
Discussion open until: Dec 8, 2014
Authors
Metrics & Citations
Metrics
Citations
Download citation
If you have the appropriate software installed, you can download article citation data to the citation manager of your choice. Simply select your manager software from the list below and click Download.